Boone Coleman Constr., Inc. v. Village of Piketon

2014 Ohio 2377
Ohio Court of Appeals·Decided May 22, 2014·No. 13CA836·Published·Cited by 3 cases

Opinion

IN THE COURT OF APPEALS OF OHIO FOURTH APPELLATE DISTRICT PIKE COUNTY

BOONE COLEMAN : Case No. 13CA836 CONSTRUCTION, INC., :

:

Plaintiff-Appellant, :

:

v. : DECISION AND : JUDGMENT ENTRY

VILLAGE OF PIKETON, OHIO, :

:

Defendant-Appellee. : RELEASED: 5/22/2014

APPEARANCES:

Stephen C. Rodeheffer and John A. Gambill, Portsmouth, Ohio, for appellant.

Eric B. Travers and Timothy A. Kelley, Kegler Brown Hill & Ritter, L.P.A., Columbus, Ohio, for appellee. Harsha, J.

{¶1} Appellant, Boone Coleman Construction, Inc. (“Boone Coleman"), filed a

complaint seeking the difference between what it actually received and the price stated in a construction contract between it and appellee, Village of Piketon, Ohio. Boone Coleman also sought additional compensation for work it performed to correct subsurface problems and to make revisions to a retaining wall and a traffic signal while performing the contract.

{¶2} Boone Coleman asserts that the trial court erred in entering summary judgment rejecting its claim for the unpaid contract amount and granting the village’s counterclaim for liquidated damages because the 397-day delay in performing the work was the village’s fault. However, Boone Coleman did not complete the construction contract within the time specified in the contract and it did not request an extension of time in accordance with the express terms of the agreement.

Pike App. No. 13CA836 2

{¶3} Boone Coleman also argues the liquidated damages provision constituted an unenforceable penalty. We agree because viewing the contract as a whole in its application, the amount of damages is so manifestly unreasonable and disproportionate that it plainly constitutes an unenforceable penalty. We sustain that portion of Boone Coleman's first assignment of error.

{¶4} Boone Coleman next contends that the trial court erred in denying its claims for additional compensation based on additional work it performed to correct subsurface problems and to revise the retaining wall and traffic signal. We reject this contention because Boone Coleman did not follow the parties’ unambiguous notice provisions to claim additional compensation. And the contract explicitly precluded recovery for additional costs related to subsurface conditions encountered by Boone Coleman.

{¶5} Therefore, we reverse that portion of the trial court's summary judgment enforcing the liquidated damages provision and remand that portion of the case for further proceedings. We affirm the remainder of the judgment I. FACTS

{¶6} In 2007, Piketon solicited bids for a construction project titled “Pike Hill Roadway and Related Improvements.” The project was described as:

Construction of a new traffic signal at the intersection of US Route 23 and Market Street, construction of approximately 330 linear feet of steel H-

pile/concrete lagging retaining wall, approximately 360 LF of full depth roadway reconstruction, miscellaneous storm drainage improvements, guard rail replacement, asphalt resurfacing of portions of Market Street and Shyville Road and other related improvements.

Pike App. No. 13CA836 3

{¶7} Because of safety concerns there had been a longstanding desire for a traffic light at the intersection of U.S. Route 23 and Market Street in the village. The need for a traffic light at the intersection was the driving force behind the construction project. The project was designed by Piketon’s engineer, Woolpert, Inc.

{¶8} Boone Coleman submitted the lowest bid, and in July 2007, the parties entered into a contract for Boone Coleman to complete the construction project for $683,300. The contract provided that the time limits were of the essence, that work would be substantially completed within 120 days after the date when the contract time began, and that as liquidated damages for delay, the contractor would pay the owner $700 for each day after the specified completion date until the project was substantially completed. The specific provisions of the contract stated:

ARTICLE 4 – CONTRACT TIMES 4.01. Time of the Essence

A. All time limits for Milestones, if any, Substantial Completion, and completion and readiness for final payment as stated in the Contract Documents are of the essence of the Contract.

4.02 Days to Achieve Substantial Completion and Final Payment

A. The Work will be substantially completed within 120 days after the date when the Contract Times commence to run as provided in paragraph 2.03 of the General Conditions, and completed and ready for final payment in accordance with paragraph 14.07 of the General Conditions within 120 days after the date when the Contract Times commence to run.

4.03 Liquidated Damages

A. CONTRACTOR and OWNER recognize that time is of the essence of this Agreement and that OWNER will suffer financial loss if the Work is not completed within the time(s) specified in paragraph 4.02 above, plus any extensions thereof allowed in accordance with Article 12 of the General Conditions. The parties also recognize the delays, expense, and difficulties involved in proving in a legal or arbitration [proceeding] the actual loss suffered by OWNER if the Work is not completed on time. Accordingly, instead of requiring any such proof, OWNER and CONTRACTOR agree that as liquidated damages for delay (but not as a penalty), CONTRACTOR shall pay OWNER $700.00 for each day that expires after the time specified in paragraph 4.02 for Substantial Completion until the Work is substantially complete.

{¶9} The contract time commenced on July 30, 2007, which meant that the required date of completion of the project was November 27, 2007. The parties subsequently agreed to an extension of the completion date to May 30, 2008.

{¶10} In an April 2008 letter to Woolpert, Boone Coleman requested another extension of the project completion date because its subcontractor for the installation of the traffic signal was unable to perform due to financial difficulties. In fact, the subcontractor had not ordered any of the required materials. By a letter in late May 2008, the village notified Boone Coleman that if it did not complete the project by May 30, 2008, it would begin assessing the specified liquidated damages of $700 per day. The village notified Boone Coleman in early July 2008 that it was assessing damages of $700 per day as of May 31, 2008 until the completion of the project.

{¶11} Boone Coleman did not complete the project by installing the traffic light and coordinating approval by the Ohio Department of Transportation (“ODOT”) until July 2, 2009, which was 397 days after the agreed project completion date of May 30, 2008.

{¶12} During the project, Boone Coleman did not request extensions of time or additional compensation in accordance with the parties’ contract, which set forth a specific procedure to resolve these claims:

10.05 Claims and Disputes

A. Notice: Written notice stating the general nature of each Claim, dispute, or other matter shall be delivered by the claimant to the

ENGINEER and the other party to the Contract promptly (but in no event later than 30 days) after the start of the event giving rise thereto. Notice of the amount or extent of the Claim, dispute, or other matter with supporting data shall be delivered to the ENGINEER and the other party to the Contract within 60 days after the start of such event (unless ENGINEER allows additional time for claimant to submit additional or more accurate data in support of such Claim, dispute, or other matter). A Claim for adjustment in Contract Price shall be prepared in accordance with the provisions of paragraph 12.01.B. A Claim for an adjustment in Contract Time shall be prepared in accordance with the provisions of paragraph 12.02.B. Each Claim shall be accompanied by claimant’s written statement that the adjustment claimed is the entire adjustment to which the claimant believes it is entitled as a result of said event. * * *

***

Free access — add to your briefcase to read the full text and ask questions with AI

Boone Coleman Constr., Inc. v. Village of Piketon, 2014 Ohio 2377 (Ohio Ct. App. 2014).

2014 Ohio 2377 (Boone Coleman Constr., Inc. v. Village of Piketon) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Boone Coleman Constr., Inc. v. Piketon
2016 Ohio 1557 (Ohio Court of Appeals, 2016)
Boone Coleman Construction, Inc. v. Village of Piketon
2016 Ohio 628 (Ohio Supreme Court, 2016)