Reecer Creek Excavating, LLC v. SRI-Rochlin Construction JV, LLC
Opinion
FILED
OCTOBER 14, 2025
In the Office of the Clerk of Court WA State Court of Appeals, Division III
IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON DIVISION THREE
REECER CREEK EXCAVATING, LLC, ) No. 40486-2-III a Washington Limited Liability Company, )
)
Appellant, )
)
v. )
) PUBLISHED OPINION SRI-ROCHLIN CONSTRUCTION JV, ) LLC, a Washington Limited Liability ) Company, JAMES ROCHLIN, an ) individual, )
)
Respondent. )
LAWRENCE-BERREY, C.J. — Reecer Creek Excavating, LLC appeals the trial court’s denial of its motion to modify/vacate the arbitration award. It argues the trial court erred because the arbitrator exceeded its authority when awarding SRI-Rochlin Construction JV, LLC consequential damages and denying it, Reecer Creek, an award of reasonable attorney fees for prevailing at arbitration.
We agree with Reecer Creek that the parties’ agreement did not permit the arbitrator to award SRI consequential damages. But we mostly disagree that the arbitrator’s offset award to SRI consisted of consequential damages. We also agree with
Reecer Creek Excavating v. SRI-Rochlin Constr.
Reecer Creek that the order referring the dispute to arbitration required the arbitrator to award the prevailing party its reasonable attorney fees. But where both parties prevail on major claims, as happened here, it is proper to order parties to bear their own fees and costs. We generally affirm the trial court and award SRI its reasonable attorney fees on appeal.
FACTS
Background 1 SRI is a contractor that oversaw the construction of a housing project in Ellensburg, Washington. In March 2020, SRI entered into a subcontract agreement with Reecer Creek. Reecer Creek was responsible for excavation, removal of various debris, paving, concrete work, and other services in connection with the housing project. The subcontract provided a completion date of April 28, 2021. After the execution of the agreement, the parties agreed that all additional work would be completed on a time and materials basis, with requests for change order work requiring written approval.
Shortly after Reecer Creek began working, the COVID-19 pandemic interrupted progress on the project for three weeks. Following the brief pause, Reecer Creek’s
1 The facts come from the arbitrator’s detailed award. The choice to provide reasoned awards makes them subject to collateral challenges. We, nevertheless, encourage arbitrators to provide reasoned awards. Parties should understand why they won or lost, and courts are apt to respect reasoned awards.
Reecer Creek Excavating v. SRI-Rochlin Constr.
excavation work continued with minimal disruption. In October 2020, SRI’s construction manager, James Rochlin, expressed concern to Reecer Creek that the excavation work was moving too slow. Mr. Rochlin was worried that the winter weather would prolong excavation and make it difficult, if not impossible, to complete asphalt paving by the deadline.
In May 2021, Reecer Creek submitted “Application #15” for its work completed through April. Clerk’s Papers (CP) at 77. SRI paid the $181,207.67 invoice in full. However, at that time, Mr. Rochlin questioned Reecer Creek about the pay applications and the change order work being billed.
In July 2021, Reecer Creek stopped working after SRI failed to pay “Application #16” in the amount of $90,272.55. CP at 78. This application was exclusively for change order work. After Reecer Creek stopped working, SRI finished a portion of the project with its own employees and hired other subcontractors for the remaining work. Reecer Creek filed a lien against the property for $201,831.98, which consisted of $90,272.55 for Application #16 and retainage amounts totaling $111,559.43 for the prior pay applications.
Reecer Creek sued SRI for breach of contract. Soon after, the parties entered a stipulated order for private arbitration. The order provided that (1) the arbitration would be subject to the mandatory arbitration rules of Kittitas County, except that the $50,000
Reecer Creek Excavating v. SRI-Rochlin Constr.
jurisdictional limit would be waived, (2) the prevailing party shall be entitled to reasonable attorney fees and costs, and (3) the arbitration award would be final with no right to appeal “under MAR,” except to challenge that the arbitrator exceeded its authority. CP at 73.
At the arbitration, both parties advanced claims for breach of contract.
The arbitrator determined that Reecer Creek breached the subcontract by not completing its work by April 28, 2021, by overbilling for survey work, and by installing a fire suppression system without being properly licensed to do so. The arbitrator also determined that SRI breached the subcontract by withholding payment for Application #16. The arbitrator awarded Reecer Creek its requested retention amount of $111,559.43 and $79,330.10 for Application #16. The unadjusted award to Reecer Creek thus totaled $190,889.53.
The arbitrator offset Reecer Creek’s award by $135,731.50. The offset was based on (1) $58,669.75 for bonding around liens and for costs to complete the contract above the budgeted amount, (2) $54,430.00 for repairing work not done properly by Reecer Creek, and (3) $22,632.75 for Reecer Creek’s unnecessary survey work. In addition, the arbitrator ordered Reecer Creek to defend, indemnify, and hold SRI harmless for future claims against SRI for injuries or damages arising from the failure of the fire suppression system. Subject to this contingent loss, the net arbitration award was $55,158.03 to
Reecer Creek Excavating v. SRI-Rochlin Constr.
Reecer Creek. The arbitrator determined that each party should bear their respective attorney fees and costs.
Reecer Creek challenged the arbitration award in superior court. It argued the arbitrator exceeded its authority by awarding SRI consequential damages and by denying it, Reecer Creek, its reasonable attorney fees and costs. The trial court denied Reecer Creek’s challenge, and Reecer Creek timely appealed to this court.
ANALYSIS
A. SRI’S OFFSET AWARD Citing § 6.4 of the subcontract, Reecer Creek argues the arbitrator exceeded its authority by offsetting Reecer Creek’s award by SRI’s consequential damages. We address the arbitrator’s authority as authorized by the parties’ contract and then address whether the arbitrator exceeded its authority.
An arbitrator’s authority derives from the parties’ agreement to arbitrate. Agnew v. Lacey Co-Ply, 33 Wn. App. 283, 287, 654 P.2d 712 (1982). Because of this, an arbitrator’s authority may sometimes be limited:
“[a]n agreement for the submission of a dispute to arbitration defines and limits the issues to be decided. The authority of the arbitrator is wholly dependent upon the terms of the agreement of submission. The arbitration award must concern only those matters included within the agreement for submission and must not exceed the powers established by the submission.”
Reecer Creek Excavating v. SRI-Rochlin Constr.
ACF Prop. Mgmt. Inc. v. Chaussee, 69 Wn. App. 913, 919, 850 P.2d 1387 (1993) (quoting Sullivan v. Great Am. Ins. Co., 23 Wn. App. 242, 246, 594 P.2d 454 (1979)).
Here, § 6.4 of the subcontract states, “The [parties] waive claims against each other for consequential damages arising out of or relating to this Subcontract.” CP at 61. We agree with the portion of Reecer Creek’s argument that the arbitrator lacked authority to award consequential damages.
We have previously defined “consequential damages” as “‘[l]osses that do not flow directly and immediately from an injurious act, but that result indirectly from the act.’” Park Ave. Condo. Owners Ass’n v. Buchan Devs., LLC, 117 Wn. App. 369, 389, 71 P.3d 692 (2003) (quoting BLACK’S LAW DICTIONARY 394 (7th ed. 1999)). Examples of consequential damages include lost profits from construction delays, London v. City of Seattle, 93 Wn.2d 657, 665, 611 P.2d 781 (1980), and lost rent from delayed completion of a construction project. Egerer v. CSR West, LLC, 116 Wn. App. 645, 657, 67 P.3d 1128 (2003).
Free access — add to your briefcase to read the full text and ask questions with AI
Reecer Creek Excavating, LLC v. SRI-Rochlin Construction JV, LLC (Reecer Creek Excavating, LLC v. SRI-Rochlin Construction JV, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.