Boone Coleman Construction, Inc. v. Village of Piketon

2016 Ohio 628, 50 N.E.3d 502, 145 Ohio St. 3d 450
CourtOhio Supreme Court
DecidedFebruary 24, 2016
Docket2014-0978
StatusPublished
Cited by35 cases

This text of 2016 Ohio 628 (Boone Coleman Construction, Inc. v. Village of Piketon) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Boone Coleman Construction, Inc. v. Village of Piketon, 2016 Ohio 628, 50 N.E.3d 502, 145 Ohio St. 3d 450 (Ohio 2016).

Opinions

O’Connor, C.J.

{¶ 1} In this appeal arising from a public-road-construction contract, we consider our precedent on contractual liquidated-damages provisions. We expressly extend that precedent to public-works contracts, vacate the judgment of the court of appeals, and remand this cause to that court for reconsideration in light of our opinion.

Relevant Background

{¶ 2} In 2007, appellant, the village of Piketon, solicited bids for the “Pike Hill Roadway and Related Improvements” project. The project included the installation of a traffic light at the intersection of U.S. Route 23 and Market Street in Piketon and improvements to the roadway.

[451]*451{¶ 3} Appellee, Boone Coleman Construction, Inc., submitted the lowest bid and was hired for the project. The parties entered into a contract in which Piketon agreed to pay Boone Coleman $683,300 to complete the work. The contract expressly provided that the time for completing the project was “of the essence”1 and that the project had to be substantially completed within 120 days of the date of commencement of the project. A liquidated-damages provision made clear that Boone Coleman would pay $700 to Piketon for each day after the specified completion date that the contract was not substantially completed.

{¶ 4} The date of commencement of the project was set for July 30, 2007. Thus, the contract required that the project be substantially completed 120 days later on November 27, 2007. Piketon granted Boone Coleman’s first request for an extension, which moved the completion date to May 30, 2008. But when Boone Coleman sought another extension, Piketon refused to grant it and notified Boone Coleman that it would assess the contractually specified liquidated damages of $700 per day if the project was not completed by May 30, 2008. Boone Coleman did not finish the project by then and on July 7, 2008, Piketon informed Boone Coleman that it was assessing damages of $700 per day as of May 31, 2008, until the completion of the project.

{¶ 5} Boone Coleman did not complete the project until July 2, 2009 — well over a year (397 days) after the parties’ extended completion date of May 30, 2008.

[452]*452{¶ 6} Boone Coleman brought suit against Piketon in the Pike County Common Pleas Court. Among other things, it alleged that Piketon had improperly faded to pay $147,477 of the contract price for the construction.2 Piketon counterclaimed for liquidated damages.

{¶ 7} Piketon moved for summary judgment. The trial court granted Piketon’s motion and entered judgment in its favor, awarding Piketon $277,900 in liquidated damages.

{¶ 8} Boone Coleman appealed, asserting that the trial court erred in awarding Piketon liquidated damages. The appellate court agreed. Citing our decision in Samson Sales, Inc. v. Honeywell, Inc., 12 Ohio St.3d 27, 465 N.E.2d 392 (1984), it held, “[W]hen we view the contract as a whole in its application, we conclude the amount of damages is so manifestly unreasonable and disproportionate that it is plainly unrealistic and inequitable.” (Emphasis added.) 2014-Ohio-2377, 13 N.E.3d 1190, at ¶ 40. It concluded that because the “resulting amount [of liquidated damages] is manifestly inequitable and unrealistic, courts are justified in determining the provision to be an unenforceable penalty.” Id. at ¶ 43, citing Samson Sales at 28. It reversed that portion of the trial court’s judgment and remanded for further proceedings.

{¶ 9} We granted Piketon’s request for discretionary review and agreed to address two related propositions of law:

When evaluating the enforceability of a liquidated damages provision in a construction contract, the court must conduct its analysis prospectively, based on the per diem amount of the liquidated damages at the time the contract is executed, and not retrospectively, based on the total liquidated damages that ultimately accrue.
[453]*453Liquidated damages are not deemed a penalty simply because a project consists of new construction of an improvement that did not exist previously and no proof of actual damages is required to enforce liquidated damages pursuant to such a contract.

See 140 Ohio St.3d 1451, 2014-Ohio-4414, 17 N.E.3d 598.

Analysis

Standard of Review for Contractual Liquidated-Damages Provisions

{¶ 10} We review the interpretation of a contract, a question of law, de novo. Arnott v. Arnott, 132 Ohio St.3d 401, 2012-Ohio-3208, 972 N.E.2d 586, ¶ 14. Similarly, the question of whether a contract clause provides for liquidated damages or an unenforceable penalty is a question of law that we also review de novo. Lake Ridge Academy v. Carney, 66 Ohio St.3d 376, 380, 613 N.E.2d 183 (1993).

Substantive Law on Liquidated Damages

{¶ 11} Simply stated, liquidated damages are damages that the parties to a contract agree upon, or stipulate to, as the actual damages that will result from a future breach of the contract. Sheffield-King Milling Co. v. Domestic Science Baking Co., 95 Ohio St. 180, 183, 115 N.E. 1014 (1917).

{¶ 12} “ ‘The effect of a clause for stipulated damages in a contract is to substitute the amount agreed upon as liquidated damages for the actual damages resulting from breach of the contract, and thereby prevents [sic] a controversy between the parties as to the amount of damages.’ ” Dave Gustafson & Co., Inc. v. South Dakota, 83 S.D. 160, 164, 156 N.W.2d 185 (1968), quoting 22 American Jurisprudence 2d, Damages, Section 235, at 321 (1965). “ ‘If a provision is construed to be one for liquidated damages, the sum stipulated forms, in general, the measure of damages in case of a breach, and the recovery must be for that amount. No larger or smaller sum can be awarded even though the actual loss may be greater or less.’ ” Id., quoting Section 235 at 321. Put another way, “a liquidated damages clause in a contract is an advance settlement of the anticipated actual damages arising from a future breach.” Carrothers Constr. Co., L.L.C. v. S. Hutchinson, 288 Kan. 743, 754, 207 P.3d 231 (2009).

{¶ 13} The common law viewed liquidated-damages provisions “with a gimlet eye,” Dist. Cablevision Ltd. Partnership v. Bassin, 828 A.2d 714, 723 (D.C.App. 2003), but that historical antipathy dissipated as parties to contracts, attorneys, and the courts recognized that such provisions serve valuable purposes.

{¶ 14} “Today the law does not look with disfavor upon ‘liquidated damages’ provisions in contracts. When they are fair and reasonable attempts to fix just [454]*454compensation for anticipated loss caused by breach of contract, they are enforced.” Priebe & Sons, Inc. v. United States, 332 U.S. 407, 411, 68 S.Ct. 123, 92 L.Ed. 32 (1947).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Charlie's CDJR, L.L.C. v. Charlie's Toledo, Inc.
2026 Ohio 18 (Ohio Court of Appeals, 2026)
Batsche v. Batsche
2025 Ohio 3017 (Ohio Court of Appeals, 2025)
Cerny v. Andrews
2025 Ohio 2864 (Ohio Court of Appeals, 2025)
United Assn. Local 168, Apprentice Educational Fund v. Robinson
2025 Ohio 2421 (Ohio Court of Appeals, 2025)
Du v. Nottingham Gate Estates HOA, Inc.
2024 Ohio 6090 (Ohio Court of Appeals, 2024)
Hawken School v. Machado
2024 Ohio 1060 (Ohio Court of Appeals, 2024)
Metro Renovations 12, L.L.C. v. Sabir
2023 Ohio 1867 (Ohio Court of Appeals, 2023)
Stark Ambulatory Surgical Ctr., L.L.C. v. CS Anesthesia, L.L.C.
2022 Ohio 3305 (Ohio Court of Appeals, 2022)
Mr. Pulpstone, L.L.C. v. The Shops on 58, L.L.C.
2021 Ohio 4467 (Ohio Court of Appeals, 2021)
Stamper v. Polley
2020 Ohio 3709 (Ohio Court of Appeals, 2020)
Economus v. Independence
2020 Ohio 266 (Ohio Court of Appeals, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
2016 Ohio 628, 50 N.E.3d 502, 145 Ohio St. 3d 450, Counsel Stack Legal Research, https://law.counselstack.com/opinion/boone-coleman-construction-inc-v-village-of-piketon-ohio-2016.