Lake Ridge Academy v. Carney

613 N.E.2d 183, 66 Ohio St. 3d 376, 1993 Ohio LEXIS 1210
CourtOhio Supreme Court
DecidedJune 16, 1993
DocketNo. 91-2464
StatusPublished
Cited by192 cases

This text of 613 N.E.2d 183 (Lake Ridge Academy v. Carney) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lake Ridge Academy v. Carney, 613 N.E.2d 183, 66 Ohio St. 3d 376, 1993 Ohio LEXIS 1210 (Ohio 1993).

Opinions

Wright, J.

This case requires the court to resolve two issues: whether Carney breached his contract with Lake Ridge and, if so, whether Lake Ridge is entitled to stipulated damages in the amount of the full tuition due under the contract. We hold that Carney had a duty to make the scheduled tuition payments and that by riot doing so he breached the contract. We also hold that Lake Ridge is entitled to the full tuition due under the contract.

I

Carney argued, and the trial court agreed, that he did not breach the contract because he substantially complied with its terms. The court ruled that Carney “substantially complied with the cancellation provision of the contract when the cancellation letter was dated August 1, 1989, mailed or postmarked August 7, 1989, and received August 14, 1989.”

The court of appeals disagreed. The court framed its analysis partly in terms of whether time was of the essence in the contract. Quoting its own precedent for the rule that time is of the essence in a contract “ ‘where a definite date is fixed for compliance,’ ” the court held that Carney breached the contract by refusing to pay the entire tuition obligation after his untimely failure to cancel. We agree with the court of appeals’ conclusion but do so for different reasons.

We do not believe that the question here is whether time was of the essence. “When it is said that time is of the essence, the proper meaning of the phrase is that the performance by one party at the time specified in the contract or within the period specified in the contract is essential in order to enable him to require performance from the other party." (Emphasis added.) 6 Williston on Contracts (3 Ed.1962) 181, Section 846. If time is not of the essence and the obligor has substantially complied with the terms of the [379]*379contract, the obligee’s duty to perform is not discharged. In this case Lake Ridge does not argue that its obligation to educate Michael Carney was discharged or altered by his father’s inaction prior to August 1. Thus, whether time was of the essence is not the correct inquiry.

Similarly, the question of substantial performance is not germane to our analysis. There is no reasonable argument that Carney “substantially complied” with the provision of the contract requiring him to notify Lake Ridge of his child’s withdrawal prior to August 1. The referee found that Carney’s notice of cancellation was not received by Lake Ridge until after the August 1 deadline had passed. Thus, Carney did not comply at all with the requirement that cancellation take place prior to August 1. There appears to us to be no question of substantial performance in this case.

We interpret the contract and the cancellation clause as follows: Under the agreement signed in March 1989, Carney reserved a spot in the fourth grade class at Lake Ridge for his son in exchange for a $630 deposit and a promise to pay the balance of the tuition later that year. The contract gave Carney the option to cancel the agreement and withdraw his son without having to pay the rest of the tuition if he did so prior to August 1. If Carney chose not to exercise this right he would remain obligated to pay the full tuition. By the express terms of the contract Carney’s ability to unilaterally repudiate the agreement expired on August 1.

It is important to understand that the contract as a whole explicitly obligated Carney to pay the full tuition and the last paragraph provided him with only a limited escape clause. This clause was placed in the contract for the benefit of the parents and to the detriment of Lake Ridge, which could have required full payment at the time the contract was entered into. Lake Ridge Headmaster Joseph J. Ferber testified why August 1 was selected as the date before which parents had to notify the school of cancellation:

“Well, on the one hand, we feel we must have a day for parents to pay tuition, and must have a contract that says that’s enforceable in order for us to be able to collect revenue; otherwise, we would be in financial difficulty.

“We pick August 1st to give our parents as much time as possible between their deposit in March and the beginning of the school year to make a financial decision as a convenience to them. But we feel that August 1st is as far as we want to go prior to the start of the school year in order for us to be able to collect our revenue for expenses that are ongoing regarding the operations of the school.”

Carney did not exercise his right to cancel the contract before August 1. By letter postmarked August 7 he repudiated the contract and withdrew his son. This repudiation, however, did not relieve him of his existing duty to pay [380]*380the full tuition because it was not communicated to Lake Ridge before August 1. When Carney subsequently failed to make the scheduled tuition payments, he breached the contract.

While not precisely the same, this contract is similar to an option contract and a similar approach is appropriate. In an option contract, a party may exercise its option only in the manner provided in the contract. Midland Properties Co. v. Union Properties, Inc. (N.D.Ohio 1957), 148 F.Supp. 150, 152. If a time limit is given for exercising an option, the option may not be exercised after that time has passed. Longworth v. Mitchell (1875), 26 Ohio St. 334, 342.

Today we adopt similar rules for cases involving school reservation agreements: Under a school reservation agreement, when a parent is given the option to cancel the agreement before a certain date without incurring liability for the full tuition and does not do so, the parent may become liable for the full tuition if the contract so provides. The parent’s notification of cancellation, if given after the option date, is ineffective to discharge this liability. Subsequent failure to make scheduled tuition payments constitutes a breach of contract.1

As part of the contract in this case, Carney was given the option to cancel. That option expired, by the express terms of the contract, on August 1. As of August 1 any attempt by Carney to exercise his option to cancel — including his letter postmarked August 7 — was ineffective. Carney, therefore, breached his contract with Lake Ridge by not making the scheduled tuition payments.

II

We now turn to the question of whether the cancellation provision is unenforceable as a penalty. “It is virtually the unanimous rule of all jurisdictions that whether a stipulation is for liquidated damages or a penalty is a question of law for the court.” Ruckelshaus v. Broward Cty. School Bd. (C.A.5, 1974), 494 F.2d 1164, 1165. Carney argues that the clause requiring [381]*381him to pay the full tuition is a “penalty” and is therefore unenforceable as a matter of law. The court of appeals held that the clause is not punitive but, instead, is a valid liquidated damages provision. We agree with the court of appeals.

A

As a general rule, parties are free to enter into contracts that contain provisions which apportion damages in the event of default. “The right to contract freely with the expectation that the contract shall endure according to its terms is as fundamental to our society as the right to write and to speak without restraint. Responsibility for the exercise, however improvident, of that right is one of the roots of its preservation.” Blount v. Smith

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harder Invests., L.L.C. v. Perin-Tyler Family Found., L.L.C.
2025 Ohio 4706 (Ohio Court of Appeals, 2025)
DN Reynoldsburg, L.L.C. v. Maurices Inc.
2023 Ohio 3492 (Ohio Court of Appeals, 2023)
Total Quality Logistics, L.L.C. v. Johnson
2023 Ohio 1319 (Ohio Court of Appeals, 2023)
Kaiser v. Goff
2022 Ohio 4725 (Ohio Court of Appeals, 2022)
Ricky Spoon Builders, Inc. v. EmGee
Court of Appeals of North Carolina, 2022
Zubek v. Dearborn
2019 Ohio 3765 (Ohio Court of Appeals, 2019)
Gaither v. Wall & Assocs., Inc.
2017 Ohio 765 (Ohio Court of Appeals, 2017)
Newland v. AEC S. Ohio College L.L.C.
2016 Ohio 675 (Ohio Court of Appeals, 2016)
Franklin Mgt. Industries, Inc. v. Far More Properties, Inc.
2014 Ohio 5437 (Ohio Court of Appeals, 2014)
R.L.R. Invests., L.L.C. v. Wilmington Horsemens Group, L.L.C.
2014 Ohio 4757 (Ohio Court of Appeals, 2014)
Wells Fargo Bank, N.A. v. Lee
2014 Ohio 4514 (Ohio Court of Appeals, 2014)
Fleming v. Kent State Univ.
2014 Ohio 3471 (Ohio Court of Appeals, 2014)
W. Res. Academy v. Franklin
2013 Ohio 4449 (Ohio Court of Appeals, 2013)
Jamison v. LDA Builders, Inc.
2013 Ohio 2037 (Ohio Court of Appeals, 2013)
Litigation Mgt., Inc. v. Bourgeois
2011 Ohio 2794 (Ohio Court of Appeals, 2011)
Akin v. Akin
2011 Ohio 2765 (Ohio Court of Appeals, 2011)
Gaylord v. Frazzini
2010 Ohio 6385 (Ohio Court of Appeals, 2010)
In Re Market Center East Retail Property, Inc.
433 B.R. 335 (D. New Mexico, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
613 N.E.2d 183, 66 Ohio St. 3d 376, 1993 Ohio LEXIS 1210, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lake-ridge-academy-v-carney-ohio-1993.