Egerer v. CSR WEST, LLC

67 P.3d 1128
CourtCourt of Appeals of Washington
DecidedApril 21, 2003
Docket49955-6-I
StatusPublished
Cited by15 cases

This text of 67 P.3d 1128 (Egerer v. CSR WEST, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Egerer v. CSR WEST, LLC, 67 P.3d 1128 (Wash. Ct. App. 2003).

Opinion

67 P.3d 1128 (2003)
116 Wash.App. 645

Robert EGERER, Respondent/Cross-Appellant,
v.
CSR WEST, LLC, d/b/a CSR Assoc., Appellant/Cross-Respondent.

No. 49955-6-I.

Court of Appeals of Washington, Division 1.

April 21, 2003.

*1130 Robert Leach, Everett, WA, for Appellant.

Ralph Phillips, William Weber, Woodinville, WA, for Respondent.

*1129 BECKER, C.J.

Appellant CSR West breached a contract to supply fill for land development. Issues on appeal include the calculation of damages based on "hypothetical cover"; the allowance of prejudgment interest; and the denial of the plaintiff's requests to include sales tax and consequential damages in the award of damages. We affirm in all respects.

MEASURE OF DAMAGES

According to unchallenged findings of fact entered after a bench trial, Robert Egerer owned a 10 acre parcel of land in Skagit County that he planned to develop into commercial property. The property required a considerable amount of fill to make it suitable for development.

Egerer first purchased fill material in 1995, when he contracted at the rate of $1.10 per cubic yard to have Wilder Construction haul to his property some material being excavated from the shoulders of Interstate 5 as a part of a highway improvement project. In its suitability to serve as structural fill, the shoulder material resembled a gravel known as "pit run", but it was cheaper than pit run because it contained asphalt grindings.

Beyond what Wilder Construction could supply, Egerer needed roughly 17,000 cubic yards of fill material. In May 1997, Egerer learned that CSR West had contracted with the Washington State Department of Transportation to excavate material from the shoulder areas of Interstate 5 near Lake Samish. He met with John Grisham, CSR's sales manager, and they reached an agreement to have CSR transport "all" the shoulder excavations from the project to Egerer's site at the rate of $.50 per cubic yard.

CSR brought fill material to Egerer's property on only two nights: July 9 and 10, 1997. Shortly thereafter, the Department of Transportation issued a change order that allowed CSR to use the excavated shoulder material in the reconstruction of the shoulder area. It was more profitable for CSR to supply the material for the State's use than to fulfill its contract with Egerer. CSR excavated a total of 16,750 cubic yards of material during its work on the shoulder project in 1997, and supplied virtually all of it to the Department of Transportation.

Egerer did not purchase replacement fill at the time of the breach in July 1997. Asked about this at trial, he explained that it would have been too expensive, and he also did not think there was time to find replacement fill and get it onto his property before the end of the summer. Egerer said that his window of opportunity to place fill on the property was June through September, before the weather became too wet. In January and February 1998, he obtained price quotes for pit run ranging from $8.25 per cubic yard to $9.00 per cubic yard. These prices exceeded Egerer's budget, and he did not contract for replacement fill at that time either.

In the summer of 1999, Egerer learned of an unexpected landslide at a gravel pit not far from his property. The company agreed to sell Egerer the unwanted slide material at *1131 a cost of $6.39 per cubic yard, including the cost of hauling and spreading.

Egerer filed suit in November 2000, alleging that CSR breached its contract by failing to deliver all the excavated shoulder material in the summer of 1997. After a bench trial, the court found breach. The court then turned to the Uniform Commercial Code to determine the measure of damages. CSR raises several legal issues with respect to the award of damages.

The findings, which are unchallenged, are deemed verities on appeal. We review conclusions of law de novo to see if they are supported by the trial court's findings of fact. Bingham v. Lechner, 111 Wash.App. 118, 127, 45 P.3d 562 (2002).

Where a seller fails to make delivery of goods sold to a buyer, the buyer has two alternative remedies under the Uniform Commercial Code. One is the remedy of "cover": the buyer may purchase substitute goods and recover as damages the difference between the cost of this cover and the contract price, provided the buyer covers in good faith and without unreasonable delay. RCW 62A.2-712. The other, a complete alternative, is damages for non-delivery, also known as "hypothetical cover"[1]: the buyer may recover as damages from the seller "the difference between the market price at the time when the buyer learned of the breach and the contract price". RCW 62A.2-713. This measure applies only when and to the extent that the buyer does not cover. Uniform Commercial Code Comment 5, RCWA 62A.2-713. "The general baseline adopted in this section uses as a yardstick the market in which the buyer would have obtained cover had he sought that relief." U.C.C. Comment 1, RCWA 62A.2-713. "The market or current price to be used in comparison with the contract price under this section is the price for goods of the same kind and in the same branch of trade." U.C.C. Comment 2, RCWA 62A.2-713.

The court determined that Egerer was limited to damages for non-delivery under section 2-713: "Mr. Egerer is limited to damages reflecting the difference between CSR contract price and the price he could have obtained replacement material for at the time of the breach in 1997. See RCW 62A.2-713(1) and Comment 3."[2] The court found that Egerer could have obtained replacement material at the time of the breach for a cost of $8.25 per cubic yard—a price quoted to Egerer in early 1998. The court calculated his damages for the non-delivery of fill to be $129,812.50, which was the difference between the market price of $8.25 per cubic yard and the contract price of $.50 per cubic yard.

CSR accepts the trial court's decision to apply the remedy furnished by section 2-713, but contends the court erred by calculating damages based on a market price of $8.25 per cubic yard for pit run. CSR argues that $8.25 was not "the price for goods of the same kind" (as U.C.C. Comment 2 calls for) because pit run is a product superior to shoulder excavations containing asphalt grindings. CSR further argues that $8.25 was not "the market price at the time when the buyer learned of the breach" (as section 2-713 calls for) because the breach was in July 1997 and the $8.25 price was as of six months later—in January, 1998. CSR takes the position that the trial court should instead have used the $1.10 per cubic yard price reflected in Egerer's 1995 contract with Wilder Construction, because that was the only evidence in the record of a price for shoulder excavations. Use of the much higher price for pit run resulted in a windfall for Egerer, according to CSR.

The trial court expressly relied on Comment 3 to U.C.C. 2 713 in determining that $8.25 per cubic yard was the price for which Egerer could have obtained replacement material at the time of the breach.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Moraglis, S.a., V. Colorado Tire Corporation
Court of Appeals of Washington, 2022
Arzola v. Name Intelligence, Inc.
355 P.3d 286 (Court of Appeals of Washington, 2015)
Kassa Ins. Services v. Ryan Pugh, et ux
Court of Appeals of Washington, 2014
Rekhter v. Dep't of Soc. & Health Servs.
Washington Supreme Court, 2014
Rekhter v. Department of Social & Health Services
323 P.3d 1036 (Washington Supreme Court, 2014)
Polygon Northwest Co. v. American Nat. Fire Ins. Co.
189 P.3d 777 (Court of Appeals of Washington, 2008)
Polygon Northwest Co. v. American National Fire Insurance
143 Wash. App. 753 (Court of Appeals of Washington, 2008)
Department of Corrections v. Fluor Daniel, Inc.
160 Wash. 2d 786 (Washington Supreme Court, 2007)
STATE DEPT. OF CORRECTIONS v. Fluor Daniel, Inc.
161 P.3d 372 (Washington Supreme Court, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
67 P.3d 1128, Counsel Stack Legal Research, https://law.counselstack.com/opinion/egerer-v-csr-west-llc-washctapp-2003.