Dravo Corp. v. Municipality of Metropolitan Seattle

484 P.2d 399, 79 Wash. 2d 214, 1971 Wash. LEXIS 587
CourtWashington Supreme Court
DecidedApril 29, 1971
Docket40965
StatusPublished
Cited by15 cases

This text of 484 P.2d 399 (Dravo Corp. v. Municipality of Metropolitan Seattle) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dravo Corp. v. Municipality of Metropolitan Seattle, 484 P.2d 399, 79 Wash. 2d 214, 1971 Wash. LEXIS 587 (Wash. 1971).

Opinion

Rosellini, J.

In response to an advertisement for bids, published by the Municipality of Metropolitan Seattle, called Metro herein, Dravo Corporation submitted the low bid for the construction of the Enatai interceptor, a sewer pipeline near the East Channel Bridge on the edge of Lake Washington in the city of Bellevue. According to the con *215 tract documents, the sewer was to be laid on hardpan where such hardpan existed at the elevation of the sewer. At other points, where the hardpan lay below the elevation of the sewer, which was designed to allow for gravity flow, the pipe was to be supported on piles driven into the hard-pan.

Metro had caused test borings to be taken at points along the route of the sewer and had made its drawings according to conclusions which it drew from these tests concerning the contour of the hardpan. Some of the sewer was to be laid underwater and some of it in a peat bog. It was impossible to determine the exact contour of the hardpan lying beneath the sewer in these areas by visual inspection, of course, and the cost of taking sufficient test borings to acquire an accurate picture of this contour would have been prohibitive.

The drawings contained in the contract documents divided the sewer line into segments, which were numbered. The terminal points of each segment were referred to as “stations.” They showed that the sewer would be laid on piling from approximately station 20+25 to station 38+00.

However, the invitation to bid advised prospective bidders that they should assume, but only for purposes of computing their bid, that piles would be driven to the depth shown by the drawings. They were advised that if actual conditions at the job site required that the piles be driven deeper, additional compensation would be paid.

The contract also provided in section A2, Information for Bidders:

A 2.04 Soil Information
Subsoil investigations, including underwater borings, were carried out in the vicinity of the interceptor sewer alignment prior to the advertisement of the contract. Reports giving the results of these investigations may be examined at the Municipality’s offices. These investigations were carried out for design purposes only, and are not considered adequate for construction.
The Municipality does not warrant the correctness of the soil investigations, or of any interpretation, deduction or conclusion given in the report relative to subsurface *216 conditions. The bidder shall make his own deductions and conclusions as to the nature of the materials to be excavated, the difficulties of making and maintaining the required excavations, the difficulties which may arise from subsurface conditions, and of doing any other work affected by the subsurface conditions, and shall accept full responsibility therefor.
No extra payment will be made over and above the contract price on account of any difference between the information relating to soil and foundation conditions provided by the Municipality and the conditions disclosed at the site of the work during the progress of the contract.

The contract was awarded to Dravo on the basis of its low bid. The work was commenced and progressed to the vicinity of station 38+00. There, as indicated in the drawings, the hardpan began to drop rather sharply and a transition to piling became necessary. This was an area of peat bog. Dravo’s subcontractor who was doing this phase of the work drove the piles, in pairs as required by the design, but when Dravo attempted to excavate for the purpose of cutting off the pile tips, capping them, placing a cradle between the two piles in each pair, and laying the sewer pipe thereon, lateral pressure from the surrounding peat caused the piles to tip over.

Metro’s representative gave Dravo the option of redriv-ing the piles or pouring a concrete base on which to lay the piles. Dravo chose the latter course.

• From that point on to approximately station 30+00, the pipe was laid on piling in accordance with Metro’s drawings. As the operation was carried to that station, it became obvious that the top of the hardpan was rising, since the piling was reaching the required load-bearing capacity at increasingly higher elevations. From about station 30+00 to station 28+86, the elevation to which the piles were driven was above the elevation at which the pipe was to be laid.

Dravo was advised by an agent of Metro that the piles were useless in that area. Nevertheless, the subcontractor *217 continued to lay the piling across this area, which was 109 feet in length, because it needed them to support its rig. When excavation was begun for laying the pipe, the piles were uprooted. In accordance with the directions of Metro’s engineer, the hardpan was excavated to the elevation called for by the drawings and the pipe was laid on a base on the hardpan.

Dravo requested extra compensation for the laying of the pipe at these two locations, but Metro denied that any extra compensation was owed. In this lawsuit which followed, these claims and others as well as certain counterclaims of Metro, were litigated. The trial court found that the conditions at station 38+00 were substantially as represented in the drawings, and that the difficulties which Dravo encountered were caused by its own method of operation. No recovery was allowed for expenses incurred by Dravo at this location.

The court found that the subsurface irregularity which was encountered at station 30+00 to station 28+86 was a condition which was not foreseen by either Dravo or Metro and could not have been foreseen with the information that was available to the parties. It held that Dravo should be compensated for the cost of laying the pipe at this location.

Dravo has appealed from that portion of the judgment which disallowed its claim for compensation for its expenses at station 38+00, and Metro has appealed from that portion which allowed Dravo’s claim for compensation for its cost of laying pipe at stations 30+00 to 28+86.

We assume, without deciding, that Dravo is correct when it declares that there was no evidence to support the trial court’s finding that its difficulties at station 38+00 were caused by its method of operation. We agree with the parties that the problems at both locations arose because of changes in the contour of the hardpan. The same legal principles apply in both appeals.

This court has subscribed to the generally accepted doctrine governing the allocation of risks involved in excavation contracts, where conditions develop which were not *218 foreseen by the contractor. In Maryland Cas. Co. v. Seattle, 9 Wn.2d 666, 670, 116 P.2d 280 (1941), 1 we stated the rule as follows, quoting from 76 A.L.R. 268 (1932):

Free access — add to your briefcase to read the full text and ask questions with AI

Related

King County v. Vinci Construction Grands Projets/Parsons RCI/Frontier-Kemper, JV
191 Wash. App. 142 (Court of Appeals of Washington, 2015)
Mike M. Johnson, Inc. v. Spokane County
150 Wash. 2d 375 (Washington Supreme Court, 2003)
Mike M. Johnson, Inc. v. County of Spokane
78 P.3d 161 (Washington Supreme Court, 2003)
Basin Paving Co. v. Mike M. Johnson, Inc.
107 Wash. App. 61 (Court of Appeals of Washington, 2001)
Scoccolo Const., Inc. v. City of Renton
9 P.3d 886 (Court of Appeals of Washington, 2000)
Scoccolo Construction, Inc. v. City of Renton
102 Wash. App. 611 (Court of Appeals of Washington, 2000)
Clevco, Inc. v. Municipality of Metropolitan Seattle
799 P.2d 1183 (Court of Appeals of Washington, 1990)
Beco Corp. v. Roberts & Sons Construction Co.
760 P.2d 1120 (Idaho Supreme Court, 1988)
Modern Builders, Inc. v. Manke
615 P.2d 1332 (Court of Appeals of Washington, 1980)
Nelson Construction Co. of Ferndale, Inc. v. Port of Bremerton
582 P.2d 511 (Court of Appeals of Washington, 1978)
Obray v. Mitchell
567 P.2d 1284 (Idaho Supreme Court, 1977)
Robert E. McKee, Inc. v. City of Atlanta
414 F. Supp. 957 (N.D. Georgia, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
484 P.2d 399, 79 Wash. 2d 214, 1971 Wash. LEXIS 587, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dravo-corp-v-municipality-of-metropolitan-seattle-wash-1971.