Wenzler & Ward Plumbing & Heating Co. v. Sellen

330 P.2d 1068, 53 Wash. 2d 96, 1958 Wash. LEXIS 281
CourtWashington Supreme Court
DecidedOctober 30, 1958
Docket34498
StatusPublished
Cited by32 cases

This text of 330 P.2d 1068 (Wenzler & Ward Plumbing & Heating Co. v. Sellen) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wenzler & Ward Plumbing & Heating Co. v. Sellen, 330 P.2d 1068, 53 Wash. 2d 96, 1958 Wash. LEXIS 281 (Wash. 1958).

Opinion

Foster, J.

Respondent, plaintiff below, a subcontractor, sued appellants, defendants below, the prime contractors, for a balance claimed under its subcontract for mechanical and plumbing work on the preflight facilities at Boeing field, Seattle, Washington. Appellants cross-complained under the same contract. The court allowed some items on the defendants’ cross-complaint but awarded respondent a judgment against appellants in excess of $11,000, from which they appeal. Respondent does not cross-appeal.

Four errors are assigned, the two most important being the rejection of appellants’ claims for denying the items in their cross-complaint for “as built” drawings amounting to $1,582.56, and compaction of trenches in the sum of $1,980. The “as built” drawings show the exact location of underground installations, and are required by the owner for maintenance and upkeep. The contract required the respondent to furnish the drawings, but it did not do so, whereupon appellants did and cross-complained for the cost thereof. Appellants made such drawings not only for the respondent, but for other subcontractors as well, and have the total costs thereof, but appellants did not keep separate accounts of such work for each subcontractor. An engineer testified that he could estimate, within ten per cent of accuracy, the time spent for this purpose, which he testified came to $1,582.56.

The court unequivocally found that the respondent had the contractual obligation to furnish such drawings, but that nothing could be allowed on account thereof because *98 no separate cost record was kept by the appellants. The finding is set out in the margin. 2

The issue of compacting dirt in the trenches is much the same. The respondent was under a contractual duty to do such work and did not do so. Appellants then hired it done as they had for other subcontractors. The testimony showed the total cost and the respondent’s proportionate part thereof.

The court found that some of this work was properly chargeable against respondent, but it was unable to find such proportionate sum or a reasonable cost basis. Finding of fact No. 7 is set out in the margin. 3

Such is a summary of the circumstances respecting both items. The fact of damage was established beyond cavil, but the dollar amount thereof was not proved with mathematical precision. Therefore, the trial court decided the respondent should be immunized from all liability.

Uncertainty as to the fact of damage is ground for denying liability, but the fact of damage being removed from the field of controversy by uncontradicted proof, immunization of the party responsible does not result from uncertainty as to the dollar amount of the damage.

The controlling rule of law was summarized by the United States supreme court in the following passage from its opinion in Bigelow v. RKO Radio Pictures, Inc., 327 U. S. 251, 90 L. Ed. 652, 66 S. Ct. 574, a private triple-damage action under the antitrust laws:

*99 “The most elementary conceptions of justice and public policy require that the wrongdoer shall bear the risk of the uncertainty which his own wrong has created. . . .
“ ‘The constant tendency of the courts is to find some way in which damages can be awarded where a wrong has- been done. Difficulty of ascertainment is no longer confused with right of recovery’ for a proven invasion of the plaintiff’s rights. ...”

Our cases are in accord. In one of them, Kramer v. Portland-Seattle Auto Freight, 43 Wn. (2d) 386, 261 P. (2d) 692, a wrongful death action, the court quoted with approval from Bigelow v. RKO Radio Pictures, Inc., supra. Other cases are collected in the margin. 4 In. Sund v. Keating, 43 Wn. (2d) 36, 259 P. (2d) 1113, the court reviewed the situation in these words:

“As to appellants’ claim that damages here are speculative and conjectural, it seems sufficient to cite our recent decisions in Gaasland Company v. Hyak Lumber & Millwork, 42 Wn. (2d) 705, 257 P. (2d) 784; Dunseath v. Hallauer, 41 Wn. (2d) 895, 253 P. (2d) 408, wherein we pointed out that while uncertainty as to the fact of damage is fatal; nevertheless, uncertainty as to the amount or quantum of damages is not to be regarded, similarly, as fatal to a litigant’s right to recover damages. . . . ”

The rule is applicable to a great variety of situations, 25 C. J. S. 493, § 28; 15 Am. Jur. 414, § 23; specifically, Allen v. Gardner, 126 Cal. App. (2d) 335, 272 P. (2d) 99 (1954), applied it in an action for the breach of a construction contract. It is most concisely stated in 14 Cal. Jur. (2d) 690, § 65:

“A party who has breached a contract or committed a tortious act is generally not permitted to escape his liability *100 in damages, therefor simply by reason of difficulty in the ascertainment of the damage to the plaintiff. Therefore, when it is clearly apparent that the plaintiff has sustained actual damage from the defendant’s wrong, a liberal rule is applied with respect to determining the amount of that damage. Moreover, where proof of actual damage to the plaintiff is available, uncertainty as to the exact amount thereof cannot deny to the plaintiff a right to recover any compensation at all. This rule applies both to a loss of profits by the plaintiff and to items, of expense incurred by him as a result of his wrongful discharge from employment.”

For a comparison with the English law, see 11 Halsbury’s Laws of England (3d ed.) 226, § 394. 5

Respondent contracted to provide the “as built” drawings and to compact the trenches and, of course, took these items into account in making its bid, and was. presumably. paid therefor. It offered no evidence thát the amount of the appellants’ damage computed by their witnesses was erroneous. There was substantial evidence of the amount of appellants’ damage, and the court manifestly erred in denying appellants, any recovery for the two items.

Error is assigned upon the allowance for extras amount *101 ing to $2,054.42, plus fifteen per cent, or $308.14, for overhead, a total of $2,362.56.

The contract provided that the subcontractor would make no claim for extras unless agreed upon in writing in. advance. Elsewhere in the contract it is provided that failure to give such advance notice shall be a waiver of extra compensation.

While the court made no finding upon this issue, the trial judge did state in his oral opinion that such contract requirement of advance written approval had been abandoned. However, the record is barren of any evidence thereof.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In the Matter of the Estate of: Danny L. Snapp
Court of Appeals of Washington, 2025
Jinni Tech Ltd v. Red.com Inc
W.D. Washington, 2020
Roil Energy, LLC v. Joseph (Jay) Edington, et ux
Court of Appeals of Washington, 2016
Amalgamated Transit Union Local 1384, V Kitsap Transit
Court of Appeals of Washington, 2015
Amalgamated Transit Union, Local 1384 v. Kitsap Transit
349 P.3d 1 (Court of Appeals of Washington, 2015)
Moore v. Health Care Auth.
Washington Supreme Court, 2014
Moore v. Washington State Health Care Authority
332 P.3d 461 (Washington Supreme Court, 2014)
James P. Thomas, et ux v. Angelo Brunetto, et ux
Court of Appeals of Washington, 2013
Spradlin Rock Products, Inc. v. Public Utility District No. 1
164 Wash. App. 641 (Court of Appeals of Washington, 2011)
SPRADLIN ROCK v. Public Utility Dist. No. 1
266 P.3d 229 (Court of Appeals of Washington, 2011)
Puget Sound Power & Light Co. v. Strong
798 P.2d 1162 (Court of Appeals of Washington, 1990)
McKernan v. Aasheim
687 P.2d 850 (Washington Supreme Court, 1984)
Omer v. Edgren
685 P.2d 635 (Court of Appeals of Washington, 1984)
Sturgis Co. v. H. D. Baker Co.
524 P.2d 413 (Court of Appeals of Washington, 1974)
V. C. Edwards Contracting Co. v. Port of Tacoma
514 P.2d 1381 (Washington Supreme Court, 1973)
V. C. Edwards Contracting Co. v. Port of Tacoma
503 P.2d 1133 (Court of Appeals of Washington, 1972)
Jacqueline's Washington, Inc. v. Mercantile Stores Co.
498 P.2d 870 (Washington Supreme Court, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
330 P.2d 1068, 53 Wash. 2d 96, 1958 Wash. LEXIS 281, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wenzler-ward-plumbing-heating-co-v-sellen-wash-1958.