ACF Property Management, Inc. v. Chaussee

850 P.2d 1387, 69 Wash. App. 913, 1993 Wash. App. LEXIS 224
CourtCourt of Appeals of Washington
DecidedMay 17, 1993
Docket30498-4-I
StatusPublished
Cited by26 cases

This text of 850 P.2d 1387 (ACF Property Management, Inc. v. Chaussee) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ACF Property Management, Inc. v. Chaussee, 850 P.2d 1387, 69 Wash. App. 913, 1993 Wash. App. LEXIS 224 (Wash. Ct. App. 1993).

Opinion

Webster, C.J.

Dean Chaussee, several of his family members, and the family partnership named Emerald Glen Two Associates (collectively, Chaussee) appeal the trial court's order denying their motion to confirm the arbitrators' award entered against ACF Property Management, Inc. (ACF). 1 Chaussee contends that (1) Judge Schindler erroneously interpreted the arbitration clause in the parties' agreement to limit arbitration to claims valued at $200,000 or less; (2) Judge Schindler should have confirmed the arbitrators' award because ACF failed to prove the prejudice required to vacate the award under RCW 7.04.160(4); (3) ACF waived any right it had to challenge Judge Holman's earlier ruling staying litigation pending arbitration; and (4) ACF was bound by the arbitrators' interpretation of the scope of the arbitration clause. ACF cross-appeals, arguing that Judge Holman erred by entering the order staying litigation and Judge Schindler erred by refusing to expressly vacate the arbitrators' award. We affirm.

In July 1989, ACF exercised its option to purchase Emerald Glen Two Associates, a Washington partnership owned by Chaussee. Chaussee had created the partnership in order to build an apartment complex in a 2-phased construction project. ACF's purchase involved two separate agreements, one for each phase of construction, but only the "Phase II" agreement is pertinent to this appeal.

Pursuant to that agreement, ACF paid Chaussee $150,000 and placed another $250,000 in escrow. That total amount of $400,000 was intended to serve as liquidated damages if ACF failed to purchase the property as agreed. Once the Phase II construction was complete, ACF would make an initial down payment and the parties would take various steps to close *915 the transaction. Construction would be deemed complete when, among other things, each party's architect certified that the project was substantially completed. The Phase II agreement also included an arbitration clause which read in pertinent part:

All claims and counterclaims between the parties arising out of or relating to a dispute as to the date or fact of final completion of the Improvements or any portion thereof, including disputes relating to the completion of construction according to the Plans and Specifications, will be decided by arbitration. . . . All demands for arbitration and all answering statements thereto which include any monetary claim must contain a statement that the total sum or value in controversy as alleged by the party making such demand or answering statement is not more than TWO HUNDRED THOUSAND DOLLARS ($200,000.00), exclusive of interest and costs. The arbitrators will not have jurisdiction, power or authority to consider, to make findings, except in denial of their own jurisdiction, or to render a monetary award in response to any claim against any party in excess of such amount. The arbitrators shall have no jurisdiction to hear any claim for specific performance or injunctive relief or any claim concerning the title to the Property and/or to the Improvements.

In July 1990, Chaussee's architect issued his certificate of substantial completion, but Chaussee allegedly was finable to determine from ACF whether its architects had inspected the construction project or whether they intended to issue their certificate. Consequently, on August 9, 1990, Chaussee's attorney wrote to ACF and demanded that the transaction be closed on August 20, 1990. ACF refused to close the deal, claiming that the construction was not complete and that Chaussee had repudiated the contract by the August 9 letter.

Subsequently, ACF sued Chaussee in superior court for repudiating the contract and sought repayment of the $150,000 it initially paid Chaussee, the $250,000 held in escrow, and approximately $52,000 also held in escrow for various change orders. 2 ACF also sought additional damages of more than $2 *916 million flowing from Chaussee's alleged breach of contract. Chaussee answered ACF's complaint and, pursuant to RCW 7.04.030, 3 filed a motion to stay the legal proceedings pending arbitration. ACF opposed that motion, arguing that the arbitration clause in the parties' contract limited arbitrable matters to claims of not more than $200,000.

On November 6, 1990, Judge Holman granted Chaussee's motion and entered the following findings:

2.2 Paragraph 5.3 of the Agreement contains an arbitration clause. This clause covers all claims and counterclaims relating to completion of the Improvements described in the Agreement.
2.3 Defendants contend, and plaintiffs in their memorandum in support of summary judgment admit, that the issue in the pending summary judgment motion involves claims arising out of and relating to the completion of the Improvements.
2.4 Final completion of the Improvements is an issue in this case.

Judge Holman's conclusions were as follows:

3.1 The arbitration clause in the Agreement is valid and binding on the parties.
3.2 There is an issue involved in the instant action which is referrable [sic] to arbitration under the terms of the Agreement.
3.3 The issues raised by the plaintiffs in their proceedings and their motion for summary judgment are appropriate under the Agreement for submission to arbitration.

Immediately following entry of Judge Holman's order, ACF filed a demand for arbitration. Chaussee moved for an order striking the arbitration demand because it did not comply with the requirement of the arbitration clause that

[a]ll demands for arbitration and all answering statements thereto which include any monetary claim must contain a *917 statement that the total sum or value in controversy as alleged by the party making such demand or answering statement is not more than TWO HUNDRED THOUSAND DOLLARS ($200,000.00), exclusive of interest and costs.

Chaussee alternatively requested that the court enter an order limiting ACF's damages to $200,000 if it prevailed at arbitration. Judge Dore denied Chaussee's motion and arbitration proceeded.

A panel of three arbitrators initially considered the scope of the arbitration clause. In a letter to the arbitrators, ACF objected to arbitration on the ground that the arbitration clause in the Phase II agreement limited arbitrable matters to claims not exceeding $200,000. ACF nevertheless asked the arbitrators to find that damages in the matter exceeded $200,000 and to refer the issue of damages to the superior court. 4 The arbitrators ultimately interpreted the arbitration clause as follows:

(i) the arbitrators have no jurisdiction to award damages in excess of $200,000;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

John Rouse & Karma Rouse v. Mons Terram, LLC
Court of Appeals of Washington, 2025
Newman Du Wors, V. Landmark Technology A, Llc
Court of Appeals of Washington, 2024
Magnadrive Corporation v. Magna Force, Inc.
Court of Appeals of Washington, 2014
Saleemi v. Doctor's Associates, Inc.
269 P.3d 350 (Court of Appeals of Washington, 2012)
Rimov v. Schultz
162 Wash. App. 274 (Court of Appeals of Washington, 2011)
Tacoma Narrows Constructors v. Nippon Steel-Kawada Bridge, Inc.
138 Wash. App. 203 (Court of Appeals of Washington, 2007)
Tacoma Narrows Constructors v. NSK BRIDGE, INC.
156 P.3d 293 (Court of Appeals of Washington, 2007)
Luvaas Family Farms v. Ferrell Family Farms
23 P.3d 1111 (Court of Appeals of Washington, 2001)
Stein v. Geonerco, Inc.
17 P.3d 1266 (Court of Appeals of Washington, 2001)
Kamaya Co. v. American Property Consultants, Ltd.
959 P.2d 1140 (Court of Appeals of Washington, 1998)
Price v. Farmers Insurance
133 Wash. 2d 490 (Washington Supreme Court, 1997)
Price v. Farmers Ins. Co.
946 P.2d 388 (Washington Supreme Court, 1997)
Kempf v. Puryear
942 P.2d 375 (Court of Appeals of Washington, 1997)
Davidson v. Hensen
933 P.2d 1050 (Court of Appeals of Washington, 1997)
Woodley v. Safeco Ins. Co.
929 P.2d 1150 (Court of Appeals of Washington, 1997)
Anderson v. Farmers Ins. Co. of Wash.
923 P.2d 713 (Court of Appeals of Washington, 1996)
Dayton v. Farmers Insurance Group
876 P.2d 896 (Washington Supreme Court, 1994)
Boyd v. Davis
876 P.2d 478 (Court of Appeals of Washington, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
850 P.2d 1387, 69 Wash. App. 913, 1993 Wash. App. LEXIS 224, Counsel Stack Legal Research, https://law.counselstack.com/opinion/acf-property-management-inc-v-chaussee-washctapp-1993.