Shepler Construction, Inc. v. Leonard

306 P.3d 988, 175 Wash. App. 239
Court of Appeals of Washington·Decided June 3, 2013·No. No. 68227-0-I·Published·Cited by 5 cases

Opinion

Appelwick, J.

¶1 Shepler and the Leonards appear before this court on their third appeal in this case. In 2006, this court reversed a summary judgment order dismissing the Leonards’ construction defect counterclaims. In 2009, we held that both parties waived arbitration, affirming the trial court’s denial of the Leonards’ motion to compel arbitration. We noted that the parties did not waive their underlying claims. Nevertheless, the trial court on remand barred the Leonards from asserting any counterclaim that should have been submitted to arbitration under the contract’s dispute resolution provision. We reverse.

FACTS

¶2 In 2000, Gary Leonard and Susan Kiraly-Leonard contracted with Shepler Construction Inc. to build a custom home on San Juan Island.1 The fixed price contract contained a dispute resolution mechanism and a provision for Shepler to remedy nonconforming work before final payment. Shepler made an express warranty that work would [241]*241be “substantially completed in a workmanlike manner.” The contract did not contain any disclaimer of implied warranties or any provision limiting remedies.

¶3 In 2001, a dispute arose regarding Shepler’s performance and the Leonards’ payment. Shepler sent letters to the Leonards recommending that they initiate the dispute resolution process. The Leonards admit that they did not respond to the requests for dispute resolution of their claims.

¶4 After filing a mechanic’s lien against the Leonards’ property, Shepler filed suit to enforce the lien and obtain damages for breach of contract. The Leonards filed affirmative defenses and counterclaims, including a construction defect claim alleging that Shepler breached the contract by failing to complete construction in a workmanlike manner. The trial court granted Shepler’s motion for summary judgment on the Leonards’ construction defect counterclaim. After holding a trial on enforcement óf the mechanic’s lien, the court entered judgment and awarded attorney fees in Shepler’s favor. The Leonards appealed the dismissal of their counterclaims on summary judgment. Leonard v. Shepler Constr., Inc., noted at 132 Wn. App. 1054, 2006 WL 1217216, at *2, 2006 Wash. App. LEXIS 908, at *4. In 2006, we reversed and remanded for trial, holding that a genuine issue of material fact existed as to whether Shepler breached its contractual obligation to perform in a workmanlike manner. 2006 WL 1217216, at *3, 2006 Wash. App. LEXIS 908, at *8-9.

¶5 In 2008, Shepler again filed for summary judgment, arguing that the Leonards’ counterclaims should be dismissed, because they breached the contract by failing to seek arbitration. The trial court initially denied the motion. Upon Shepler’s motion for reconsideration, the trial court granted summary judgment on March 31, 2008. The court ordered:

The Leonards are barred from bringing any claim before this court that should have been determined by submittal to bind[242]*242ing arbitration under the contract [’]s dispute resolution provision. All causes of actions or counterclaims relating to Shepler Construction’s performance under the parties agreement, and specifically those asserting that Shepler Construction’s work was not performed in accordance with the contract between the parties, applicable building codes, and in good and workmanlike manner, are therefore dismissed.

The Leonards did not directly appeal the grant of summary judgment.

¶6 On April 11, 2008, the Leonards filed a motion for reconsideration of the summary judgment order or, alternatively, to compel arbitration. The court denied the motion for reconsideration, finding that it was not timely. But, the court determined that the Leonards’ right to bring a timely motion to compel arbitration at a later date was preserved. On May 21, 2008, the Leonards filed a motion to compel arbitration, which the court denied. The Leonards appealed from that denial. Shepler Constr., Inc. v. Leonard, noted at 153 Wn. App 1035, 2009 WL 5153672, 2009 Wash. App. LEXIS 3288.

¶7 On appeal before this court, Shepler argued that the Leonards waived arbitration and were therefore estopped from invoking it. 2009 WL 5153672, at *2, 2009 Wash. App. LEXIS 3288, at *5-6. We held that both parties waived arbitration. 2009 WL 5153672, at *3, 2009 Wash. App. LEXIS 3288, at *7. Neither party initiated notice of arbitration as provided by chapter 7.04A RCW. 2009 WL 5153672, at *3, 2009 Wash. App. LEXIS 3288, at *7. Neither party asserted a right to arbitration in their answers to the pleadings of the other party. 2009 WL 5153672, at *3, 2009 Wash. App. LEXIS 3288, at *7. Both parties conducted discovery and engaged in substantial litigation, including the prior appeal of the counterclaims. 2009 WL 5153672, at *3, 2009 Wash. App. LEXIS 3288, at *7. Seven years passed, and substantial case development occurred before the Leonards asserted the right to arbitrate. 2009 WL 5153672, at *3, 2009 Wash. App. LEXIS 3288, at *7. Therefore, the [243]*243trial court did not err in denying their motion to compel arbitration. 2009 WL 5153672, at *3, 2009 Wash. App. LEXIS 3288, at *7.

¶8 The Leonards argued in the same appeal that the trial court erred in dismissing their counterclaims on summary judgment. 2009 WL 5153672, at *3, 2009 Wash. App. LEXIS 3288, at *7. They did not directly appeal the March summary judgment order but asked that we consider it under RAP 2.4(b). 2009 WL 5153672, at *3 n.l, 2009 Wash. App. LEXIS 3288, at *7 n.1. We declined to do so. 2009 WL 5153672, at *3 n.l, 2009 Wash. App. LEXIS 3288, at *7 n.1. But, we added in note 1 that “[t]he arbitration clause did not provide that it was the exclusive remedy for breach. As noted above, the parties waived the arbitration clause by litigating, not the underlying claims.” 2009 WL 5153672, at *3 n.1, 2009 Wash. App. LEXIS 3288, at *7 n.1.

¶9 The case was tried a second time on August 8-10, 2011. Citing note 1 of our 2009 opinion, the Leonards requested that evidence of construction defects be admitted at least for a recoupment or offset defense, or more broadly for the purpose of their underlying counterclaims. 2009 WL 5153672, at *3 n.1, 2009 Wash. App. LEXIS 3288, at *7 n.1. The court recognized, “I want to make sure that I follow [t]he Court of Appeal’s mandate, and I’m having a difficult time considering that the footnote is a mandate.” But, the court continued, “I believe that the mandate here is exactly as [Shepler’s counsel] has indicated and that is to determine ... the amount owed under the charge [sic] orders ... but it’s not to consider construction defects, and I will so rule.”

¶10 Affirming the March 2008 summary judgment order, the trial court barred the Leonards’ counterclaims for construction defects. In a November 9, 2011, decision letter, the court reiterated that the “Leonards’ refusal to comply with the dispute resolution procedure set forth in the contract waived any claim of construction defect.” (Citing Absher Constr. Co. v. Kent Sch. Dist. No. 415, 77 Wn. App. 137, 890 P.2d 1071 (1995).) The trial was limited to [244]*244Shepler’s claims for compensation and foreclosure, and the Leonards’ counterclaims for incomplete work or offsets. The court entered judgment and awarded attorney fees and costs in Shepler’s favor.

Free access — add to your briefcase to read the full text and ask questions with AI

Shepler Construction, Inc. v. Leonard, 306 P.3d 988, 175 Wash. App. 239 (Wash. Ct. App. 2013).

306 P.3d 988 (Shepler Construction, Inc. v. Leonard) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Larson Motors And Rj 35700 Llc, V. Jet Chevrolet
Court of Appeals of Washington, 2022
Gordon Schuster v. Prestige Senior Management LLC
376 P.3d 412 (Court of Appeals of Washington, 2016)
Shepler Construction, Inc. v. Leonard
175 Wash. App. 1008 (Court of Appeals of Washington, 2013)