Burton v. F. A. Seifert & Co.

61 S.E. 933, 108 Va. 338, 1908 Va. LEXIS 40
CourtSupreme Court of Virginia
DecidedJune 11, 1908
StatusPublished
Cited by24 cases

This text of 61 S.E. 933 (Burton v. F. A. Seifert & Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Burton v. F. A. Seifert & Co., 61 S.E. 933, 108 Va. 338, 1908 Va. LEXIS 40 (Va. 1908).

Opinion

Cardwell, J.,

delivered the opinion of the court.

This is a writ of error to the judgment of the Circuit Court of the city of Richmond, in an action of debt, and for con[346]*346venience the plaintiffs in error, W. O. & C. G. Burton, a partnership, will he spoken of in this opinion as “the Burtons,” and the Frank A. Seifert Plastic Belief Company, a corporation, as “Seifert & Co.”

The Burtons being the lowest bidders for the work of constructing two United States government buildings at the St. Louis Purchase Exposition, St. Louis, Mo., obtained a contract, dated November 20, 1902, through H. A. Taylor, acting secretary of the treasury, to construct said buildings, furnish the material therefor, etc., as required by the plans and specifications furnished by the government, the contract price for the work, etc., being two hundred and sixty-eight thousand, nine hundred and eighty dollars ($268,980). The Burtons were required to execute a bond in the penalty of one hundred and thirty-five thousand dollars, with surety to be approved by H. A. Taylor, acting secretary, &c.; and accordingly they, on the 26th day of November, 1902, as principals, and the Virginia Trust Company, as surety, executed the required bond, payable to H. A. Taylor, acting secretary of the treasury, acting for and on behalf of the United States government. One of the conditions of the bond was that the Burtons should “promptly make payment to all persons supplying them with labor or materials in the prosecution of the work contemplated by said contract,” which bond was given in pursuance of the Federal Statute approved August 13, 1894. 28 Stat. 278 (U. S. Comp. St. 1901, p. 2523).

The buildings which the United States government desired to .construct at the St. Louis exposition were of a temporary character, and it was only intended that they should last about. eight months. The outsides were composed' of plaster, plaster of paris, and “staff” work, such as is generally used upon temporary structures, which plaster, staff work, etc., was to he painted with weatherproof paint.

The Burtons made a contract with Seifert & Co., whereby Seifert & Co., in consideration of the sum of $53,696, agreed to furnish the labor and material necessary for and to com[347]*347píete all the plastering, plain and ornamental staff work, and all exterior cement work (excepting foundations for steel trusses) of said United States government buildings, in strict compliance with the plans and specifications, drawings and details, as prepared by Jno. Knox Taylor, supervising architect for the United States government.

One of these buildings — the “fisheries building” — was first completed, and no claim or dispute between the Burtons and Seifert & Co. ever arose over that work. The other work, known as the “government building,” was begun about the 1st of October, 1903, and several letters passed between the Burtons and Seifert & Co. as to the delay in and slow progress of the work undertaken by the latter, but these letters, while a part of the history of the transaction, are, so far as they relate to the question of delay, of no importance, as the government made no claim against the Burtons for delay, nor did they make any such claim against Seifert & Co. True, the Burtons on April 19, 1904, wrote Seifert & Co. that some of the plaster had fallen down, but this was remedied, and in the early part of May, 1904, the work was completed, the building accepted by the government, and the Burtons were paid for it the contract price on May 19, 1904.

During the progress of the work, the Burtons made to Seifert & Co. partial payments, amounting to about $48,556, but after many efforts, by correspondence between the parties running from about May 13, 1904, to January 9, 1905, for a settlement, the payment of the balance claimed by Seifert & Oo. on the contract price for the work done by the company was refused, and this suit was brought in the name of the United States of America against the Burtons and the Virginia Trust Oo., surety, to recover for the use and benefit of Seifert & Oo. the balance claimed by the latter of the Burtons, the trial of the case resulting in a verdict and judgment in favor of Seifert & Co. for the sum of $4,407, with legal interest thereon from May 19, 1904, until paid.

[348]*348A number of letters that passed between these parties were introduced in evidence at the trial. The letters of Seifert & Co. merely show efforts to get a settlement, while the Burtons set forth their causes of complaint. In their letters, the Burtons only claimed three specific offsets, viz.: $416.99 for insurance placed on the work; $400 for certain work omitted by order of the g’overnment officer; and $75 for water charges; but they also refused to pay because some of the plaster began to fall and the government ordered that it be replaced. The cause of such falling of the plaster was, as Seifert & Co. contended, not from any bad workmanship done or bad material used by it, but because the Burtons painted the plaster with an improper paint, and because they did not place tin on certain places as required by their contract with the government; while the contention of the Burtons was, that Seifert & Co. should restore the plaster, no matter what caused it to fall, under Seifert & Co.’s guarantee as to the plaster. After this suit was brought, however, the Burton’s claimed not only the items of offset mentioned, but pleaded an offset of $5,250.99 for furnishing the scaffold used by Seifert & Co. in putting on the plaster and staff work.

At the trial, both sides agreed that Seifert & Co. did some extra work, amounting in the aggregate to $268.99, which was to be added to the original contract price, making a total of $53,964.99; and it was also agreed as to the credits to which the Burtons were entitled for partial payments during the progress of the work.

It is clear from the record and the finding of the jury that they rejected all items for work which Seifert & Co. did not demand when seeking settlement out of court, and allowed the Burtons the three items of credit claimed as to insurance, work omitted by order of the government’s officer, and for water bill, but disallowed their claim of $5,250.99, for furnishing the scaffold used by Seifert & Co., and also their claim for credit as to repairs done to the plaster after May 19, 1904, when the government accepted and paid for the building.

[349]*349We are asked to review and reverse the judgment of the •circuit court because of its errors — (1) in overruling the demurrer to the declaration; (2) in rejecting or admitting certain evidence at the trial; (3) in misdirecting the jury by instructions given them; and (4) in refusing to set aside the verdict and award plaintiffs in error a new trial.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Melissa Nanette Diaz v. Commonwealth of Virginia
Court of Appeals of Virginia, 2024
Peter Timothy Gionis v. Commonwealth of Virginia
Court of Appeals of Virginia, 2022
James Jesus Montgomery v. Commonwealth of Virginia
Court of Appeals of Virginia, 2022
Deon Christopher Cobb v. Commonwealth of Virginia
Court of Appeals of Virginia, 2013
Rodney Lamar Carter v. Commonwealth of Virginia
Court of Appeals of Virginia, 2012
Resk v. Roanoke County
73 Va. Cir. 272 (Roanoke County Circuit Court, 2007)
Taylor v. Commonwealth
604 S.E.2d 103 (Court of Appeals of Virginia, 2004)
Ragone v. Waldvogel, Poe, & Cronk Real Estate Group, Inc.
54 Va. Cir. 581 (Roanoke County Circuit Court, 2001)
Price v. Price
355 S.E.2d 905 (Court of Appeals of Virginia, 1987)
Washington v. Commonwealth
217 S.E.2d 815 (Supreme Court of Virginia, 1975)
Chesterfield, Etc. v. Board of Zoning, Etc.
209 S.E.2d 925 (Supreme Court of Virginia, 1974)
Chesterfield Civic Ass'n v. Board of Zoning Appeals
209 S.E.2d 925 (Supreme Court of Virginia, 1974)
Boggs v. Duncan
121 S.E.2d 359 (Supreme Court of Virginia, 1961)
City of Norfolk v. Stephenson
38 S.E.2d 570 (Supreme Court of Virginia, 1946)
Royal Indemnity Co. v. Woodbury Granite Co.
101 F.2d 689 (D.C. Circuit, 1938)
Terry v. United States Fidelity & Guaranty Co.
82 P.2d 532 (Washington Supreme Court, 1938)
Fulghum & Union Indemnity Co. v. State
109 So. 644 (Supreme Court of Florida, 1926)
Waddell v. Trowbridge
119 S.E. 290 (West Virginia Supreme Court, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
61 S.E. 933, 108 Va. 338, 1908 Va. LEXIS 40, Counsel Stack Legal Research, https://law.counselstack.com/opinion/burton-v-f-a-seifert-co-va-1908.