Terry v. United States Fidelity & Guaranty Co.

82 P.2d 532, 196 Wash. 206
CourtWashington Supreme Court
DecidedAugust 31, 1938
DocketNo. 27142. Department Two.
StatusPublished
Cited by3 cases

This text of 82 P.2d 532 (Terry v. United States Fidelity & Guaranty Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Terry v. United States Fidelity & Guaranty Co., 82 P.2d 532, 196 Wash. 206 (Wash. 1938).

Opinion

Blake, J.

— This is an action on a contractor’s bond, executed pursuant to Rem. Rev. Stat., § 1159 [P. C. *207 § 9724], to secure persons performing labor and furnishing material in connection with the construction of a public highway. From judgment entered on a verdict in favor of plaintiff, defendant appeals.

The bond was executed by appellant as surety for Bjork Bros., Pearson & Strom, co-partners, to whom we shall refer as Bjork, who had a contract from the state for certain tunnel and rock work on state road No. 5, in the vicinity of the Teiton dam. The contractors entered into a contract with respondent for the removal of about 12,000 cubic yards of material between stations 748 and 751+35. The excavation between these stations was through solid rock. Under the contract, the contractors agreed to do all drilling, furnish explosives, and do all blasting, at their own expense, without interfering with respondent in his operations in removing the material. Respondent was to receive thirty-eight cents per cubic yard for material moved. It was agreed “that the quantities involved shall be estimated by the resident engineer in charge.”

September 21, 1936, respondent moved a steam shovel onto the job. Before the work contemplated was completed, a controversy arose between the parties, which finally resulted in the contractors ordering respondent off the job early in December, 1936. On December 21st, the resident engineer submitted to the contractors an estimate of the material removed by respondent, fixing the quantity at 8,069 cubic yards. On the basis of this estimate, respondent was entitled, Under the contract, to $3,066.22, of which he had theretofore received $1,980.

Respondent brought this suit against the surety company, setting up two causes of action: (1) For recovery of the balance due for material actually removed; (2) for damages, by way of loss of profits, by reason of the fact that he was prevented by the con *208 tractors from removing some 4,742 cubic yards additional material contemplated by the contract. The jury returned a verdict on the first cause of action for $748.27, and for $348.33 on the second. Judgment was entered accordingly.

The assignments of error challenge (1) the sufficiency of the evidence to sustain any verdict for plaintiff; (2) the sufficiency of the evidence to sustain the amount of the verdict on the first cause of action; (3) the liability of the bond, in any case, on the second cause of action.

First: The challenge to the sufficiency of the evidence is based on the theory that respondent breached the contract. We shall not undertake to review the evidence which appellant adduced, tending to support that theory. We may say, however, that it was sufficient to support a verdict for appellant, had the jury accepted it at face value. On the other hand, we think that respondent’s theory that Bjork breached the contract is amply supported by the evidence.

Briefly, from the standpoint of respondent, the evidence shows that respondent started operations September 21, 1936, and continued uninterruptedly until October 23rd; that he then ceased operations, because he had caught up with Bjork’s blasting operations and there was no more material to be moved; that he was ready at all times to proceed with the job, if and when Bjork proceeded with the blasting; that he received a written demand from Bjork that he resume operations not later than six p. m., November 14th; that he returned to the job about December 1st, ready and willing to carry on the work under his contract, Bjork having, for reasons unnecessary to state here, waived strict compliance with the demand; that *209 no blasting had been done since he ceased operations on October 23rd.

It is admitted that no blasting was done by Bjork between October 23rd and December 14th and 15th. In view of the provision in the contract to the effect that Bjork would do the blasting so as not to interfere with the progress of respondent’s operations, we think the foregoing evidence was sufficient to make the question of the breach of the contract one for the jury to determine.

Second: As we have seen, the resident engineer estimated that respondent had moved 8,069 cubic yards of material. He was called as a witness and testified in accordance with his estimate. On cross-examination, certain admissions were elicited from him, which cast doubt on the accuracy of his estimate. It appears'that the estimate was not‘entirely harmonious with monthly estimates he made to the highway department as to the amount of material moved by Bjork between stations 748 and 751+35 before respondent commenced operations. There seems to be no dispute in the evidence that he included in the Terry estimate a thousand cubic yards or more of material which Bjork removed after respondent ceased operations. We think, however, it is apparent from the verdict on the first cause of action that the jury took account of the latter discrepancy.

As to the apparent discrepancy between the estimates made to the highway department on Bjork’s account and the estimate made as between Bjork and respondent, the resident engineer testified that, in his monthly estimates to the highway department before respondent commenced operations, he made allowances for greater quantities of material than were actually moved. He and other witnesses testified that this was customary, in dealing with contractors-of unquestioned *210 responsibility, and was done to assist them in adequately financing and carrying on their work.

Appellant insists that the estimates made to the highway department are official and therefore binding. There is nothing in the contract that makes them so. The provision in the contract, leaving to the resident engineer the determination of the quantity of material moved by respondent, is general in terms. It was not stipulated that his estimate be conclusive. And it was not so treated in the trial of the case. Its accuracy or inaccuracy was clearly a matter to be determined by the jury.

In this connection, appellant complains that the court committed error, in that evidence was admitted of a

“. . . custom to the effect that a subcontractor was entitled to be paid for yardage not actually removed by the subcontractor, but removed by the principal contractors before contractual relations ever arose between the parties.”

Whatever error was committed in admitting such evidence was not prejudicial. For the court specifically instructed the jury:

“You cannot allow him [respondent] compensation for any yardage which the principal contracting firm removed from the stations upon which the plaintiff worked prior to the time that the plaintiff commenced his operations.”

See McCormick v. Tappendorf, 51 Wash. 312, 99 Pac. 2.

Third: Whether unliquidated damages for breach of contract may be recovered against such a bond as this, is a question of first impression in this state. A number of cases have been cited which are thought to bear one way or the other upon the question.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reynolds Metals Co. v. Electric Smith Construction & Equipment Co.
483 P.2d 880 (Court of Appeals of Washington, 1971)
Lucas v. Western Casualty & Surety Co.
176 F.2d 506 (Tenth Circuit, 1949)
Maryland Casualty Co. v. City of Seattle
118 P.2d 416 (Washington Supreme Court, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
82 P.2d 532, 196 Wash. 206, Counsel Stack Legal Research, https://law.counselstack.com/opinion/terry-v-united-states-fidelity-guaranty-co-wash-1938.