Dehoney v. Gjarde

236 P. 290, 134 Wash. 647, 1925 Wash. LEXIS 725
CourtWashington Supreme Court
DecidedMay 29, 1925
DocketNo. 18632. Department Two.
StatusPublished
Cited by13 cases

This text of 236 P. 290 (Dehoney v. Gjarde) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dehoney v. Gjarde, 236 P. 290, 134 Wash. 647, 1925 Wash. LEXIS 725 (Wash. 1925).

Opinion

Fullerton, J.

On April 5, 1922, J. H. DeHoney and wife entered into a contract with Peder P. Gjarde, by the terms of which Gjarde agreed to erect for the DeHoneys a building on a described tract of land, in the city of Seattle, to be used as a dancing academy. The contract provided that Gjarde should furnish all the necessary labor and materials and erect the building according to plans and specifications agreed upon between the parties,- prepared by one Svarz as architect. The contract price was $27,329, and the building *649 was to be completed on or before 110 days from tbe date of tbe contract. Gjarde entered at once upon tbe performance of tbe work, completed it witbin tbe time fixed by tbe contract, and was paid tbe contract price.

DeHoney and wife took possession of tbe building sometime in August, 1923, and began to use it for tbe purposes for wbicb it was constructed. Tbe building gave no trouble during tbe dry weather wbicb followed tbe time possession was taken, but in tbe latter part of October, when tbe. rainy season began, water came into tbe ball of tbe building used for dancing in considerable quantities; so considerable, in fact, as to damage tbe furnishings and to cause tbe dancing floor to swell and buckle. The DeHoneys conceived that tbe water came into tbe room because of a defective and leaking roof, and called upon Gjarde to repair it. Some correspondence passed between them, resulting in a denial on tbe part of Gjarde of liability. Tbe DeHoneys caused tbe roof to be repaired by another person, and caused some additional ventilation to be installed in tbe building, whereupon water ceased to come into the room, and the walls thereof became dry soon thereafter.

Tbe DeHoneys, as plaintiffs, thereafter began tbe present action to recover against Gjarde and bis bondsman, tbe Fidelity and Deposit Company of Maryland, in damages for tbe injuries caused by tbe water. They alleged that Gjarde failed to construct tbe building in accordance with tbe plans and specifications, in that be “negligently and carelessly failed to turn up tbe felt and flashings onto the walls of said building not less than 18 inches as tbe contract and good workmanship required, but instead turned tbe same up not to exceed 12 inches in any place, and around tbe greater portion of tbe walls, not to exceed four inches, and negligently and carelessly failed to put tbe same up *650 tight against said walls or to nail or otherwise fasten or cement the same at sufficiently close intervals, so that as a result the upper portions of the same were allowed to be loose and to bulge out from said walls, so that water could go- through where the same should have been fastened tight to the walls and from thence go down under the roofing and thence into the building; that where there were columns erected just inside said side walls, making numerous angles, the said felt and flashings were in some places pressed in so hard by them as to have cracked and broken the same, leaving openings for the water to go through, while in other places, they negligently and carelessly failed to press the same into- the angles sufficiently, but on the contrary allowed the same-to be loose and to bulge out at the top where it should have been tightly joined to the wall, so that the water could run down into the building as hereinbefore mentioned; that they negligently and carelessly allowed approximately 100 holes and openings to be and remain where the water could leak through, said holes and openings, for the most part being located where said felt and flashings should have been joined tight to the wall and columns, and where the same had been broken as hereinbefore mentioned, which were thereupon hidden by them by placing the counter flashings so as to conceal the same; that the top of said counter flashings was fastened by them to a wooden strip set in the concrete wall; that they negligently placed around said wooden strip certain plaster which was made out of poor material in that there was too much sand in the same, so that the same was so porous that it allowed the water to run through the same and back of said counter flashings and that much of said plastering material fell out after the same became water soaked; that the felt and flash-ings around the ventilators were not properly fastened *651 by them, as hereinbefore stated, so- that the same were loose and bulged at the top, allowing the water to leak in; that the paper used by them on the slopes where the roof slopes steeply from the upper portion of the roof to the 'valley’ portion of the roof below, was of poor quality, in that the same was checked and cracked; that the paper used by them on the roof and slopes was so put together by them that the same would leak at the joints and seams, the cause thereof not being known to plaintiffs; that along the south side of said building there were leaks under the windows; that they wholly failed to place any galvanized iron boxes in the comers, surrounding the drain pipes, but instead placed boxes made of cheap tin, none of which were securely soldered, so that the water leaked out of them, instead of going into the pipes; that no screens were placed in said boxes until after the first rains hereinafter mentioned, and on approximately the 17th day of November, 1923, thus allowing said pipes to become clogged; that by reason of the matters herein-above set forth, said building, when turned over to the plaintiffs on or about Aug. 29,1922, did not have a roof capable of turning water during an ordinary rain, but on the contrary said roof was in such condition as to be leaky in wet weather, none of which defects were discovered by plaintiffs or known to them until the rains hereinafter mentioned occurred.”

Damages were claimed in the following sums for the following items:

Repairing roof ........................... $541.35
Carpenter work .......................... 400.30
Redecorating the walls and work on damaged paintings ............................. 403.65
Plumbing work........................... 25.47
Tinning.................................. 5.25
Resurfacing the dancing floor.............. 600.00
*652 Redecorating the walls and ceiling.......... 1,500.00
Additional work on paintings.............. 600.00
Damage to seats.......................... 800.00
Damage to piano...................•...... 500.00
Damage to curtains....................... 300.00
Depreciation of building (Not repairable).. .10,000.00
Loss of profits because of non-usability of building ..............................25,000.00

The first five of the items of damage were for money actually expended for the work therein indicated. Other items, in so far as they relate to work, were the estimates of witnesses of the reasonable cost of performance. The remaining items are self-explanatory. After issue had been joined on the complaint, a trial was entered upon before a jury.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carlson v. Leonardo Truck Lines, Inc.
538 P.2d 130 (Court of Appeals of Washington, 1975)
Lindbrook Construction, Inc. v. Mukilteo School District No. 6
458 P.2d 1 (Washington Supreme Court, 1969)
Harris Cattle Co. v. Paradise Motors, Inc.
448 P.2d 866 (Arizona Supreme Court, 1968)
Municipality of Metropolitan Seattle v. Kenmore Properties, Inc.
410 P.2d 790 (Washington Supreme Court, 1966)
Valley Construction Co. v. Lake Hills Sewer District
410 P.2d 796 (Washington Supreme Court, 1966)
Sposari v. Matt Malaspina & Co.
388 P.2d 970 (Washington Supreme Court, 1964)
Pappas v. Zerwoodis
153 P.2d 170 (Washington Supreme Court, 1944)
Bates v. Tirk
31 P.2d 525 (Washington Supreme Court, 1934)
Knickerbocker Co. v. Gjarde
22 P.2d 987 (Washington Supreme Court, 1933)
Schultz v. Wells Butchers' Supply Co.
275 P. 737 (Washington Supreme Court, 1929)
State v. Presta
253 P. 811 (Washington Supreme Court, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
236 P. 290, 134 Wash. 647, 1925 Wash. LEXIS 725, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dehoney-v-gjarde-wash-1925.