Reecer Creek Excavating, LLC v. SRI-Rochlin Construction JV, LLC

CourtCourt of Appeals of Washington
DecidedOctober 14, 2025
Docket40486-2
StatusPublished

This text of Reecer Creek Excavating, LLC v. SRI-Rochlin Construction JV, LLC (Reecer Creek Excavating, LLC v. SRI-Rochlin Construction JV, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reecer Creek Excavating, LLC v. SRI-Rochlin Construction JV, LLC, (Wash. Ct. App. 2025).

Opinion

FILED OCTOBER 14, 2025 In the Office of the Clerk of Court WA State Court of Appeals, Division III

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON DIVISION THREE

REECER CREEK EXCAVATING, LLC, ) No. 40486-2-III a Washington Limited Liability Company, ) ) Appellant, ) ) v. ) ) PUBLISHED OPINION SRI-ROCHLIN CONSTRUCTION JV, ) LLC, a Washington Limited Liability ) Company, JAMES ROCHLIN, an ) individual, ) ) Respondent. )

LAWRENCE-BERREY, C.J. — Reecer Creek Excavating, LLC appeals the trial

court’s denial of its motion to modify/vacate the arbitration award. It argues the trial

court erred because the arbitrator exceeded its authority when awarding SRI-Rochlin

Construction JV, LLC consequential damages and denying it, Reecer Creek, an award of

reasonable attorney fees for prevailing at arbitration.

We agree with Reecer Creek that the parties’ agreement did not permit the

arbitrator to award SRI consequential damages. But we mostly disagree that the

arbitrator’s offset award to SRI consisted of consequential damages. We also agree with No. 40486-2-III Reecer Creek Excavating v. SRI-Rochlin Constr.

Reecer Creek that the order referring the dispute to arbitration required the arbitrator to

award the prevailing party its reasonable attorney fees. But where both parties prevail on

major claims, as happened here, it is proper to order parties to bear their own fees and

costs. We generally affirm the trial court and award SRI its reasonable attorney fees on

appeal.

FACTS

Background 1

SRI is a contractor that oversaw the construction of a housing project in

Ellensburg, Washington. In March 2020, SRI entered into a subcontract agreement with

Reecer Creek. Reecer Creek was responsible for excavation, removal of various debris,

paving, concrete work, and other services in connection with the housing project. The

subcontract provided a completion date of April 28, 2021. After the execution of the

agreement, the parties agreed that all additional work would be completed on a time and

materials basis, with requests for change order work requiring written approval.

Shortly after Reecer Creek began working, the COVID-19 pandemic interrupted

progress on the project for three weeks. Following the brief pause, Reecer Creek’s

1 The facts come from the arbitrator’s detailed award. The choice to provide reasoned awards makes them subject to collateral challenges. We, nevertheless, encourage arbitrators to provide reasoned awards. Parties should understand why they won or lost, and courts are apt to respect reasoned awards.

2 No. 40486-2-III Reecer Creek Excavating v. SRI-Rochlin Constr.

excavation work continued with minimal disruption. In October 2020, SRI’s

construction manager, James Rochlin, expressed concern to Reecer Creek that the

excavation work was moving too slow. Mr. Rochlin was worried that the winter weather

would prolong excavation and make it difficult, if not impossible, to complete asphalt

paving by the deadline.

In May 2021, Reecer Creek submitted “Application #15” for its work completed

through April. Clerk’s Papers (CP) at 77. SRI paid the $181,207.67 invoice in full.

However, at that time, Mr. Rochlin questioned Reecer Creek about the pay applications

and the change order work being billed.

In July 2021, Reecer Creek stopped working after SRI failed to pay “Application

#16” in the amount of $90,272.55. CP at 78. This application was exclusively for

change order work. After Reecer Creek stopped working, SRI finished a portion of the

project with its own employees and hired other subcontractors for the remaining work.

Reecer Creek filed a lien against the property for $201,831.98, which consisted of

$90,272.55 for Application #16 and retainage amounts totaling $111,559.43 for the prior

pay applications.

Reecer Creek sued SRI for breach of contract. Soon after, the parties entered a

stipulated order for private arbitration. The order provided that (1) the arbitration would

be subject to the mandatory arbitration rules of Kittitas County, except that the $50,000

3 No. 40486-2-III Reecer Creek Excavating v. SRI-Rochlin Constr.

jurisdictional limit would be waived, (2) the prevailing party shall be entitled to

reasonable attorney fees and costs, and (3) the arbitration award would be final with no

right to appeal “under MAR,” except to challenge that the arbitrator exceeded its

authority. CP at 73.

At the arbitration, both parties advanced claims for breach of contract.

The arbitrator determined that Reecer Creek breached the subcontract by not

completing its work by April 28, 2021, by overbilling for survey work, and by

installing a fire suppression system without being properly licensed to do so. The

arbitrator also determined that SRI breached the subcontract by withholding payment for

Application #16. The arbitrator awarded Reecer Creek its requested retention amount of

$111,559.43 and $79,330.10 for Application #16. The unadjusted award to Reecer Creek

thus totaled $190,889.53.

The arbitrator offset Reecer Creek’s award by $135,731.50. The offset was based

on (1) $58,669.75 for bonding around liens and for costs to complete the contract above

the budgeted amount, (2) $54,430.00 for repairing work not done properly by Reecer

Creek, and (3) $22,632.75 for Reecer Creek’s unnecessary survey work. In addition, the

arbitrator ordered Reecer Creek to defend, indemnify, and hold SRI harmless for future

claims against SRI for injuries or damages arising from the failure of the fire suppression

system. Subject to this contingent loss, the net arbitration award was $55,158.03 to

4 No. 40486-2-III Reecer Creek Excavating v. SRI-Rochlin Constr.

Reecer Creek. The arbitrator determined that each party should bear their respective

attorney fees and costs.

Reecer Creek challenged the arbitration award in superior court. It argued the

arbitrator exceeded its authority by awarding SRI consequential damages and by denying

it, Reecer Creek, its reasonable attorney fees and costs. The trial court denied Reecer

Creek’s challenge, and Reecer Creek timely appealed to this court.

ANALYSIS

A. SRI’S OFFSET AWARD

Citing § 6.4 of the subcontract, Reecer Creek argues the arbitrator exceeded its

authority by offsetting Reecer Creek’s award by SRI’s consequential damages. We

address the arbitrator’s authority as authorized by the parties’ contract and then address

whether the arbitrator exceeded its authority.

An arbitrator’s authority derives from the parties’ agreement to arbitrate. Agnew

v. Lacey Co-Ply, 33 Wn. App. 283, 287, 654 P.2d 712 (1982). Because of this, an

arbitrator’s authority may sometimes be limited:

“[a]n agreement for the submission of a dispute to arbitration defines and limits the issues to be decided. The authority of the arbitrator is wholly dependent upon the terms of the agreement of submission. The arbitration award must concern only those matters included within the agreement for submission and must not exceed the powers established by the submission.”

5 No. 40486-2-III Reecer Creek Excavating v. SRI-Rochlin Constr.

ACF Prop. Mgmt. Inc. v. Chaussee, 69 Wn. App. 913, 919, 850 P.2d 1387 (1993)

(quoting Sullivan v. Great Am. Ins. Co., 23 Wn. App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

London v. City of Seattle
611 P.2d 781 (Washington Supreme Court, 1980)
ACF Property Management, Inc. v. Chaussee
850 P.2d 1387 (Court of Appeals of Washington, 1993)
Agnew v. Lacey Co-Ply
654 P.2d 712 (Court of Appeals of Washington, 1982)
Sullivan v. Great American Insurance
594 P.2d 454 (Court of Appeals of Washington, 1979)
Riss v. Angel
934 P.2d 669 (Washington Supreme Court, 1997)
Wright v. DAVE JOHNSON INS. INC.
275 P.3d 339 (Court of Appeals of Washington, 2012)
Park Avenue Condominium Owners Ass'n v. Buchan Developments, LLC
71 P.3d 692 (Court of Appeals of Washington, 2003)
Egerer v. CSR WEST, LLC
67 P.3d 1128 (Court of Appeals of Washington, 2003)
In Re Marriage of Bernard
204 P.3d 907 (Washington Supreme Court, 2009)
Riss v. Angel
131 Wash. 2d 612 (Washington Supreme Court, 1997)
In re the Marriage of Bernard
165 Wash. 2d 895 (Washington Supreme Court, 2009)
Saleemi v. Doctor's Associates, Inc.
292 P.3d 108 (Washington Supreme Court, 2013)
Egerer v. CSR West, L.L.C.
116 Wash. App. 645 (Court of Appeals of Washington, 2003)
Park Avenue Condominium Owners Ass'n v. Buchan Developments, L.L.C.
117 Wash. App. 369 (Court of Appeals of Washington, 2003)
Saleemi v. Doctor's Associates, Inc.
269 P.3d 350 (Court of Appeals of Washington, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Reecer Creek Excavating, LLC v. SRI-Rochlin Construction JV, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reecer-creek-excavating-llc-v-sri-rochlin-construction-jv-llc-washctapp-2025.