Carrothers Construction Co. v. City of South Hutchinson

207 P.3d 231, 288 Kan. 743, 2009 Kan. LEXIS 105
CourtSupreme Court of Kansas
DecidedMay 22, 2009
Docket98,023
StatusPublished
Cited by43 cases

This text of 207 P.3d 231 (Carrothers Construction Co. v. City of South Hutchinson) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Carrothers Construction Co. v. City of South Hutchinson, 207 P.3d 231, 288 Kan. 743, 2009 Kan. LEXIS 105 (kan 2009).

Opinion

The opinion of the court was delivered by

Biles, J.:

This is an appeal from a district court’s decision on cross-motions for summary judgment in a contract case. The district court awarded liquidated damages against a construction company for failure to timely complete a municipal wastewater treatment facility. The issue is the extent to which liquidated damages are enforceable under the parties’ contract. The Court of Appeals affirmed the district court. This court granted the construction company’s petition for review. Our jurisdiction arises from K.S.A. 20-3018(b).

*745 We affirm. In doing so, we explain below that the reasonableness of a liquidated damages clause in a contract deliberately entered into should be determined with regard to the conditions of the parties existing at the time the contract was executed, not from hindsight after the contract is breached. In addition, we reject the construction company’s argument that liquidated damages for completion delays cannot be assessed after the owner occupied the new facility.

Factual and Procedural Background

The material facts are not in dispute. Carrothers Construction Company, L.L.C., entered into a contract with the Ciiy of South Hutchinson to construct a $5,618,000 wastewater treatment facility to replace the City’s existing plant. The contract contained completion dates as well as a liquidated damages provision for delays in meeting the completion dates.

Carrothers has acknowledged it did not meet those bargained-for completion deadlines, and it conceded at oral argument an assessment for some liquidated damages under the contract is appropriate. Accordingly, the dispute before this court reduces itself down to deciding whether the district court was correct as to exactly how much the liquidated damages should be under the contract.

The provision labeled “Liquidated Damages” is found in the contract at Section 3.3 and is plainly identified. In it, Carrothers and the City agreed as follows:

“3.3 Liquidated Damages. OWNER and CONTRACTOR recognize that time is of the essence of this Agreement and that OWNER will suffer financial loss if the Work is not started and completed within the times specified in paragraphs 3.1 and 3.2 above, plus any extensions thereof allowed in accordance with Article 12 of the General Conditions. They also recognize the delays, expense and difficulties involved in proving the actual loss suffered by OWNER if the Work is not completed on time. Accordingly, instead of requiring any such proof, OWNER and CONTRACTOR agree that as liquidated damages for delay (but not as a penalty) CONTRACTOR shall pay OWNER Six Hundred DoEars ($600.00) for each day that expires after the time specified in paragraph 3.1 for the work to start, and Eight Hundred Fifty DoEars ($850.00) for each day that expires after the time specified in paragraph 3.2 for Substantial Completion until the Work is substantiaEy complete. After Substantial Completion, if CONTRACTOR shaE *746 neglect, refuse or fail to complete the remaining Work within the time specified in paragraph 3.2 for completion and readiness for final payment or any proper extension thereof granted by OWNER, CONTRACTOR shall pay OWNER Eight Hundred Fifty Dollars ($850.00) for each day that expires after the time specified in paragraph 3.1 for completion and readiness for final payment.”

The standard general conditions of the construction contract (see Section 8.5 incorporating general conditions) define the term “Work” in Article 1 as follows:

“48. Work — The entire completed construction or the various separately identifiable parts thereof required to be provided under the Contract Documents. Work includes and is the result of performing or providing all labor, services, and documentation necessary to produce such construction, and furnishing, installing, and incorporating all materials and equipment into such construction, all as required by the Contract Documents.”

Article 1, entitled ‘Work,” further provides:

“The project for which the Work under the Contract Documents may be the whole or only a part is generally described as follows:
Construct wastewater treatment liquid process facilities to replace the existing liquid process facilities. Construct a maintenance building, site piping, other site utilities, site grading, and system controls. Drain, clean existing basins for future use and remove obsolete equipment. The capacity of the new process facilities will be 2 MGD. A new computer based control system for the improvements is included in the Work.”

The contract documents also define the term “Substantial Completion” as:

“43. Substantial Completion — The time at which the Work (or a specified part thereof) has progressed to the point where, in the opinion of ENGINEER, the Work (or a specified part thereof) is sufficiently complete, in accordance with the Contract Documents, so that the Work (or a specified part thereof) can be utilized for the purposes for which it is intended.”

The term “final completion” is not defined in the contract. But in describing how the contractor may apply for final payment under Section 14.07 A.I., the agreement provides:

“A. Application for Payment. 1. After CONTRACTOR has, in the opinion of ENGINEER, satisfactorily completed all corrections identified during the final inspection and has delivered, in accordance with the Contract Documents, all maintenance and operating instructions . . . CONTRACTOR may make application for final payment following the procedure for progress payments.”

*747 The provisions recited above show at the time the contract was entered into by the parties, the City and Carrothers agreed: (1) Time was of the essence in completing the project; (2) actual damages would be difficult to ascertain, so the parties chose to use the liquidated damages provision if a breach occurred rather than requiring proof of actual damages; (3) the same per diem amount of liquidated damages applicable to a failure to achieve substantial completion would apply to a failure to achieve final completion; (4) the $850 per diem liquidated damages amount for failure to achieve either substantial or final completion was not a penalty; and (5) the project engineer’s opinion would be relied upon by both parties to determine whether the completion dates were met. The record reflects Carrothers had multiple opportunities to object to the liquidated damages provision during the bidding and contracting process, but it did not.

The engineer for this project was MKEC Engineering Consultants, Inc. (MKEC), which also assisted in drafting the contract. An MKEC employee, David Chase, performed the calculations for the liquidated damages provision. Lynn Moore, MKEC’s manager of environmental engineering, discussed those calculations with Chase and approved the liquidated damages provision.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

All States Home Improvement v. Beltz
Court of Appeals of Kansas, 2026
Schutt v. Foster
Court of Appeals of Kansas, 2024
Hawken School v. Machado
2024 Ohio 1060 (Ohio Court of Appeals, 2024)
Stark Ambulatory Surgical Ctr., L.L.C. v. CS Anesthesia, L.L.C.
2022 Ohio 3305 (Ohio Court of Appeals, 2022)
Sacred Leaf v. Riahi
Court of Appeals of Kansas, 2022
Cybertron International, Inc. v. Capps
Court of Appeals of Kansas, 2022
Bates v. Flemming
D. Kansas, 2019
Law Co. Building Associates v. Law
444 P.3d 376 (Court of Appeals of Kansas, 2019)
Law Company Building Associates v. Law
Court of Appeals of Kansas, 2019
Vizant Techs., LLC v. Yrc Worldwide Inc.
2018 NCBC 63 (North Carolina Business Court, 2018)
Wise v. Bailey
Court of Appeals of Kansas, 2017
In re Marriage of South
Court of Appeals of Kansas, 2017
Oldendick v. Crocker
2016 Ohio 5621 (Ohio Court of Appeals, 2016)
Boone Coleman Constr., Inc. v. Piketon
2016 Ohio 1557 (Ohio Court of Appeals, 2016)
Boone Coleman Construction, Inc. v. Village of Piketon
2016 Ohio 628 (Ohio Supreme Court, 2016)
In re Marriage of Lundemo
Court of Appeals of Kansas, 2015

Cite This Page — Counsel Stack

Bluebook (online)
207 P.3d 231, 288 Kan. 743, 2009 Kan. LEXIS 105, Counsel Stack Legal Research, https://law.counselstack.com/opinion/carrothers-construction-co-v-city-of-south-hutchinson-kan-2009.