Shepler Construction v. Gary And Susan Leonard

CourtCourt of Appeals of Washington
DecidedJune 3, 2013
Docket68227-0
StatusUnpublished

This text of Shepler Construction v. Gary And Susan Leonard (Shepler Construction v. Gary And Susan Leonard) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shepler Construction v. Gary And Susan Leonard, (Wash. Ct. App. 2013).

Opinion

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

SHEPLER CONSTRUCTION, INC., No. 68227-0-1 Respondent, DIVISION ONE v.

UNPUBLISHED OPINION GARY LEONARD and SUSAN KIRALY- LEONARD, and the marital community thereof,

Appellants

PHH MORTGAGE SERVICES CORPORATION, a New Jersey corporation,

Defendant. FILED: June 3, 2013

Appelwick, J. — Shepler and the Leonards appear before this court on their third

appeal in this case. In 2006, this court reversed a summary judgment order dismissing

the Leonards' construction defect counterclaims. In 2009, we held that both parties

waived arbitration, affirming the trial court's denial of the Leonards' motion to compel

arbitration. We noted that the parties did not waive their underlying claims.

^Nevgtheless, the trial court on remand barred the Leonards from asserting any

<5couj3erclaim that should have been submitted to arbitration under the contract's dispute

FACTS

In 2000, Gary Leonard and Susan Kiraly-Leonard contracted with Shepler

Construction, Inc., to build a custom home on San Juan Island.1 The fixed price contract contained a dispute resolution mechanism and a provision for Shepler to

remedy nonconforming work before final payment. Shepler made an express warranty

that work would be "substantially completed in a workmanlike manner." The contract

did not contain any disclaimer of implied warranties or any provision limiting remedies.

In 2001, a dispute arose regarding Shepler's performance and the Leonards'

payment. Shepler sent letters to the Leonards recommending that they initiate the

dispute resolution process. The Leonards admit that they did not respond to the

requests for dispute resolution of their claims.

After filing a mechanic's lien against the Leonards' property, Shepler filed suit to

enforce the lien and obtain damages for breach of contract. The Leonards filed

affirmative defenses and counterclaims, including a construction defect claim alleging

that Shepler breached the contract by failing to complete construction in a workmanlike

manner. The trial court granted Shepler's motion for summary judgment on the

Leonards' construction defect counterclaim. After holding a trial on enforcement of the

mechanic's lien, the court entered judgment and awarded attorney fees in Shepler's

favor. The Leonards appealed the dismissal of their counterclaims on summary

judgment. Leonard v. Shepler Constr.. Inc.. noted at 132 Wn. App. 1054, 2006 WL

1 The underlying facts of this case are detailed at length in this court's two previous opinions. Shepler Constr., Inc. v. Leonard, noted at 153 Wn. App 1035, 2009 WL 5153672, at *1-2; Leonard v. Shepler Constr., Inc., noted at 132 Wn. App. 1054, 2006 WL 1217216, at *1-2. We repeat only those facts necessary to this opinion. No. 68227-0-1/3

1217216, at *2. In 2006, we reversed and remanded for trial, holding that a genuine

issue of material fact existed as to whether Shepler breached its contractual obligation

to perform in a workmanlike manner. kL at *3.

In 2008, Shepler again filed for summary judgment, arguing that the Leonards'

counterclaims should be dismissed, because they breached the contract by failing to

seek arbitration. The trial court initially denied the motion. Upon Shepler's motion for

reconsideration, the trial court granted summary judgment on March 31, 2008. The

court ordered:

The Leonards are barred from bringing any claim before this court that should have been determined by submittal to binding arbitration under the contractus dispute resolution provision. All causes of actions or counterclaims relating to Shepler Construction's performance under the parties agreement, and specifically those asserting that Shepler Construction's work was not performed in accordance with the contract between the parties, applicable building codes, and in good and workmanlike manner, are therefore dismissed.

The Leonards did not directly appeal the grant of summary judgment.

On April 11, 2008, the Leonards filed a motion for reconsideration of the

summary judgment order or, alternatively, to compel arbitration. The court denied the

motion for reconsideration, finding that it was not timely. But, the court determined that

the Leonards' right to bring a timely motion to compel arbitration at a later date was

preserved. On May 21, 2008, the Leonards filed a motion to compel arbitration, which

the court denied. The Leonards appealed from that denial. Shepler Constr.. Inc. v.

Leonard, noted at 153 Wn. App 1035, 2009 WL 5153672.

On appeal before this court, Shepler argued that the Leonards waived arbitration

and were therefore estopped from invoking it. Id at *2. We held that both parties No. 68227-0-1/4

waived arbitration. Jd. at *3. Neither party initiated notice of arbitration as provided by

chapter 7.04A RCW. Id Neither party asserted a right to arbitration in their answers to

the pleadings of the other party. Jd. Both parties conducted discovery and engaged in

substantial litigation, including the prior appeal of the counterclaims. Jd Seven years

passed and substantial case development occurred before the Leonards asserted the

right to arbitrate. Jd Therefore, the trial court did not err in denying their motion to

compel arbitration. Jd

The Leonards argued in the same appeal that the trial court erred in dismissing

their counterclaims on summary judgment. Jd They did not directly appeal the March

summary judgment order, but asked that we consider it under RAP 2.4(b). Jd We

declined to do so. Jd But, we added in footnote one that "[t]he arbitration clause did

not provide that it was the exclusive remedy for breach. As noted above, the parties

waived the arbitration clause by litigating, not the underlying claims." Jd at *3 n.1.

The case was tried a second time on August 8-10, 2011. Citing footnote one of

our 2009 opinion, the Leonards requested that evidence of construction defects be

admitted at least for a recoupment or offset defense, or more broadly for the purpose of

their underlying counterclaims. Id The court recognized, "I want to make sure that I

follow The Court of Appeal's mandate, and I'm having a difficult time considering that

the footnote is a mandate." But, the court continued, "I believe that the mandate here is

exactly as [Shepler's counsel] has indicated and that is to determine ... the amount

owed under the charge orders ... but it's not to consider construction defects, and I will

so rule." No. 68227-0-1/5

Affirming the March 2008 summary judgment order, the trial court barred the

Leonards' counterclaims for construction defects. In a November 9, 2011, decision

letter, the court reiterated that the "Leonards' refusal to comply with the dispute

resolution procedure set forth in the contract waived any claim of construction defect."

(citing Absher Constr. co. v. Kent Sen. Dist. No. 415, 77 Wn. App. 137, 890 P.2d 1071

(1995)). The trial was limited to Shepler's claims for compensation and foreclosure, and

the Leonards' counterclaims for incomplete work or offsets. The court entered judgment

and awarded attorney fees and costs in Shepler's favor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brown v. Safeway Stores, Inc.
617 P.2d 704 (Washington Supreme Court, 1980)
State v. Strauss
832 P.2d 78 (Washington Supreme Court, 1992)
Detweiler v. J. C. Penney Casualty Insurance
751 P.2d 282 (Washington Supreme Court, 1988)
Franz v. Lance
836 P.2d 832 (Washington Supreme Court, 1992)
Ives v. Ramsden
174 P.3d 1231 (Court of Appeals of Washington, 2008)
Peterson v. Groves
44 P.3d 894 (Court of Appeals of Washington, 2002)
Mike M. Johnson, Inc. v. County of Spokane
78 P.3d 161 (Washington Supreme Court, 2003)
Hadley v. Maxwell
27 P.3d 600 (Washington Supreme Court, 2001)
Harting v. Barton
6 P.3d 91 (Court of Appeals of Washington, 2000)
Auburn Mechanical, Inc. v. Lydig Construction, Inc.
951 P.2d 311 (Court of Appeals of Washington, 1998)
Absher Construction Co. v. Kent School District No. 415
890 P.2d 1071 (Court of Appeals of Washington, 1995)
Otis Housing Ass'n, Inc. v. Ha
201 P.3d 309 (Washington Supreme Court, 2009)
Hadley v. Maxwell
144 Wash. 2d 306 (Washington Supreme Court, 2001)
Mike M. Johnson, Inc. v. Spokane County
150 Wash. 2d 375 (Washington Supreme Court, 2003)
Otis Housing Ass'n v. Ha
165 Wash. 2d 582 (Washington Supreme Court, 2009)
Torgerson v. One Lincoln Tower, LLC
166 Wash. 2d 510 (Washington Supreme Court, 2009)
Harting v. Barton
101 Wash. App. 954 (Court of Appeals of Washington, 2000)
Peterson v. Groves
111 Wash. App. 306 (Court of Appeals of Washington, 2002)
Graoch Associates 5 Ltd. Partnership v. Titan Construction Corp.
109 P.3d 830 (Court of Appeals of Washington, 2005)
Ives v. Ramsden
142 Wash. App. 369 (Court of Appeals of Washington, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
Shepler Construction v. Gary And Susan Leonard, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shepler-construction-v-gary-and-susan-leonard-washctapp-2013.