V. C. Edwards Contracting Co. v. Port of Tacoma

503 P.2d 1133, 7 Wash. App. 883, 1972 Wash. App. LEXIS 1064
CourtCourt of Appeals of Washington
DecidedNovember 22, 1972
Docket466-2
StatusPublished
Cited by6 cases

This text of 503 P.2d 1133 (V. C. Edwards Contracting Co. v. Port of Tacoma) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
V. C. Edwards Contracting Co. v. Port of Tacoma, 503 P.2d 1133, 7 Wash. App. 883, 1972 Wash. App. LEXIS 1064 (Wash. Ct. App. 1972).

Opinion

Armstrong, J.

Defendant Port of Tacoma appeals from a judgment of $225,595.49 in favor of Y. C. Edwards Contracting Company and against the Port of Tacoma. Defendant also appeals from a judgment of dismissal dismissing a third-party defendant, McDowell-Wellman Engineering Company.

This appeal raises three issues: (1) Was there substantial evidence of breach of contract by the Port of Tacoma? (2) Were damages properly assessed? (3) Did the trial court properly dismiss the third-party defendant? We answer each question in the affirmative.

The Port of Tacoma (Port) and V. C. Edwards Contracting Company (Edwards) entered into a contract on December 13, 1967. The contract provided that Edwards would construct a rail service yard and connecting trackage on the Port’s premises, the Tacoma tideflats, and the Port would supply the necessary materials. McDowell-Wellman Engineering Company, independent consulting engineers, had prepared the plans and specifications according to information supplied by the Port. Among other things, the plans called for 1,000 yards of fill to be used as ballast under the track. This fill was to be excavated by the contractor from other portions of the site. After consulting with McDowell-Wellman, the Port issued an addendum (No. 2) to the plans on November 15, 1967 which called the contractor’s attention to five separate places where a sewer *885 project would interfere with this rail project. The bids were opened 1 week later.

Notice to proceed was given to Edwards and construction began on January 18, 1968. For several reasons the work was not completed within the 270 days specified in the contract documents.

Edwards brought this suit against the Port alleging that the delay was caused by, among other things, defective plans, failure of the Port to supply necessary materials and failure of the Port to warn the plaintiff of conflicts with other contractors in the area. The Port entered a general denial, cross-complained for work to be completed and filed a third-party complaint against McDowell-Wellman alleging responsibility for the defective plans.

The trial court found that the Port substantially breached its contract in several respects. The court found the Port’s failure to make decisions within a reasonable time, failure to furnish the promised material, and the Port’s unintentionally misleading addendum No. 2 caused the plaintiff substantial delay in completing the work and was a substantial breach of contract.

The court also found that the contractor had to correct several design errors in the plans and that addendum No. 2 was misleading because the paths of Edwards and the sewer contractor crossed in over 30 places, not in only 5 as specified. The correction of the design errors entailed resurveying and recalculating parts of the plans plus importing an extra 92,000 yards of fill to be used as ballast when the plans called for only 1,000 yards. The misleading addendum and the Port’s failure to supply materials and make decisions required Edwards to construct the railroad piecemeal and to shut down operations entirely for a short time during August, 1968. All this required Edwards to perform extra work not contemplated in the contract. The court found the contractor’s cost (minus $18,000 due to overmanning) for this extra work to be reasonable so awarded plaintiff recovery for the extra costs plus profit in quantum meruit.

*886 The court dismissed defendant’s third-party complaint against McDowell-Wellman because it found that' the defendant Port was equally responsible for the design errors.

Defendant’s first contention is that the trial court erred in finding that the Port caused the delay.' We disagree. A review of the record satisfies us that there is substantial evidence to support the court’s'finding that the Port did cause the delay. Where this court finds substantial evidence to support the finding of the trial court, we will not disturb it. Thorndike v. Hesperian Orchards, Inc., 54 Wn.2d 570, 343 P.2d 183 (1959).

Next defendant contends that the delay was not a breach of contract for which damages are recoverable because the general conditions of the contract provide that the contractor’s sole remedy in the event of owner-caused delay is a time extension. We disagree.

Paragraph 19 of the general conditions provides in relevant part:

[T]he contractor shall not be charged with liquidated damages or any excess cost when the delay in completion of the work is due:
(b) To unforseeable cause beyond the control and without the fault or. negligence of the contractor, including but not restricted to, acts of God, or of the public enemy, acts of the owner, acts of another contractor in the performance of a contract with the owner, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and severe weather.

Paragraph 19 states merely that the contractor will not be liable in damages in the event of a delay. Impliedly, therefore, the Port’s sole remedy in the event of a delay not caused by the contractor is a time extension. Neither paragraph 19 nor any other provision in the contract precludes the contractor from recovering damages caused by the owner’s delay.

Defendant’s next contention is that the trial court erred in its assessment of damages. Here the Port argues four matters: (1) the total reasonable cost to the plaintiff is not *887 the proper measure of damages, (2) the total cost of $706,918.42 was not shown to be reasonable, (3) the expense due to overmanning by plaintiff ($18,000), which was deducted from the total reasonable cost to the plaintiff, was not proven, and (4) the plaintiff was not entitled to overhead'and profit of $137,783.68.

We turn first to the proper measure of damages. Defendant contends that the proper measure of damages is the contract price plus the damage occasioned by the breach. Defendant would then require the plaintiff to show exactly what damage he suffered by the breach. If this were an ordinary breach of contract case we would agree. However, where an owner-caused delay has required the contractor to perform extra work not contemplated in the contract Washington cases have awarded recovery therefor in quantum meruit. These cases allow the contractor to recover the reasonable cost of performance where the delay caused by the owner is so substantial as to materially alter the contract. Bignold v. King County, 65 Wn.2d 817, 399 P.2d 611 (1965); Schuehle v. Seattle, 199 Wash. 675, 92 P.2d 1109 (1939).

In Bignold v. King County the contract called for a “cut and fill” plan of constructing a county road. The material excavated from one portion of the roadway was to be used for embankment purposes at other places. The plans specified how much extra fill material would be required.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

KWIK-LOK CORPORATION v. Pulse
702 P.2d 1226 (Court of Appeals of Washington, 1985)
Barnard v. Compugraphic Corp.
667 P.2d 117 (Court of Appeals of Washington, 1983)
Nelse Mortensen & Co. v. Group Health Cooperative
566 P.2d 560 (Court of Appeals of Washington, 1977)
S. L. Rowland Construction Co. v. Beall Pipe
540 P.2d 912 (Court of Appeals of Washington, 1975)
V. C. Edwards Contracting Co. v. Port of Tacoma
514 P.2d 1381 (Washington Supreme Court, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
503 P.2d 1133, 7 Wash. App. 883, 1972 Wash. App. LEXIS 1064, Counsel Stack Legal Research, https://law.counselstack.com/opinion/v-c-edwards-contracting-co-v-port-of-tacoma-washctapp-1972.