Nelse Mortensen & Co. v. Group Health Cooperative

566 P.2d 560, 17 Wash. App. 703, 1977 Wash. App. LEXIS 1628
CourtCourt of Appeals of Washington
DecidedJune 6, 1977
Docket4034-1
StatusPublished
Cited by17 cases

This text of 566 P.2d 560 (Nelse Mortensen & Co. v. Group Health Cooperative) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Nelse Mortensen & Co. v. Group Health Cooperative, 566 P.2d 560, 17 Wash. App. 703, 1977 Wash. App. LEXIS 1628 (Wash. Ct. App. 1977).

Opinion

Pearson, J.

Group Health Cooperative of Puget Sound (Group Health) appeals from a judgment totalling *704 $614,782.77 for damages due to delays in the remodeling and construction of additions to Group Health Hospital in Seattle. The judgment was awarded to the construction project's general contractor, Nelse Mortensen & Co. (Mortensen), and to subcontractors Berg Plastering, Inc. (Berg), Industrial Electric-Seattle, Inc. (Industrial Electric), and W. L. Henson Co., Inc. (Henson), on a theory of semitortious interference by Group Health with the contractors' performance of their work under the contract. The dispositive issue in this appeal is whether the construction delays caused by the owner, Group Health, and its architect were so unreasonable as to justify disregard of certain contractual clauses providing for no damages due to owner-caused delay. We conclude the trial court erred in holding that the contract was not intended to encompass the delays which occurred in this case, and we reverse.

The Facts of the Case

There is no question the construction project undertaken by Mortensen was difficult and complex. The contract dated May 1, 1969, called for a completion date of November 8, 1971. Construction was planned in four distinct phases: (1) The first 18 months were to be devoted to demolition and excavation of the site of the new structure, erection of an 8-story building, and interior finishing of its two basements and third floor. (2) The next 4 months were for completion of the remaining floors of the addition, plus demolition and remodeling of lower levels of the existing hospital—which could only begin after certain areas under phase 1 were completed and available for hospital activities displaced by the phase 2 remodeling. (3) Phase 3 was to take 4 months for demolition and remodeling of the surgery areas of the hospital's fourth floor. Again, however, commencement of this phase depended upon completion of the new surgery areas under construction in phases 1 and 2. (4) The final phase, also planned for 4 months, involved demolition and remodeling of the fifth floor of the old hospital, which could begin only after completion of new areas *705 in phases 2 and 3 to accommodate the nursery, obstetrics, and delivery room activities displaced by phase 4. The hospital could maintain patient care with minimum disruptions by proceeding with construction by phases, which required detailed scheduling for the transfer of facilities from the old structure to the new.

There were additional complicating factors known to the parties before the project began. The new structure was to adjoin the old, thereby necessitating level connections between the two buildings and limiting the ceiling spaces in the new building to the same sizes as existed in the old hospital. The new building was to be fully air conditioned, which created uncommon problems of fitting the heating and cooling system into smaller ceiling cavities than those found in most modern construction. A city height limitation on new buildings made it necessary to fill the available space with as much new construction as possible in order to obtain the desired amount of additional square footage; this was expected to cramp the construction site all the more. In addition, two streets bordering the site could not be closed off because they were major arterials.

Besides the unusual difficulties involved in this project, hospital construction is inordinately complex because provision must be made for such factors as extensive plumbing work and electrical circuitry, installation of tracks to supply intravenous feeding and oxygen and other gases, a complete communications network, and various other medical diagnostic and treatment apparatus.

Mortensen had built hospitals before and knew, or should have known, of the complexities common to hospital construction, and of the difficulties inherent in the Group Health job. Despite these difficulties, Mortensen believed the job could be completed in 2 years. Nevertheless, in accordance with the contract, it submitted to the architects, The Richardson Associates, a detailed "critical path schedule" calling for a November 8, 1971, completion date. This was the only schedule maintained by Mortensen on the job site to monitor and schedule the progress of the work. The *706 architect testified that he allowed at least three formal extensions of the contract completion date: an initial 41-day extension due to a delay in City of Seattle approval of the site excavation; a 93-day extension for labor disputes in the summer of 1971; and a 5-day extension caused by bad weather in December 1971. In its oral opinion, the trial court indicated that the contract completion date had been extended to April 8, 1972. 1 The project was substantially completed on June 30, 1972—less than 3 months later.

The trial court based its decision on a finding that Group Health and its architect were responsible for unreasonable delays and that Mortensen and the subcontractors were entitled to recover additional costs and profit caused by Group Health's "unreasonable" interference with their timely performance of the contract. In essence, the court decided that the delays attributable to the hospital were so substantial that they were outside the contemplation of the parties and their contractual terms relevant to delays and extra compensation, thereby warranting a recovery in quantum meruit. We must examine the contract to review this decision. The basic contract documents are standard American Institute of Architects (AIA) forms.

The Contract Provisions

Section 8.2.2, as amended, provides as follows:

8.2.2 The contractor shall begin the work on the date of commencement as defined in subparagraph 8.1.2. He shall carry the work forward expeditiously with adequate forces and shall complete it within the contract time.
It is the responsibility of the contractor to complete the work within the contract time. The owner makes no promise or representation that this can or will be done.

Section 8.3 provides:

Delays and Extensions of Time
8.3.1 If, however, the contractor is delayed at any time in the progress of the work by any of the following causes, the contract time shall be extended for such reasonable *707 time as the architect shall determine. The contractor agrees to complete the work within the contract time as thus extended. Such extensions shall postpone the beginning of period for payment of liquidated damages but they and the events producing them shall not be ground for claim by the contractor of damages or for additional costs, expenses, overhead or profit or other compensation.
.1 Floods, fire, strikes, lockouts, war, acts of the public enemy, acts of God.
.2 Change Orders
.3 Acts of performance or delays in performance by other contractors employed by owner or their subcontractors.
.4

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Davidow v. Zalnatrav Inc
W.D. Washington, 2024
Scoccolo Const., Inc. v. City of Renton
9 P.3d 886 (Court of Appeals of Washington, 2000)
Scoccolo Construction, Inc. v. City of Renton
102 Wash. App. 611 (Court of Appeals of Washington, 2000)
CKP, Inc. v. GRS Construction Co.
821 P.2d 63 (Court of Appeals of Washington, 1991)
Hensel Phelps Construction Co. v. King County
787 P.2d 58 (Court of Appeals of Washington, 1990)
Interlake Porsche + Audi, Inc. v. Bucholz
728 P.2d 597 (Court of Appeals of Washington, 1986)
Lyall v. DeYoung
711 P.2d 356 (Court of Appeals of Washington, 1985)
Donald B. Murphy Contractors, Inc. v. State
696 P.2d 1270 (Court of Appeals of Washington, 1985)
Osolo School Buildings, Inc. v. Thorleif Larsen & Son of Indiana, Inc.
473 N.E.2d 643 (Indiana Court of Appeals, 1985)
Modern Builders, Inc. v. Manke
615 P.2d 1332 (Court of Appeals of Washington, 1980)
Allen-Howe Specialties Corp. v. U. S. Construction, Inc.
611 P.2d 705 (Utah Supreme Court, 1980)
Lester N. Johnson Co. v. City of Spokane
588 P.2d 1214 (Court of Appeals of Washington, 1978)
CHRISTIANSEN BROTHERS v. State
25 Cont. Cas. Fed. 83 (Washington Supreme Court, 1978)
Nelse Mortensen & Co. v. Group Health Cooperative of Puget Sound
586 P.2d 469 (Washington Supreme Court, 1978)
Cheney v. City of Mountlake Terrace
583 P.2d 1242 (Court of Appeals of Washington, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
566 P.2d 560, 17 Wash. App. 703, 1977 Wash. App. LEXIS 1628, Counsel Stack Legal Research, https://law.counselstack.com/opinion/nelse-mortensen-co-v-group-health-cooperative-washctapp-1977.