Integrated Design Eng'g & Analysis Servs. v. Giddy Holdings, Inc.

CourtCourt of Appeals for the Sixth Circuit
DecidedMarch 24, 2022
Docket21-3433
StatusUnpublished

This text of Integrated Design Eng'g & Analysis Servs. v. Giddy Holdings, Inc. (Integrated Design Eng'g & Analysis Servs. v. Giddy Holdings, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Integrated Design Eng'g & Analysis Servs. v. Giddy Holdings, Inc., (6th Cir. 2022).

Opinion

NOT RECOMMENDED FOR PUBLICATION File Name: 22a0129n.06

No. 21-3433

UNITED STATES COURT OF APPEALS FOR THE SIXTH CIRCUIT FILED Mar 24, 2022 INTEGRATED DESIGN ENGINEERING ) DEBORAH S. HUNT, Clerk AND ANALYSIS SERVICES, INC., ) ) Plaintiff-Appellee, ) ON APPEAL FROM THE ) UNITED STATES DISTRICT v. ) COURT FOR THE NORTHERN ) DISTRICT OF OHIO GIDDY HOLDINGS, INC. AND BRETT ) JACOBSON, ) OPINION ) Defendants-Appellants. ) )

Before: SUTTON, Chief Judge; MOORE and GILMAN, Circuit Judges.

KAREN NELSON MOORE, Circuit Judge. Giddy Holdings, Inc. (“Giddy”) and

Integrated Design Engineering and Analysis Services (“IDEAS”) contracted for IDEAS to

manufacture Giddy’s product. After a pricing dispute, IDEAS, Giddy, and Giddy’s CEO, Brett

Jacobson, entered into a settlement agreement. IDEAS subsequently sued Giddy and Jacobson for

breaching that agreement, and Giddy and Jacobson counterclaimed. The district court enforced

part of the settlement agreement’s stipulated-damages clause, and, for the remaining damages, the

jury awarded IDEAS $85,600 in lost profits. On appeal, Giddy argues that IDEAS was improperly

allowed to recover both liquidated damages and lost profits, that the district court erred in finding

that the settlement agreement assigned the costs of Food and Drug Administration (“FDA”)

compliance to Giddy, and that the district court abused its discretion when it did not grant a mid-

trial continuance. For the reasons that follow, we AFFIRM. No. 21-3433, Integrated Design Eng’g & Analysis Servs., Inc. v. Giddy Holdings, Inc.

I. BACKGROUND

Giddy sells a product known as a “Giddy Pack,” which includes a device used to treat

erectile dysfunction known as the “Eddie.” R. 116 (Tr. at 83, 137–38) (Page ID #1291, 1345–46).

Giddy contracted with IDEAS to produce the Giddy Pack, R. 59-2 (Settlement Agreement at 1)

(Page ID #484), and IDEAS subcontracted with other companies to manufacture the component

parts of the Giddy Pack. R. 116 (Tr. at 49) (Page ID #1257).

Giddy initially contracted to purchase 55,112 packs over the course of two production runs.

R. 59-2 (Settlement Agreement at 1) (Page ID #484). After a pricing dispute between the parties,

they entered into a settlement agreement, agreeing to a third production run. Id. IDEAS agreed

to a discounted rate for the first two production runs “in exchange for the express understanding

th[at] Giddy will proceed with and fully fund” the third production run. Id.

While Giddy was importing the devices from China, some issues with FDA compliance

arose. At one point, the FDA seized a shipment for failure properly to register the devices. R. 117

(Tr. at 204) (Page ID #1412). Giddy ultimately paid both FDA registration fees and legal fees

during the registration process. Id. at 203 (Page ID #1411). The parties dispute whether, pursuant

to the settlement agreement, Giddy had agreed to bear the cost of FDA compliance.

After Giddy ultimately opted not to fund the third production run, IDEAS sued Giddy and

its CEO, Brett Jacobson, in state court, alleging that Giddy breached the settlement agreement.

R. 1-1 (Compl.) (Page ID #6–27). Giddy removed the suit to federal court, R. 1 (Not. of Removal)

(Page ID #1–3), and filed an answer and counterclaim, R. 4 (Answer & Countercl.) (Page ID #35–

46). Both parties then moved for summary judgment. R. 58 (Pl.’s Mot. for Summ. J.) (Page ID

#384–402); R. 59 (Def.’s Mot. for Summ. J.) (Page ID #470–80). The district court granted both

2 No. 21-3433, Integrated Design Eng’g & Analysis Servs., Inc. v. Giddy Holdings, Inc.

motions in part, making the following findings that are relevant to this case: (1) Giddy and

Jacobson were liable for breach of contract; and (2) the $40,000 liquidated-damages provision with

respect to the first two production runs was enforceable, but the $120,000 liquidated-damages

provision with respect to the third production run was unenforceable.1 Integrated Design Eng’g

& Analysis Servs., Inc. v. Giddy Holdings, Inc., No. 5:20-cv-00563, 2021 WL 848949, at *3–4

(N.D. Ohio Mar. 5, 2021). After a two-day virtual jury trial, the jury awarded IDEAS an additional

$85,600 in lost profits with respect to the third production run, in lieu of the unenforceable

$120,000 liquidated-damages provision. R. 109-1 (Verdict) (Page ID #1115). Giddy and Jacobson

timely appealed. R. 112 (Notice of Appeal) (Page ID #1120).

II. ANALYSIS

A. Recovery of Both Liquidated Damages and Lost Profits

The first issue raised on Giddy’s appeal is whether the district court impermissibly allowed

IDEAS to recover both liquidated damages and lost profits. We review this issue of law de novo.

Andrews v. Columbia Gas Transmission Corp., 544 F.3d 618, 624 (6th Cir. 2008).

The settlement agreement contained two closely related damages provisions: “In the event

Giddy’s business plan changes and it decides not to proceed with PR3, then Giddy will pay the

balance of the first two Production Runs in the amount of $40,000 representing the non-discounted

pricing plus liquidated damages in the amount of 3 times the $40,000 amount.” R. 59-2

1 The district court also held that IDEAS did not breach the settlement agreement and that both IDEAS and Brad Borne (IDEAS’s president) were entitled to summary judgment on Giddy’s and Jacobson’s conversion counterclaim. Integrated Design Eng’g & Analysis Servs., Inc. v. Giddy Holdings, Inc., No. 5:20-cv-00563, 2021 WL 848949, at *5–6 (N.D. Ohio Mar. 5, 2021).

3 No. 21-3433, Integrated Design Eng’g & Analysis Servs., Inc. v. Giddy Holdings, Inc.

(Settlement Agreement ¶ 3.3) (Page ID #485). Giddy argues that the district court should have

permitted IDEAS to recover liquidated damages or lost profits but not both.

Under Ohio law, which the parties agree applies in this diversity-of-citizenship case, “[t]he

effect of a clause for stipulated damages in a contract is to substitute the amount agreed upon as

liquidated damages for the actual damages resulting from breach of the contract, and thereby

prevent[] a controversy between the parties as to the amount of damages.” Boone Coleman

Constr., Inc. v. Village of Piketon, 50 N.E.3d 502, 508 (Ohio 2016) (quoting Dave Gustafson &

Co. v. South Dakota, 156 N.W.2d 185, 187 (S.D. 1968)). When a party recovers an amount of

damages stipulated in the contract, it typically may not recover other damages, such as lost profits.

Id.; see also Domestic Linen Supply & Laundry Co. v. Kenwood Dealer Grp., Inc., 672 N.E.2d

184, 190 (Ohio Ct. App. 1996).

The bar against receiving both actual and liquidated damages stems from the principle that

parties may not receive duplicate damages. See Mentor Lagoons, Inc. v. Laity, No. 10-184, 1985

WL 9999, at *1 (Ohio Ct. App. May 24, 1985) (“To allow a party to recover liquidated damages,

as stipulated in the contract, and to also prove and recover actual damages allows a double recovery

since liquidated damages are a pre-determined amount of what the actual damages will be in case

of a breach.”). If, however, separate damage provisions compensate a party for separate losses,

this principle does not apply. In such circumstances, a party “is not barred from seeking both

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Humphrey
608 F.3d 955 (Sixth Circuit, 2010)
Andrews v. Columbia Gas Transmission Corp.
544 F.3d 618 (Sixth Circuit, 2008)
Dave Gustafson & Co. v. State
156 N.W.2d 185 (South Dakota Supreme Court, 1968)
Boone Coleman Construction, Inc. v. Village of Piketon
2016 Ohio 628 (Ohio Supreme Court, 2016)
Domestic Linen Supply & Laundry Co. v. Kenwood Dealer Group, Inc.
672 N.E.2d 184 (Ohio Court of Appeals, 1996)
Prime Rate Premium Fin. Corp., Inc. v. Karen Larson
930 F.3d 759 (Sixth Circuit, 2019)
Graham v. Drydock Coal Co.
667 N.E.2d 949 (Ohio Supreme Court, 1996)
Cincinnati Insurance v. Anders
789 N.E.2d 1094 (Ohio Supreme Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
Integrated Design Eng'g & Analysis Servs. v. Giddy Holdings, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/integrated-design-engg-analysis-servs-v-giddy-holdings-inc-ca6-2022.