Lsf Structures Ltd & Lightweight Steel Framing 2007 Ltd, Apps v. Brix Condos, Resps

Court of Appeals of Washington·Decided November 7, 2016·No. 73427-0·Unpublished

Opinion

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

LSF STRUCTURES LTD, a foreign, corporation; LIGHTWEIGHT STEEL No. 73427-0-1 FRAMING 2007 LTD, a Washington corporation, DIVISION ONE

Appellants,

v.

BRIX CONDOMINIUM, LLC, a UNPUBLISHED OPINION Washington limited liability company; W.G. CLARK CM, INC., a Washington FILED: November 7, 2016 corporation;

Respondents,

SAFECO INSURANCE COMPANY OF AMERICAAS SURETY FOR CONTRACTOR'S REGISTRATION BOND NO. 6079369, a Washington corporation,

Defendant.

Becker, J. — Respondents Brix Condominium LLC and W.G. Clark CM Inc. were entitled to summary judgment because Appellants LSF Structures LTD and Lightweight Steel Framing 2007 Ltd. failed to satisfy the contractual condition precedent to bringing the lawsuit and failed to show that its lawsuit should be interpreted as a complaint to compel arbitration. We affirm.

FACTS

This is the second time these parties have been before this court on the same facts and mostly the same legal issues. Brix Condominium LLC (Brix) was the developer of the Brix Condominiums project. W.G. Clark CM Inc. (WGC) was the general contractor for the Brix Condominiums project and a member of Brix. In 2007, subcontractor Lightweight Steel Framing 2007 Ltd. and LSF Structures Ltd. (together LSF)1 and WGC executed a subcontract for work on the Brix Condominiums project. Section U2 and U3 of the subcontract required the parties to submit their disputes to nonbinding mediation followed by binding arbitration. Section U3 also provided:

Subcontractor agrees not to file any claim in mediation, arbitration, or litigation, until thirty (30) days after having submitted its full claim in writing to Mike Ducey, president of [WGC], along with detailed cost documentation and all points of argument in Subcontractor's favor. Subcontractor acknowledges its responsibility to cooperate with [WGC] in avoiding unnecessary arbitration or litigation by providing [it] with all information available upon which a decision can be made.

(Emphasis added.) Effective July 1, 2008, WGC assigned its interest in the subcontract to Brix and notified LSF that all references in the subcontract to WGC would be deemed to mean Brix. The notice informed LSF that Brix had retained H.A. Andersen Company (Andersen) as the new representative and all "applications, lien releases and notices should be delivered" to Brix with a copy to Andersen.

1 The subcontract states that it is with LSF Structures Ltd., but it is signed by Lightweight Steel Framing 2007 Ltd.

Later in July 2008, Brix terminated LSF. A dispute arose over unpaid invoices. By letter dated February 4, 2009, Brix invoked the arbitration and mediation provisions of the subcontract and made a formal demand for arbitration.2 The parties subsequently agreed on a mediator and arbitrator but did not reach agreement on dates for holding the mediation and arbitration.

In August 2009, LSF filed a complaint in superior court for, among other claims, breach of contract, quantum meruit, and recovery of its contractor registration bond. LSF does not mention the 2009 complaint in its brief. While the 2009 complaint was pending, the parties continued to discuss arbitration. However, LSF failed to produce the files or documentation requested by Brix despite a series of e-mail exchanges between February 2010 and August 2010.

In August 2010, Brix moved for summary judgment. Brix argued that LSF had failed to satisfy the condition precedent set forth in section U3 prior to filing the complaint. In response, LSF argued that there were issues of fact regarding its compliance with section U3. In support of its response, LSF attached the declaration of Al Malcolm, president of LSF, stating that he had been submitting monthly billing statements and had met with Brix personnel regarding the amounts due. Malcolm attached a one-page exhibit that was a summary of the amounts LSF claimed were owed.

2 Some of this background factual information is gleaned from this court's 2012 opinion, which was entered into the record as an attachment to Brix's motion for summary judgement.

On September 10, 2010, the superior court granted summary judgment, dismissing the 2009 complaint without prejudice and finding that LSF had failed to satisfy the condition precedent to filing the lawsuit. LSF appealed. On April 30, 2012, this court dismissed the appeal, holding that a dismissal without prejudice is not appealable and concluding that discretionary review was not warranted.

On July 28, 2014, LSF3 filed the present lawsuit in superior court for breach of contract, promissory estoppel/unjust enrichment, quantum meruit, and recovery of its contractor registration bond. It was based upon the same underlying facts as the 2009 complaint. The complaint requested a stay pending resolution of the claims by mediation/arbitration, pursuant to the subcontract.

On February 20, 2015, Brix again moved for summary judgment based on LSF's failure to satisfy the condition precedent prior to filing the lawsuit. In response, LSF again claimed that there were issues of material fact as to whether it complied with the condition precedent. LSF presented the same August 30, 2010, declaration of Al Malcolm that had been presented in the prior lawsuit. Attached to Malcom's declaration was the same one-page summary listing the amounts allegedly due from Brix pursuant to the subcontract.

3 Lightweight Steel Framing 2007 Ltd. was the plaintiff in the 2009 complaint. In 2014, LSF Structures Ltd. was added as a second plaintiff, but LSF has not argued that there is anything significant about adding a second named plaintiff.

In reply, Brix noted that LSF was presenting the same arguments and declaration that were previously unsuccessful but expecting a different result. Brix asked the court to dismiss this case with prejudice because the complaint was filed on the day the statute of limitations was set to expire, precluding LSF from filing another complaint. The superior court granted summary judgment and dismissed the complaint with prejudice. LSF appeals.

ANALYSIS

"We review summary judgment orders de novo . . ., viewing all facts and reasonable inferences in the light most favorable to the nonmoving party. . . . [S]ummary judgment is appropriate where there is 'no genuine issue as to any material fact and ... the moving party is entitled to a judgment as a matter of law.'" Eicon Const.. Inc. v. E. Wash. Univ., 174 Wn.2d 157, 164-65, 273 P.3d 965 (2012) (some alteration in original) (citations omitted) (quoting CR 56(c)). Although the evidence is viewed in the light most favorable to the nonmoving party, ifthat party is the plaintiff and it fails to make a factual showing sufficient to establish an element essential to its case, summary judgment is warranted. Young v. Key Pharms., Inc., 112 Wn.2d 216, 225, 770 P.2d 182(1989). "Conclusory statements and speculation will not preclude a grant of summary judgment." Eicon Const., Inc., 174 Wn.2d at 169.

The complaint does not ask the trial court to compel arbitration LSF contends that it filed this lawsuit "for the purpose of compelling arbitration," and the trial court erred because the arbitrator should decide "'whether a condition precedent to aribitrability has been fulfilled.'"

LSF filed a complaint alleging breach of contract and seeking over one million dollars "in an amount to be proven at trial (or arbitration)." It is not a complaint to compel arbitration, it contains no allegations that Brix refused to arbitrate, and it does not ask the trial court to compel arbitration. Accordingly, the trial court rightfully considered whether LSF satisfied that condition precedent to filing a lawsuit. Although LSF contends that it filed the lawsuit so that it would have "a mechanism to compel [Brix] to arbitrate" the issue of enforcing the arbitration provision was never before the trial court.

Free access — add to your briefcase to read the full text and ask questions with AI

Lsf Structures Ltd & Lightweight Steel Framing 2007 Ltd, Apps v. Brix Condos, Resps, (Wash. Ct. App. 2016).

Lsf Structures Ltd & Lightweight Steel Framing 2007 Ltd, Apps v. Brix Condos, Resps (Lsf Structures Ltd & Lightweight Steel Framing 2007 Ltd, Apps v. Brix Condos, Resps) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Walter Implement, Inc. v. Focht
730 P.2d 1340 (Washington Supreme Court, 1987)
Young v. Key Pharmaceuticals, Inc.
770 P.2d 182 (Washington Supreme Court, 1989)
Mendoza v. Rivera-Chavez
999 P.2d 29 (Washington Supreme Court, 2000)
Ross v. Harding
391 P.2d 526 (Washington Supreme Court, 1964)
PUD DISTRICT NO. 1, KLICKITAT COUNTY v. International Insurance Co.
881 P.2d 1020 (Washington Supreme Court, 1994)
Elcon Construction, Inc. v. Eastern Washington University
273 P.3d 965 (Washington Supreme Court, 2012)
Little v. Countrywood Homes, Inc.
133 P.3d 944 (Court of Appeals of Washington, 2006)
Staples v. Allstate Insurance
295 P.3d 201 (Washington Supreme Court, 2013)
Little v. Countrywood Homes, Inc.
132 Wash. App. 777 (Court of Appeals of Washington, 2006)
Shepler Construction, Inc. v. Leonard
306 P.3d 988 (Court of Appeals of Washington, 2013)