Reynolds Metals Co. v. Electric Smith Construction & Equipment Co.

483 P.2d 880, 4 Wash. App. 695, 1971 Wash. App. LEXIS 1428
CourtCourt of Appeals of Washington
DecidedApril 12, 1971
Docket466-41380-1
StatusPublished
Cited by33 cases

This text of 483 P.2d 880 (Reynolds Metals Co. v. Electric Smith Construction & Equipment Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Reynolds Metals Co. v. Electric Smith Construction & Equipment Co., 483 P.2d 880, 4 Wash. App. 695, 1971 Wash. App. LEXIS 1428 (Wash. Ct. App. 1971).

Opinion

James, J.

Reynolds Metals Company, a Delaware corporation, planned to expand its aluminum reduction plant located in, Longview, Washington. Through its contracting agent, Bechtel Corporation, Reynolds sought bids for the fabrication and assembly of the required bus system. Electric Smith Construction & Equipment Co. was the success *697 ful bidder. Under the terms of a “purchase order” which became the written contract, Reynolds was to supply the copper and aluminum components which Electric Smith agreed to fabricate and assemble. Reynolds agreed to pay Electric Smith for its labor and services the sum of $1,399,630.55.

By the terms of the contract, time was of the essence. Electric Smith was to begin to ship complete pot bus assemblies by October 1, 1967, and to reach and thereafter maintain a production rate of 20 assemblies per week by November 1,1967.

Electric Smith never met the agreed production schedule.

By a letter delivered on January 3, 1968, Electric Smith was notified that pursuant to the general conditions, Reynolds had cancelled the contract because of Electric Smith’s failure to meet the required production schedule. Coincident with the delivery of the letter of cancellation, Reynolds replevied the materials it had theretofore delivered to Electric Smith for its labor and services the sum of seeking compensatory damages, asserting that by its unilateral cancellation, Reynolds had breached the contract. Reynolds in turn sought damages alleging that Electric Smith had breached the contract by its failure to meet the contractual production schedule.

The submission of evidence required 27 days of trial. Three hundred eighty-nine exhibits, many of them multiple exhibits, were admitted. The statement of facts contains 3,900 pages.

Reynolds appeals from the judgment which dismissed its complaint with prejudice and awarded Electric Smith $345,828.97 as compensatory damages.

Appropriate assignments of error challenge the trial judge’s ultimate finding that Reynolds

totally breached its contract by a wrongful termination on January 3,1968 for the following reasons:

a. Reynolds Metals Company and Bechtel Corporation *698 substantially and materially contributed to the causes of Electric Smith failing to meet its production schedule.

Finding of fact 21.

The ways in which Reynolds and Bechtel had “substantially and materially contributed” to Electric Smith’s inability to perform are detailed in finding of fact 14. The various failures of performance by Reynolds and Bechtel are characterized in finding of fact 15:

Some of the delays occasioned by [Reynolds] and its agents as set forth in the immediately preceding paragraph were major in nature and some were minor, but the total effect leads to an inescapable conclusion that they did constitute a serious, substantial and material cause of the delay in the Electric Smith production schedule. Inspection interference was, in itself, a material cause of delay.

If a contract requires performances by both parties, one who would assert nonperformance by the other must establish his own performance. 17 Am. Jur. 2d Contracts § 355 (1964). Performance is a question of fact. Terry v. United States Fidelity & Guar. Co., 196 Wash. 206, 82 P.2d 532, 119 A.L.R. 1276 (1938).

Reynolds recognizes that, as an appellate court, we cannot retry factual issues. Evans v. Columbia Int'l Corp., 3 Wn. App. 955, 478 P.2d 785 (1970). Reynolds points out, however, that our review of the evidence must persuade us that the findings are supported by substantial evidence;. A major portion of Reynolds’ brief is devoted to an analysis of testimony and evidence which, in Reynolds’ view, would compel a finding contrary to that of the trial judge. We agree that the proper focus of our review of the evidence is to ascertain if substantial evidence supports the trial judge’s finding. We likewise agree with Reynolds that “[b]y ‘substantial evidence’ is meant that character of evidence which would convince an unprejudiced, thinking mind of the truth of the fact to which the evidence is directed.” Omeitt v. Department of Labor & Indus., 21 Wn.2d 684, 686, 152 P.2d 973 (1944). However, our exami *699 nation of the record goes no further than to determine whether there is substantial evidence to sustain the trial court’s findings. Stutz v. Moody, 3 Wn. App. 457, 476 P.2d 548 (1970). As an appellate court, we cannot weigh conflicting evidence. McGarvey v. Seattle, 62 Wn.2d 524, 384 P.2d 127 (1963).

Our review of the record satisfies us that the finding that Reynolds “substantially and materially contributed to the causes of Electric Smith failing to meet its production schedule” is supported by substantial evidence.

Reynolds further contends, however, that if it be conceded for the purpose of argument that Reynolds did substantially and materially contribute to Electric Smith’s failure to meet the required production schedule, Electric Smith nevertheless waived its “right to assert such excuses as a defense for its subsequent breach of contract.”

In support of this contention, Reynolds relies upon “Revision 4” to the contract, contending that it embodies a modification of the basic contract. Reynolds argues that by performing after agreeing to modify the contract, Electric Smith waived its right to rely upon Reynolds’ earlier breach in defense of its own later failure to meet the agreed production schedule.

According to 5 S. Williston, A Treatise on the Law of Contracts § 688 (3d ed. W. Jaeger 1961), it is generally held that when a contract not fully performed on either side is continued in spite of a known excuse, the right to rely upon the known excuse is waived. In the law of contracts, the term “waiver,” when used in connection with the required performance of a condition, is usually defined as the voluntary and intentional relinquishment of a known right. Ross v. Harding, 64 Wn.2d 231, 391 P.2d 526 (1964); 5 S. Williston, A Treatise on the Law of Contracts § 678 (3d ed. W. Jaeger 1961); 17 Am. Jur. 2d Contracts § 392 (1964). But, as Williston further points out,

Waiver is a troublesome term in the law. Its use is not confined to conditional contracts, and any satisfactory discussion of it must consider all its applications. It is used with different meanings and there are, therefore, *700 necessarily conflicting judicial statements as to its requisites.

5 S.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rebecca E Wolfe
E.D. Washington, 2023
Kittitas County v. Sky Allphin
Court of Appeals of Washington, 2022
Ohring v. UniSea Inc
W.D. Washington, 2021
AMERICAN SAFETY CASUALTY INS. CO. v. City of Olympia
137 P.3d 865 (Court of Appeals of Washington, 2006)
American Safety Casualty Insurance v. City of Olympia
133 Wash. App. 649 (Court of Appeals of Washington, 2006)
Mike M. Johnson, Inc. v. Spokane County
150 Wash. 2d 375 (Washington Supreme Court, 2003)
Mike M. Johnson, Inc. v. County of Spokane
78 P.3d 161 (Washington Supreme Court, 2003)
Mike M. Johnson, Inc. v. County of Spokane
49 P.3d 916 (Court of Appeals of Washington, 2002)
Mike M. Johnson, Inc. v. Spokane County
49 P.3d 916 (Court of Appeals of Washington, 2002)
Oregon Mutual Insurance v. Barton
109 Wash. App. 405 (Court of Appeals of Washington, 2001)
Oregon Mut. Ins. Co. v. Barton
36 P.3d 1065 (Court of Appeals of Washington, 2001)
Harting v. Barton
6 P.3d 91 (Court of Appeals of Washington, 2000)
Dombrosky v. Farmers Ins. Co. of Wash.
928 P.2d 1127 (Court of Appeals of Washington, 1997)
Dombrosky v. Farmers Insurance
928 P.2d 1127 (Court of Appeals of Washington, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
483 P.2d 880, 4 Wash. App. 695, 1971 Wash. App. LEXIS 1428, Counsel Stack Legal Research, https://law.counselstack.com/opinion/reynolds-metals-co-v-electric-smith-construction-equipment-co-washctapp-1971.