Valley Construction Co. v. Lake Hills Sewer District

410 P.2d 796, 67 Wash. 2d 910, 1966 Wash. LEXIS 866
CourtWashington Supreme Court
DecidedFebruary 3, 1966
Docket37739
StatusPublished
Cited by8 cases

This text of 410 P.2d 796 (Valley Construction Co. v. Lake Hills Sewer District) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Valley Construction Co. v. Lake Hills Sewer District, 410 P.2d 796, 67 Wash. 2d 910, 1966 Wash. LEXIS 866 (Wash. 1966).

Opinion

Langenbach, J.

— Respondents, as contractor, sued to recover the unpaid balance on a contract and to recover costs for repairs which were requested by appellant. Appellant affirmatively counterclaimed for damages which allegedly resulted from respondents’ failure to follow contract specifications, but admitted a balance was still due on the contract.

The trial court granted judgment for respondents as pleaded, and dismissed the counterclaim with prejudice. This appeal was perfected.

Respondents contracted to construct an 18-inch trunk sewer and two syphon lines according to contract specifications. The trunk sewer was satisfactorily completed; this dispute concerned only the installation of the syphon lines.

The syphon lines consisted of two pipes, one 10 inches and the other 12 inches, inside diameter, to be laid beside each other in a single trench for a distance of 4,100 feet with a minimum of 6 inches between them, and with the maximum trench width (at pipe level) of 16 inches plus the outside diameter of the pipe. The 12-inch pipe was to be laid 7 feet from the edge of a road, under a drainage ditch, with a minimum 36-inch cover. The lines were to follow the grade of the road.

The contract required the respondents to perform trench excavation and backfill, furnish and install pipe, manholes, *912 fittings and other appliances. The respondents used 13-foot sections of asbestos cement pressure pipe as the syphon lines.

The applicable pipe bedding method was prescribed as follows:

10. Pipe Bedding
Pipe bedding shall be accomplished as shown in the Standard Detail. Where the material at the bottom of the trench is unstable, the matter shall be brought to the attention of the Engineer. The unstable material shall be removed to the extent directed by the Engineer and back-filled with foundation gravel, bedding gravel, and/or bedding concrete.
Boulders, rocks, roots and other obstructions shall be entirely removed or cut out to the full width of the trench and to a depth 6" below the pipe. The trench shall be backfilled and compacted to grade with select materials from the excavation or with bedding gravel.
In solid rock the trench shall be excavated 6" below the pipe bottom and backfilled as provided above.
The bottom of the trench shall be finished with hand tools to provide uniform bearing along the barrel of the pipe and to provide suitable holes to fit the pipe bells.
Whenever the trench is excavated below the depth required for proper bedding, it shall be backfilled with bedding gravel and compacted as required by the Engineer.

The evidence disclosed that, as the syphon line trench was being excavated, hardpan was encountered. The contract stated respondents had inspected the area and were satisfied as to the conditions of the site and contract specifications prior to submitting a bid. The contract specified that respondents handshape the trench bottom to fit the pipe barrel so that the pipe would rest on the shaped trench bottom. Respondents admitted this, but asserted that, when the hardpan was reached, it became impossible to hand-shape the bottom of the trench.

This hardpan condition was orally called to the attention of appellant’s inspector, chief inspector, and project engineer, in an attempt to secure permission to use bedding *913 material (pea gravel) in preparation of the trench bottom. Inspector Sims approved and reported favorably to his superiors, who refused this permission. Such requests were verbal, and none were in writing, as required by the contract:

7. Corrections, Interpretations and Addenda
Any omissions, discrepancies or need for interpretations should be brought to the attention of the Engineer in writing. The Engineer will issue written addenda to clarify questions which may arise. All interpretations or explanation of the Contract Documents shall be in writing in the form of an addendum and no oral statements by the Owner, Engineer or other representatives of the Owner shall in any way modify the Contract Documents whether made before or after letting the Contract.
9. Omissions and Discrepancies:
If the Contractor, in the course of the work, finds any discrepancy between the drawings and the physical conditions of the locality, or any errors or omissions in drawings or in the layout as given by points and instructions, it shall be his duty to inform the Engineer immediately in writing, and the Engineer shall promptly verify the same. Any work done after such discovery, until authorized, will be done at the Contractor’s risk.

The contract provision for payment of bedding material was:

Item No. 15
Unit price includes furnishing, placing and compacting bedding and foundation gravel and pit run gravel backfill material other than materials available from trenching. Payment will be made for only such material as is ordered by the Engineer. Bedding or foundation material required by unauthorized excavation below the required trench depth or for special bedding for Class 3 clay pipe shown on the plans will not be paid for.
Furnish & Install Bedding Gravel 500 CY $4.50 $2250.00.

When these oral requests for use of bedding material in the hardpan trench were refused, respondents determined that handshaping the trench bottom for suitable support of *914 the trench barrel was impracticable in all instances and impossible in hardpan. Consequently, a cushion course method of installation was utilized. From the excavation, selected material (excluding rocks, roots and foreign material) was used for a cushion course of approximately 4 inches in depth. This was compacted by men walking on it. Thereon mounds would be placed; one where each end of the pipe was to be laid. Due to over-excavation, the mounds in some instances were 12 inches high; normally, the mounds were approximately 4 inches high. These mounds would not be compacted nor tamped prior to laying the pipes. After the pipes were laid, select material was used to fill the ditch up to the middle portion of the pipes; then, the dirt was compacted by two-by-fours, handles of shovels, and men using their feet. Due to the narrowness of the trench, this compacting was difficult.

The material used for mounding and filling was relatively dry. When the rains fell, the mound and fill material (the pipes being laid under a drainage ditch) became so saturated that it turned into a mush substance. Accordingly, the pipes were allowed to change position to such an extent that they broke. The engineers testified that the breaks were caused by “beam action.” The plane of separation was nearly perpendicular to the center line of the pipe.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lake Hills Invs., LLC v. Rushforth Constr. Co., Inc.
494 P.3d 410 (Washington Supreme Court, 2021)
Pacific Boring, Inc. v. Staheli Trenchless Consultants, Inc.
138 F. Supp. 3d 1156 (W.D. Washington, 2015)
Absher Construction Co. v. Kent School District No. 415
890 P.2d 1071 (Court of Appeals of Washington, 1995)
S. L. Rowland Construction Co. v. Beall Pipe
540 P.2d 912 (Court of Appeals of Washington, 1975)
Dravo Corp. v. Municipality of Metropolitan Seattle
484 P.2d 399 (Washington Supreme Court, 1971)
Lindbrook Construction, Inc. v. Mukilteo School District No. 6
458 P.2d 1 (Washington Supreme Court, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
410 P.2d 796, 67 Wash. 2d 910, 1966 Wash. LEXIS 866, Counsel Stack Legal Research, https://law.counselstack.com/opinion/valley-construction-co-v-lake-hills-sewer-district-wash-1966.