Hutton Contracting Co. v. City of Coffeyville

487 F.3d 772, 2007 U.S. App. LEXIS 9914, 2007 WL 1241638
CourtCourt of Appeals for the Tenth Circuit
DecidedApril 30, 2007
Docket05-3223
StatusPublished
Cited by23 cases

This text of 487 F.3d 772 (Hutton Contracting Co. v. City of Coffeyville) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hutton Contracting Co. v. City of Coffeyville, 487 F.3d 772, 2007 U.S. App. LEXIS 9914, 2007 WL 1241638 (10th Cir. 2007).

Opinion

HARTZ, Circuit Judge.

Hutton Contracting Company, Inc., a North Dakota corporation based in Colorado, contracted to construct a power line and a fiber-optic line for the City of Cof-feyville, Kansas. Upon completion of the project the City refused to pay the final $110,159.47 out of the contract price of $1,131,947.12, claiming that it was entitled to these funds as liquidated damages because of Hutton’s delays. Hutton sued the City in the United States District Court for the District of Kansas to obtain the unpaid amount of the contract price. See 28 U.S.C. § 1332 (diversity jurisdiction). After a jury trial the court ordered the City to pay Hutton $24,659.47 — the retain-age of $110,159.47 minus $85,500.00 in liquidated damages to which the City was entitled.

Hutton appeals from this judgment, challenging four holdings by the district court: (1) that the contract’s force-majeure clause did not excuse Hutton for delays caused by late deliveries from its pole supplier; (2) that the contract’s liquidated-damages provision was enforceable; (3) that the liquidated-damages provision allowed the court to apportion delays between Hutton and the City; and (4) that Hutton was not entitled to prejudgment interest on its damages. Hutton also challenges (5) a special interrogatory asking the jury whether the parties had modified their contract and (6) the court’s responses to questions from the jury. We have jurisdiction under 28 U.S.C. § 1291 and affirm.

*775 I. BACKGROUND

A. Contract and Performance

The contract between Hutton and the City is dated March 28, 2000. The engineer designated for the project was All-geier, Martin & Associates, Inc. (the Engineer). Rather than specifying when construction was to begin, the contract contained the following provision:

[Hutton] agrees to commence construction on the Project on a date (hereinafter called the “Commencement Date”) which shall be determined by the Engineer after notice in writing of approval of the Contract by the [City] and notice in writing from [Hutton] that [Hutton] has sufficient materials to warrant commencement and continuation of construction, but in no event will the Commencement Date be later than * (See Special Conditions) calendar days after date of approval of the Contract by the [City].

ApliApp. Vol. IV at 933. (The cross-referenced Special Conditions provide that “[t]he starting date shall be no later than May 1, 2000,” id. at 969, but this date never figures explicitly in the parties’ arguments.) The contract contemplated completion of construction within 45 days of commencement (excluding Sundays), with flexibility for bad weather:

[Hutton agrees] to prosecute diligently and to complete construction phases as described in strict accordance with the Plans, Specifications and Construction Drawings within Forty-five (45) calendar days (excluding Sundays) after Commencement Date; Provided, however, that [Hutton] will not be required to perform any construction on such days when in the judgment of the Engineer snow, rain, or wind or the results of snow, rain or frost make it impracticable to perform any operation of construction and to extent of the time lost due to the conditions described herein and approved in writing by the Engineer, the time of completion set out above will be extended if [Hutton] makes a written request therefor to the [City]....

Id. at 933. A provision that both parties call a force-majeure clause gave Hutton more time to complete the project in exceptional circumstances, provided that it submitted requests for extensions in writing:

The time for Completion of Construction shall be extended for the period of any reasonable delay which is due exclusively to causes beyond the control and without the fault of [Hutton], including Acts of God, fires, floods and acts or omissions of the [City] with respect to matters for which the [City] is solely responsible: Provided, however, that no extension of time for completion shall be granted [Hutton] unless within ten (10) days after the happening of any event relied upon by [Hutton] for such an extension of time [Hutton] shall have made a request therefor in writing to the [City], and provided further that no delay in such time of completion or in the progress of the work which results from any of the above causes or from any changes in construction which may be made pursuant to Subsection “d” of this Section 1 [which allowed the City to modify the construction plans and provide extensions therefor] shall result in any liability on the part of the [City]. Time extensions due to weather will be considered only when [Hutton] is on site.

Id.

The contract required the City to pay Hutton within 90 days of the project’s completion:

Upon completion by [Hutton] of the construction of the project, the Engineer will prepare an inventory of the Project *776 showing the total number and character of Construction Units and, after checking such Inventory with [Hutton], will certify it to the [City] together with a certificate of the total cost of the construction performed. Upon the approval of such certificates by the Engineer, the [City] shall make payment to [Hutton] of all amounts to which [Hutton] shall be entitled thereunder which shall not have been paid, provided, however, that such final payment shall be made not later than ninety (90) days after the date of Completion of Construction of the Project as specified in the Certificate of Completion, unless withheld because of the fault of [Hutton].

Id. at 936. But the amount owed would be reduced by $500 in liquidated damages for each day by which the completion of the project was late:

The time of the Completion of Construction of the Project is of the essence of the Contract. Should [Hutton] neglect, refuse or fail to complete the construction within the time herein agreed upon, after giving effect to extensions of time, if any, herein provided, then, in that event and in view of the difficulty of estimating with exactness damages caused by such delay, the [City] shall have the right to deduct from and retain out of such monies which may be then due, or which may become due and payable to [Hutton], the sum of FIVE HUNDRED DOLLARS ($500.00) per day for each and every day that such construction is delayed on its completion beyond the specified time, as liquidated damages and not as a penalty.

Id. at 943.

The parties have disputed the contractual commencement date, the completion date, and the number of days of excused delay. Both agree that a commencement date of August 9, 2000, was set at a pre-construction conference on August 4, 2000. But Hutton asserts that the City set the date “arbitrarily,” Aplt. Br. at 4, and therefore contrary to the contract. In any event, Hutton began clearing the construction site — the first step in the construction process — on August 10, 2000.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vreeland v. Schwartz
Tenth Circuit, 2021
Holcomb v. Whitten
Tenth Circuit, 2020
Torgerson v. LCC International, Inc.
227 F. Supp. 3d 1224 (D. Kansas, 2017)
Great American Insurance Co. v. E.L. Bailey & Co.
841 F.3d 439 (Sixth Circuit, 2016)
Boone Coleman Construction, Inc. v. Village of Piketon
2016 Ohio 628 (Ohio Supreme Court, 2016)
Wahlcometroflex, Inc. v. Westar Energy, Inc.
773 F.3d 223 (Tenth Circuit, 2014)
Elder v. Herlocker
405 F. App'x 351 (Tenth Circuit, 2010)
Stein v. Paradigm Mirasol, LLC
586 F.3d 849 (Eleventh Circuit, 2009)
June v. Union Carbide Corp.
577 F.3d 1234 (Tenth Circuit, 2009)
Carrothers Construction Co. v. City of South Hutchinson
207 P.3d 231 (Supreme Court of Kansas, 2009)
Hysten v. Burlington Northern Santa Fe Railway Co.
530 F.3d 1260 (Tenth Circuit, 2008)
General Injectables & Vaccines, Inc. v. Gates
527 F.3d 1375 (Federal Circuit, 2008)
Carrothers Construction Co. v. City of South Hutchinson
184 P.3d 943 (Court of Appeals of Kansas, 2008)
Ney v. City of Hoisington
264 F. App'x 678 (Tenth Circuit, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
487 F.3d 772, 2007 U.S. App. LEXIS 9914, 2007 WL 1241638, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hutton-contracting-co-v-city-of-coffeyville-ca10-2007.