Sposari v. Matt Malaspina & Co.

388 P.2d 970, 63 Wash. 2d 679, 1964 Wash. LEXIS 529
CourtWashington Supreme Court
DecidedJanuary 30, 1964
Docket36744
StatusPublished
Cited by10 cases

This text of 388 P.2d 970 (Sposari v. Matt Malaspina & Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sposari v. Matt Malaspina & Co., 388 P.2d 970, 63 Wash. 2d 679, 1964 Wash. LEXIS 529 (Wash. 1964).

Opinion

Hale, J.

The best laid plans of a sewer construction may go awry. If the ditch happens upon an underground bog, an action at law is sure to follow. This is such a case.

Matt Malaspina & Company, Inc., as a prime contractor in competitive bidding, won the contract with the Lake City Sewer District to construct a sewer in King County. Matt Malaspina, president of and dominating figure in the company, had known James Sposari and Joseph Macri for many years. He knew them personally and as partners in the excavating business. He knew that their experience in putting in sewers, water pipes and utility lines underground came from smaller jobs for individuals and land developers and that they had insufficient capital to stand by themselves as subcontractors on his Lake City contract. He knew, too, that they had been in business together for more than 6 years and that their work and experience had shown them to be competent in excavation jobs, though of smaller scope than the subcontracts contemplated by the prime Lake City contract.

*681 Sposari and Macri talked the matter of a subcontract over with Mr. Malaspina many times; they studied the contract carefully after its award to Malaspina & Company and made a bid on a part of it. They undertook to do all of the work and make all of the installations specified by the prime contract in the area between North 155th Street on the north and North 145th Street on the south, including installing sewers along Interlake, Wallingford and Meridian Avenues. They started the job about June 10, 1959.

During the first week of construction, they met their own payroll with money received from another job. In their second week, Mr. Malaspina advanced them $1,500 for their payroll, but cautioned them that thereafter they must look elsewhere for financing. The third week’s payroll was met by Sposari and Maori with money taken in on a different contract, and later Mr. Malaspina, despite earlier'warnings, advanced them an additional $2,000 by check with which to meet their current payroll. Subsequently, in about the sixth week of construction, Malaspina paid them by check for a small job they had done for him elsewhere.

On this last check he stopped payment, explaining to Sposari and Macri that he had learned they were not paying their bills for materials and supplies put into the Lake City contract. He said he had stopped payment on the check in self-protection as he would be held liable for these bills in the long run.

Aside from a scarcity of money on which to operate — a problem readily anticipated — Sposari and Macri ran into more serious obstacles. After finishing the sewer installation along Wallingford Avenue with fair speed, and while extending the sewer from a point in the plans marked “manhole 139” to another point called “manhole 148,” they unexpectedly ran into an underground bog or swamp.

Their progress dropped, as they estimated it, from over 160 feet per day to 250 feet in two weeks. The ditch filled with water sometimes to a depth of 4 feet; in some places it caved in and widened; they installed well points and pumps, which, at times, they had their crews operate *682 around the clock. At other times, their crews had to stand by for several hours while the ditch area drained and dried. Mr. Malaspina said that they were tardy in putting in the well points and niggardly in operating the pumps, and that these blunders inexcusably forced the crew to stand idle at times during the regular day shift.

Malaspina, worried that the slow going in this sector would jeopardize his completion of the prime contract, pressed Sposari and Macri to speed up. He said that underground waters of this sort were to be expected and that, had Sposari and Macri put in well points and pumps early enough and kept them going day and night, the problems caused by the water would have been small. Sposari and Macri countered this, saying that they had taken all reasonable steps to keep the job moving and that, once through the bog, they would have easier going and could readily make up the lost time in the remaining portion of their part of the project.

Out of the swamp, or bog, emerged an enigma: Did Spo-sari and Macri give up the job, or did Malaspina take it away from them? From conflicting evidence, a jury decided that Mr. Malaspina had, in violation of his agreement, terminated Sposari and Macri and turned the unfinished part of their subcontract over to others. The jury awarded Sposari and Macri $13,500 against Matt Malaspina & Company, Inc., as damages for breach of contract.

From a judgment on this verdict, Malaspina & Company appeals; we will discuss two of the three assignments of error.

(1) Did the court err in excluding evidence of debts incurred by the plaintiffs for materials and supplies delivered to and put into the construction by them as subcontractors which debts the prime contractor orally promised to the creditors he would pay but had not paid?

(2) Did the court err in submitting to the jury the issue of anticipated profits?

On the point raised by the first assignment of error, Mr. Malaspina testified that the materialmen and suppliers had *683 all done business with him for many years on excellent terms. Many of them, he said, looked to him for assurances of payment for materials ordered by, delivered to, and put into the job by Sposari and Macri. He said that a number of these creditors would not have delivered such items as concrete and metal pipe, crushed gravel and timber, to the jobsite but for his promises to them that he would see to the payment of their invoices and, if necessary, would pay them himself. The court struck from the record and removed from the jury’s consideration all invoices that were not actually paid by Malaspina. They came to a total of $3,521.09, owing and unpaid to five separate suppliers whom Malaspina had orally promised to pay if plaintiffs failed to do so. He now argues his own liability on these oral representations to these unpaid creditors as a proper offset to plaintiffs’ claim for loss of expected profits, even though none of these creditors have been joined as parties or appeared as witnesses to prove their claims. Appellants assert error in the trial court’s removal of these debts from the cause.

At the outset, the language of the statute of frauds gives us a clue to the proper decision. RCW 19.36.010(2). 1 If the promises made come within the meaning of the act as being special promises to answer for the debt default or misdoings of another person, and are not in writing, they are unenforceable against the promissor and, thus, not available as an offset in defense to an action for lost profits. In trying to determine if the promises are of such nature as to fall within the statute of frauds, we must ascertain if the oral promise was a direct, original agreement, constituting an undertaking on the part of the promissor to the creditor to pay for the materials, or whether it was *684 merely a collateral agreement by the promissor to answer for the debts of another if the latter did not discharge them.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McAlister v. Loeb
Arizona Supreme Court, 2025
HTS, Inc. v. Boley
954 F. Supp. 2d 927 (D. Arizona, 2013)
South Sound National Bank v. Meek
544 P.2d 25 (Court of Appeals of Washington, 1975)
Hall v. Anton Industries, Inc.
516 P.2d 1070 (Court of Appeals of Washington, 1973)
Seaboard v. WILLIAMS'NW CHRYSLER
504 P.2d 1139 (Washington Supreme Court, 1973)
Williams v. Fixdahl
491 P.2d 1309 (Court of Appeals of Washington, 1971)
Drake v. Ross
478 P.2d 251 (Court of Appeals of Washington, 1970)
Harris Cattle Co. v. Paradise Motors, Inc.
448 P.2d 866 (Arizona Supreme Court, 1968)
Smith v. Twohy
425 P.2d 12 (Washington Supreme Court, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
388 P.2d 970, 63 Wash. 2d 679, 1964 Wash. LEXIS 529, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sposari-v-matt-malaspina-co-wash-1964.