Donald B. Murphy Contractors, Inc. v. State

696 P.2d 1270, 40 Wash. App. 98
CourtCourt of Appeals of Washington
DecidedMarch 14, 1985
Docket6440-5-II
StatusPublished
Cited by13 cases

This text of 696 P.2d 1270 (Donald B. Murphy Contractors, Inc. v. State) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Donald B. Murphy Contractors, Inc. v. State, 696 P.2d 1270, 40 Wash. App. 98 (Wash. Ct. App. 1985).

Opinion

Petrich, J.

Plaintiff Donald B. Murphy Contractors, Inc. (DBM), after a trial to the court, appeals from the judgment which held the State of Washington free from liability for "impact costs" for repairs and reconstruction on two highway construction projects damaged by flood- *100 waters, as well as impact costs for various change orders and stop work orders on the projects.

The issues on appeal are:

1. Whether the State's plans and specifications of certain culverts which were unable to handle the excess flow of water were in breach of the State's implied warranty of design.

2. Whether the "changed conditions" clause of the contracts, which entitled the contractor to an equitable adjustment for unanticipated site conditions, may be invoked by unusual weather conditions encountered during the course of construction.

3. Whether portions of the project damaged by the flood-waters were temporary work with consequence that the risk of loss was on the contractor rather than the State.

4. Whether the contractor is entitled to indirect or impact damages due to delays arising from various change orders and stop work orders issued by the State.

5. Whether statements by certain employees of the State were properly excluded because they were hearsay and not admissions under ER 801(d)(2).

We affirm.

In 1975, DBM contracted with the State to build two highway construction projects, Nos. 9840 and 9973. The two contracts provided for the construction of new adjoining sections of Interstate 90 just east of Issaquah, Washington. Both projects were similar in nature. They called for construction of new traffic lanes, building new bridges, demolishing old bridges, and constructing several detours. Heavy rain in early December 1975 damaged both projects and gave rise to the present dispute.

The State provided all plans, designs, and specifications for both projects. Contract 9840 included changing the course of East Issaquah Creek by diverting the creek through a 96-inch steel culvert under the existing freeway. Contract 9973 included installing another 96-inch steel culvert in the creek bed to serve as a detour while a bridge was demolished and replaced. Both culverts were in place on *101 December 2, 1975.

After several days of heavy rain and the melting of snow, East Issaquah Creek reached flood stage on December 2 and 3, 1975. The flow of water in the creek during these 2 days peaked at the highest volume ever recorded. In addition to the tremendous flow of water, the flood carried a significant amount of debris. In order to save property owners and work downstream, the State ordered DBM to excavate the culvert on No. 9840 late in the night of December 2, 1975. The pressure behind the remaining culvert on No. 9973 caused the culvert to fail and wash downstream on December 3, 1975.

Pursuant to change orders, the State paid DBM for the direct cost of replacing the culvert in No. 9973 in a substantially modified form, as well as the direct cost of numerous other change orders and stop work orders. Many, but not all, of the orders were issued to remedy the problems caused by the failure of the culverts. DBM sought to recover damages stemming from the indirect or impact costs attributed to the delays caused by the flood damage as well as additional compensation for delay attributable to change orders not directly related to the flood damage. According to DBM the impact cost of the culvert failures and subsequent change orders and stop work orders totaled $662,192. DBM contended at trial 1 that the State was liable as a matter of law (1) for the breach of its implied warranty of design because the specified culverts were inadequate to handle the flow of water in the creek experienced on December 2 and 3, (2) under the "changed conditions" clause of the contract, which entitles the contractor to an equitable adjustment for unanticipated site conditions, and (3) under the "changes" clause of the contract for the impact costs arising from the State's change orders and stop work orders.

We consider first DBM's contention that the *102 State breached its implied warranty of design because the culverts failed to handle the floodwaters of December 2 and 3, 1975. By furnishing the designs and specifications calling for the 96-inch culverts, the State warrants by implication that the designs are "sufficient] for the purpose in view." Prier v. Refrigeration Eng'g Co., 74 Wn.2d 25, 29, 442 P.2d 621 (1968). Here, the trial court found that the designs for the culverts met a reasonable design standard and failed only because of an unprecedented flood—an act of God— and concluded, therefore, that the State had not breached the implied warranty of design. DBM fails either to assign error to all of the court's findings upon this issue or to set forth verbatim the findings it challenges. Therefore, the court's findings are verities on appeal. Thomas v. French, 99 Wn.2d 95, 659 P.2d 1097 (1983); Hindquarter Corp. v. Property Dev. Corp., 95 Wn.2d 809, 631 P.2d 923, 23 A.L.R.4th 897 (1981).

However, DBM contends that the reasonableness of the culverts' design is irrelevant and that the failure of the culverts is a breach of the implied warranty of design as a matter of law and renders the State strictly or absolutely liable for the flood damage.

We disagree with DBM's contention that the implied warranty of design is the equivalent of strict or absolute liability. As noted above, Washington law requires only that the design be sufficient for the intended purpose. Prier v. Refrigeration Eng'g Co., supra. Further, the main case cited by DBM in support of its contention, United States v. Spearin, 248 U.S. 132, 63 L. Ed. 166, 39 S. Ct. 59 (1918), holds only that a design must be "defective" for there to be a breach of the implied warranty. Later federal cases which have applied Spearin have stated that under the implied warranty of design, the owner warrants only that if the design is followed, a satisfactory result will follow. See, e.g., Hol-Gar Mfg. Corp. v. United States, 360 F.2d 634 (Ct. Cl. 1966). Moreover, in Praxis-Assurance Venture, 81-1 B.C.A. ¶ 15,028 (Armed Servs. 1981), it is stated at page 74,357:

*103 It is unrealistic, at least insofar as this type of work is concerned, to expect and demand that the design be prepared so as to cover the worst possible circumstances. The law only mandates that the design be adequate to handle the normal circumstances which history and experience has shown can reasonably be expected to be encountered.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Grant County Port District No. 9 v. Washington Tire Corp.
349 P.3d 889 (Court of Appeals of Washington, 2015)
Davis v. Cox
325 P.3d 255 (Court of Appeals of Washington, 2014)
Kent L. And Linda Davis v. Grace Cox
Court of Appeals of Washington, 2014
Basin Paving Co. v. Mike M. Johnson, Inc.
107 Wash. App. 61 (Court of Appeals of Washington, 2001)
RAINIER NATIONAL BANK v. Wells
829 P.2d 1168 (Court of Appeals of Washington, 1992)
Douglas Northwest, Inc. v. Bill O'Brien & Sons Construction, Inc.
828 P.2d 565 (Court of Appeals of Washington, 1992)
Passovoy v. Nordstrom, Inc.
758 P.2d 524 (Court of Appeals of Washington, 1988)
Codd v. Stevens Pass, Inc.
725 P.2d 1008 (Court of Appeals of Washington, 1986)
Molander v. Raugust-Mathwig, Inc.
722 P.2d 103 (Court of Appeals of Washington, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
696 P.2d 1270, 40 Wash. App. 98, Counsel Stack Legal Research, https://law.counselstack.com/opinion/donald-b-murphy-contractors-inc-v-state-washctapp-1985.