Lake Hills Investments Llc, App/cross-res. v. Ap Rushforth Constr. Co., Inc., Res/cross-app.

CourtCourt of Appeals of Washington
DecidedSeptember 14, 2020
Docket79116-8
StatusPublished

This text of Lake Hills Investments Llc, App/cross-res. v. Ap Rushforth Constr. Co., Inc., Res/cross-app. (Lake Hills Investments Llc, App/cross-res. v. Ap Rushforth Constr. Co., Inc., Res/cross-app.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lake Hills Investments Llc, App/cross-res. v. Ap Rushforth Constr. Co., Inc., Res/cross-app., (Wash. Ct. App. 2020).

Opinion

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON DIVISION ONE LAKEHILL INVESTMENTS LLC, a ) No. 79116-8-I Washington limited liability company, ) ) Appellant/Cross Respondent, ) ) v. ) ) RUSHFORTH CONSTRUCTION ) COMPANY, INC., d/b/a ) PUBLISHED OPINION AP RUSHFORTH, a Washington ) corporation, and ADOLPH & ) PETERSON, INC., a Minnesota ) corporation, ) ) Respondent/Cross Appellant. ) )

VERELLEN, J. — A contractor accused of breach of contract due to

construction defects may assert the affirmative defense that the owner’s plans and

specifications were defective and caused all of the construction defects. Because

the successful affirmative defense shields the contractor from all liability, the

contractor is required to prove all construction defect damages established by the

owner are attributable to defective plans and specifications. Here, jury instruction

9 misstated AP Rushforth Construction Company’s burden of proving its

affirmative defense, and a new trial is required. No. 79116-8-I/2

Lake Hills Investments, LLC assigns error to two other instructions but fails

to demonstrate prejudice. The court’s instruction on liquidated construction delay

damages misled the jury that it could excuse AP from delay days caused by

agents of AP, but Lake Hills does not establish any prejudice. The court should

have instructed the jury that only a material breach of the duty of good faith and

fair dealing by hindrance could excuse performance by AP, but under these

circumstances, the omission of “material” was harmless. None of the other issues

raised on appeal and cross appeal warrant any relief.

Therefore, we reverse and remand for a new trial.

FACTS

Lake Hills Village consists of several buildings constructed around a large

parking lot. The buildings are a public library, two mixed-use residential/retail

buildings, three commercial buildings, and some townhouses. Connecting the

library and an adjacent commercial building are an elevator tower and a

pedestrian bridge.

These structures were constructed over several years in several phases.

AP was the general contractor for four phases. Phase 1 was construction of the

library and Building A, a commercial building. Phase 2C was construction of half

of a large underground parking garage, including a large concrete slab on the

ground; the concrete topping slab on the parking garage, which also served as the

above-ground parking lot; and foundation work on the mixed-use buildings and

another commercial building, which are called, respectively, Building B, Building C,

2 No. 79116-8-I/3

and Building D. Phase 3 was completing construction of Buildings B, C, and D.

Phase 4 was construction of the townhomes. Phase 5A was construction of the

elevator tower, the pedestrian bridge, the rest of the underground parking garage,

and construction of retail space under Building A. Phase 5B was construction of

the third commercial building, Building F.

Construction on AP’s portion of Lake Hills Village was supposed to begin on

February 16, 2013, and be completed by January 31, 2015. Each phase of the

project had its own substantial completion date, and Lake Hills could assess

liquidated damages for delay days past those substantial completion dates.1

Every phase of the project AP was contracted to build, phases 2C, 3, 5A, and 5B,

was delayed. In November of 2014, Lake Hills notified AP it was in breach of the

contract schedule and blamed AP’s management practices and insufficient jobsite

staffing. Lake Hills also began identifying work it considered defective, such as

excessive cracking in the concrete garage floor slab. AP blamed the delays on

Lake Hills “arbitrarily” cutting its pay applications, making it difficult for it to hire and

retain subcontractors.2 AP blamed construction defects on Lake Hills providing “a

1 At trial, the parties disputed whether delay days for purposes of liquidated damages were calculated per phase per day, totaling $10,000 per calendar day if each of the four contractual phases was simultaneously delayed, or was calculated for the entire project. The jury concluded it applied per phase per day but that the parties did not intend to assess liquidated damages for phases 5A and 5B. These findings have not been challenged. 2Report of Proceedings (RP) (July 30, 2018) at 2476-77; RP (Aug. 7, 2018) at 3482-83.

3 No. 79116-8-I/4

sketch” or “a concept” rather than buildable designs.3 Relations deteriorated, and

in late October of 2015, Lake Hills filed suit against AP for breach of contract. AP

stopped work a few weeks later and filed its own breach claim alleging

underpayment.

Pretrial, the parties produced more than 1,000,000 documents, took 59

depositions, and participated in six days of mediation. The court ruled that neither

party could introduce evidence of the other party’s “[d]isputes with others,” and the

court prohibited AP from introducing evidence of certifications Lake Hills made to

its lender when requesting funds.4

The trial lasted almost two months, and the jury heard from two dozen

witnesses. One witness, Oscar Del Moro, the owner’s representative overseeing

the Lake Hills Village project, testified for six-and-a-half days. Using a special

verdict form, the jury returned a mixed verdict. It found that construction defects

by AP breached the contract and awarded damages in six of eight areas of

claimed defects. The jury also found that each phase of the project was

completed past its substantial completion date, Lake Hills was responsible for the

vast majority of delay days, AP did not breach by stopping work, and Lake Hills

breached the contract by underpaying AP. The court awarded a net judgment in

favor of AP of $9,624,695.80, including $5,866,016 in attorney fees and costs.

Lake Hills appeals, and AP cross appeals.

3 RP (Aug. 2, 2018) at 3203. 4 RP (June 25, 2018) at 39.

4 No. 79116-8-I/5

ANALYSIS

I. Jury Instructions

Lake Hills argues the court gave three erroneous jury instructions and erred

by refusing to adopt its proposed instruction. We review jury instructions “‘de novo

if based upon a matter of law or for abuse of discretion if based upon a matter of

fact.’”5 Jury instructions are legally erroneous when, read as a whole, they fail to

allow a party to argue its theory of the case, mislead the jury, or fail to inform the

jury of the applicable law.6 An erroneous instruction is grounds for reversal if it

prejudiced a party.7 We presume a party was prejudiced when the instruction

contains a clear misstatement of the law, but when the instruction was merely

misleading, the appellant must prove the instruction was prejudicial.8 The

presumption of prejudice can be overcome on a showing that the error was

harmless.9

5 Hendrickson v. Moses Lake Sch. Dist., 192 Wn.2d 269, 274, 428 P.3d 1197 (2018) (internal quotation marks omitted) (quoting Taylor v. Intuitive Surgical, 187 Wn.2d 743, 767, 389 P.3d 517 (2017)). 6 Anfinson v. FedEx Ground Package Sys., Inc., 174 Wn.2d 851, 860, 281 P.3d 289 (2012) (quoting Bodin v. City of Stanwood, 130 Wn.2d 726, 732, 927 P.2d 240 (1996)). 7 Id. (citing Joyce v. Dep’t of Corr., 155 Wn.2d 306, 323, 119 P.3d 825 (2005)). 8 Id. (citing Keller v. City of Spokane, 146 Wn.2d 237, 249-50, 44 P.3d 845 (2002)). 9 Paetsch v. Spokane Dermatology Clinic, P.S., 182 Wn.2d 842, 849, 348 P.3d 389 (2015) (citing Griffin v. W.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hutton Contracting Co. v. City of Coffeyville
487 F.3d 772 (Tenth Circuit, 2007)
United States v. George Mostella
802 F.2d 358 (Ninth Circuit, 1986)
Risley v. Moberg
419 P.2d 151 (Washington Supreme Court, 1966)
Tyee Construction Co. v. Pacific Northwest Bell Telephone Co.
472 P.2d 411 (Court of Appeals of Washington, 1970)
State v. Browder
378 P.2d 295 (Washington Supreme Court, 1963)
Baldwin v. National Safe Depository Corp.
697 P.2d 587 (Court of Appeals of Washington, 1985)
State v. Johnson
462 P.2d 933 (Washington Supreme Court, 1969)
Egede-Nissen v. Crystal Mountain, Inc.
606 P.2d 1214 (Washington Supreme Court, 1980)
Hizey v. Carpenter
830 P.2d 646 (Washington Supreme Court, 1992)
Valley Construction Co. v. Lake Hills Sewer District
410 P.2d 796 (Washington Supreme Court, 1966)
Hartley v. State
698 P.2d 77 (Washington Supreme Court, 1985)
Donald B. Murphy Contractors, Inc. v. State
696 P.2d 1270 (Court of Appeals of Washington, 1985)
Highlands Plaza, Inc. v. Viking Investment Corp.
435 P.2d 669 (Washington Supreme Court, 1967)
Jacks v. Blazer
235 P.2d 187 (Washington Supreme Court, 1951)
Puget Sound Service Corp. v. Bush
724 P.2d 1127 (Court of Appeals of Washington, 1986)
State v. Lampshire
447 P.2d 727 (Washington Supreme Court, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
Lake Hills Investments Llc, App/cross-res. v. Ap Rushforth Constr. Co., Inc., Res/cross-app., Counsel Stack Legal Research, https://law.counselstack.com/opinion/lake-hills-investments-llc-appcross-res-v-ap-rushforth-constr-co-washctapp-2020.