Hartman v. Port of Seattle

389 P.2d 669, 63 Wash. 2d 879, 1964 Wash. LEXIS 557
CourtWashington Supreme Court
DecidedFebruary 27, 1964
Docket36591
StatusPublished
Cited by36 cases

This text of 389 P.2d 669 (Hartman v. Port of Seattle) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hartman v. Port of Seattle, 389 P.2d 669, 63 Wash. 2d 879, 1964 Wash. LEXIS 557 (Wash. 1964).

Opinion

Hunter, J.

This is an appeal from a judgment for the plaintiff (respondent), David Hartman, entered in an action brought against the defendant (appellant), Port of Seattle, to recover damages for personal injuries.

In 1958 and 1959, the Port of Seattle was expanding the Seattle-Tacoma Airport and the Service Electric Company, Inc., was awarded a contract to perform certain wiring. The electrical power, which up to this time had supplied the airport facilities, was brought onto the airport property through power lines called a “feeder system.” This “feeder system” consisted of three electrical cables that traveled underground through a series of manholes connected by underground ducts. The Service Electric Company contracted to replace the old cables with larger cables that were capable of carrying four times more current. The system was put in approximately 10 years earlier when the airport was built. The cables were designed to last 30 to 50 years.

On the day of the injury, the plaintiff, who is a journeyman electrician employed by the Service Electric Company, and his foreman were engaged in the process of identifying the cable. The foreman was in manhole No. 12 and the *881 plaintiff was in manhole No. 13. The identification was made by pulling back and forth on the cables and marking them with pieces of tape. The power was on, and the cables were each carrying the normal operating voltage, 4,160 volts. As they were performing the identification, the foreman heard the plaintiff scream and immediately thereafter the plaintiff was found face down on the floor of the manhole. He was removed and found to have been badly burned on his head, left arm, back and left leg. The palm of the left hand was very shrunken and black. Thereafter, one of the cables was found to have a burned spot on it.

At the time of the accident, the plaintiff was not using any rubber gloves, insulated platform, or electrician’s gloves. The defendant’s resident engineer had observed the work being done without these safety precautions. The plaintiff did not remember whether he was pulling on the cable.

The defendant presented expert testimony that the identification of the cable should not have been made with the power on; that pulling barehanded on energized cable carrying 4,160 volts is not a customary practice used by electricians to identify cable; and that the use of protective equipment is mandatory. On the other hand, plaintiff produced expert evidence that the cable of this age, make and model was widely used and was safe to touch without gloves. A journeyman electrician testified that it would be customary for journeymen electricians in the plaintiff’s union local to handle this cable barehanded.

It was shown that 6 months before this accident the defendant’s maintenance electricians observed an unusual spot in the insulation on a wire in manhole No. 13. When they cut the lacings which bound the cables together and started to separate them, there was a large flash as the current arced to a nearby pull wire causing the main north feeder circuit breaker to trip or “kick out.” The cable was then spliced and wrapped with high voltage tape. This was a different cable, but in the same manhole, as the one causing injury to the plaintiff. Neither the plaintiff nor his foreman was ever advised of the prior arcing incident. *882 The expert testimony was in conflict as to whether the plaintiff’s burn came from a defect in the insulation which was caused by the prior arcing in the adjacent cable. Plaintiff’s experts testified that a “hi-pot” test should have been performed and that if one had been performed it probably would have revealed the defect that caused the plaintiff’s burn.

The plaintiff brought this action alleging that the defendant was negligent (1) in failing to provide or maintain a safe place for the plaintiff to work; and (2) in failing to warn plaintiff of a condition unreasonably dangerous to plaintiff of which the defendant knew, or reasonably should have known, and of which the plaintiff neither knew, nor reasonably should have known. Defendant denied negligence and alleged that the plaintiff was guilty of contributory negligence (1) by handling high-tension electrical cables without taking adequate safety precautions and without using safety equipment; and (2) in attempting to mark high-tension electrical cables in a negligent and careless manner not in conformance with the standard of care required under the circumstances and conditions existing at the time. The jury returned a verdict in favor of the plaintiff upon which judgment was entered. The defendant appeals.

The defendant assigns error to the refusal of the trial court to find that the evidence was insufficient to establish the defendant’s negligence as a matter of law. The plaintiff was an employee of an independent contractor, and as such enjoyed the status of an invitee. The duty owed to an invitee is to exercise reasonable care to maintain the premises in a reasonably safe condition, or to warn the invitee of any danger which is known or discoverable by a reasonable inspection on the part of the occupier and not known or not discoverable by the invitee using reasonable care for his own protection. Greenleaf v. Puget Sound Bridge & Dredging Co., 58 Wn. (2d) 647, 364 P. (2d) 796 (1961); Restatement, Torts § 343. The defendant argues that the plaintiff failed to produce any evidence that there was a condition which the defendant knew, or reasonably *883 should have known, that involved an unreasonable risk to the plaintiff other than that inherent in the work.

This argument is not supported by the record. There was evidence in the record from which the jury could conclude that the prior arcing incident in manhole No. 13 did affect the other cables in the manhole. Plaintiff’s expert, Warren Wehmeyer, a consulting professional engineer, testified that where there is a failure in a cable, a good deal of heat energy is transmitted to the adjacent cables and that such heat energy would have a detrimental effect on the insulation of the adjacent cables. Once the insulation is perforated, moisture and dirt can enter and travel along the interior of the cable, causing a weak point to occur in the insulation. Here no tests were made on the adjacent cables following the first arcing to ground incident. Wehmeyer testified that if a “hi-pot” test had been performed, there is reasonable probability that the weak point would have been discovered. He said the normal custom is to make such a test. The trial court correctly refused to find that the evidence was insufficient to establish the defendant’s negligence as a matter of law.

The defendant contends that the trial court erred when it refused to find that the plaintiff was contributorily negligent as a matter of law. The defendant submits that the plaintiff handled these high-tension electrical cables without taking adequate safety precautions, and that he was, therefore, negligent when he attempted to identify the cables.

The evidence most favorable to the plaintiff does not justify this conclusion. Gordon Bailey, an expert witness who was an electrical construction foreman, testified that it was the general practice to handle unshielded cable carrying 4,160 volts with bare hands.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Farias v. United States
41 F. App'x 122 (Ninth Circuit, 2002)
Kamla v. Space Needle Corp.
105 Wash. App. 123 (Court of Appeals of Washington, 2001)
Diversified Development & Investment, Inc. v. Heil
889 P.2d 1212 (New Mexico Supreme Court, 1995)
Codd v. Stevens Pass, Inc.
725 P.2d 1008 (Court of Appeals of Washington, 1986)
Donald B. Murphy Contractors, Inc. v. State
696 P.2d 1270 (Court of Appeals of Washington, 1985)
Boeke v. International Paint Co.
620 P.2d 103 (Court of Appeals of Washington, 1980)
Lamborn v. Phillips Pacific Chemical Co.
575 P.2d 215 (Washington Supreme Court, 1978)
Ball v. Smith
540 P.2d 906 (Court of Appeals of Washington, 1975)
Hansen v. Wightman
538 P.2d 1238 (Court of Appeals of Washington, 1975)
Sons of Norway v. Boomer
519 P.2d 28 (Court of Appeals of Washington, 1974)
Avery v. State
514 P.2d 637 (Alaska Supreme Court, 1973)
Nerbun v. State
506 P.2d 873 (Court of Appeals of Washington, 1973)
Golding v. United Homes Corp.
495 P.2d 1040 (Court of Appeals of Washington, 1972)
Baltzelle v. Doces Sixth Avenue, Inc.
490 P.2d 1331 (Court of Appeals of Washington, 1971)
Thorpe v. Boeing Co.
490 P.2d 448 (Court of Appeals of Washington, 1971)
Miller v. Argus Publishing Co.
490 P.2d 101 (Washington Supreme Court, 1971)
Tex Brotherton, Inc. v. Lammers
484 P.2d 934 (Court of Appeals of Washington, 1971)
Marsland v. Bullitt Co.
474 P.2d 589 (Court of Appeals of Washington, 1970)
Moss v. Vadman
463 P.2d 159 (Washington Supreme Court, 1969)
Johnson v. Safeway Stores, Inc.
461 P.2d 890 (Court of Appeals of Washington, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
389 P.2d 669, 63 Wash. 2d 879, 1964 Wash. LEXIS 557, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hartman-v-port-of-seattle-wash-1964.