Page v. Travis-Williamson County Water Control & Improvement District No. 1

367 S.W.2d 307, 6 Tex. Sup. Ct. J. 455, 1963 Tex. LEXIS 605
CourtTexas Supreme Court
DecidedMay 8, 1963
DocketA-9136
StatusPublished
Cited by10 cases

This text of 367 S.W.2d 307 (Page v. Travis-Williamson County Water Control & Improvement District No. 1) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Page v. Travis-Williamson County Water Control & Improvement District No. 1, 367 S.W.2d 307, 6 Tex. Sup. Ct. J. 455, 1963 Tex. LEXIS 605 (Tex. 1963).

Opinion

SMITH, Justice.

On December 17, 1955, Petitioner-Respondent, Holland Page, entered into a *308 contract with Petitioner-Respondent, Travis-Williamson County Water Control and Improvement District No. 1, for the construction of a water system. Thereafter, Page subcontracted all of the digging of ditches, laying of pipe and back-filling to Petitioner-Respondent, R. Ward Smith; Page was to furnish all of the materials. On December 20, 195S, the Water District’s engineer issued Page a work order instructing him to begin work on the contract and advising that the agreed working time of 210 working days would be computed from December 30, 1955. Page and Smith proceeded with the construction of the water system.

In the early part of 1957 the work on the project was nearing completion. On May 10, 1957, after making an inspection of the work, the engineer for the Water District furnished Page a list of deficiencies (commonly referred to in the record as a “gig sheet”). Thereafter, additional work was done; and on July 10, 1957, a second and final “gig sheet” was prepared by the Water District’s engineer. The two “gig sheets” indicated that they were not to be considered inclusive of all deficiencies and stated that other deficiencies would be made known to Page as they were observed. Certain efforts were made by Page and Smith toward remedying these deficiencies. At this point, a controversy arose between the Water District, Page and Smith as to whether the alleged deficiencies had been corrected and whether or not some of the alleged deficiencies amounted to unreasonable demands.

On July 29, 1957, the engineer for the Water District advised Page that the working days on the contract would expire at midnight on July 31, 1957, and that from that time the liquidated damages provision of the contract would be invoked. The engineer, thereafter, periodically advised Page as to the number of days of liquidated damages which had been assessed during each month.

In March of 1958 all work ceased on the project. The Water District directed Page to proceed; and upon his failure to do so, and upon the failure of the surety on his bond to do so, the Water District advertised for bids to carry the project to final completion. The completion contract was awarded to the Bland Construction Company, and the work was finally accepted by the Water .District and their engineer on October 3, 1958.

In March of 1960 Page brought this suit against the Water District for certain •■amounts alleged to be due for labor and material furnished the Water District by Page. Page’s suit was also against Smith and his surety on the subcontract. As against the Water District, Page asserted that the prime contract had been substantially completed ; and as against Smith and his surety, it was alleged that the subcontract had not been substantially completed. Smith filed a cross action against the Water District and a counterclaim against Page for damages for certain extra work he had furnished the Water District, and for which he had not been compensated. The Water District counterclaimed against Page and his surety seeking liquidated damages because of Page’s alleged failure to substantially complete the work under the contract within 210 working days.

Upon the trial on the merits in response to special issues, the jury found that on July 31, 1957, the work under Page’s contract with the Water District had been substantially completed by Smith and Page. The jury further found that the reasonable cost of the work and materials necessary to remedy the deficiencies listed in the two “gig sheets” dated May 10, 1957, and July 10, 1957, was $14,990.00. The trial court rendered judgment upon such verdict for Page against the Water District for $29,629.95, and for Smith against the Water District for $15,854.77, together -with interest on such sums from March 15, 1958. The Water District recovered noth *309 ing on its counterclaim against Page and his surety for liquidated damages.

The Court of Civil Appeals has held that the actual cost of completion ($39,234.07) under the Water District’s contract with Bland Construction Company, and not the reasonable cost of completion of the work listed on the two “gig sheets” ($14,990.00), is the proper charge to be made against the amount due Page and Smith from the Water District. Therefore, the judgment of the trial court was reformed and affirmed. As against the Water District, Page was given a judgment for $1,608.99, and Smith was awarded a take nothing judgment. Tex.Civ.App., 358 S.W.2d 158.

The application for writs of error of Page, Smith and the Water District have been granted. We will first dispose of the points of error asserted by Page and Smith.

Measure of Damages

After concluding that the evidence amply supported the jury finding that the work done by Page and Smith under the contract had been substantially completed, the Court of Civil Appeals applied Section 42(b) of the contract 1 for the determination of the charge to be made against the amount due Page from the Water District. Page and Smith contend that the Court of Civil Appeals has erred in resorting to Section 42(b), so as to charge the actual cost of completion under the Bland contract ($39,234.07) rather than the reasonable cost of completion of the deficiencies listed in the two “gig sheets” ($14,990.00) against the amount due Page from the Water District since Section 42 applies only in instances of abandonment before the work has been substantially completed. We disagree with this contention.

Section 42 is not limited in its application to instances of abandonment before substantial completion; it is also applicable should Page fail to comply with the orders of the engineer, when such orders are consistent with this contract. In such event, the Water District is authorized to let a new contract for completion of the work, and if the cost of the completion work increases the cost to the Water District, such increase may be charged to Page. Thus, when Page and his surety failed to resume work after being ordered to do so by the engineer, the Water District properly let the Bland contract, and the costs to the Water District under such contract were properly charged against the amount the Water District owed Page. The Court of Civil Appeals committed no error in reducing Page’s recovery against the Water District to $1,608.99, and in ordering that Smith take nothing in his cross action against the Water District.

Adjustment of Accounts

All of the work which was completed by Bland Construction Company related exclusively to the work which was to have *310 been performed by Smith under his subcontract with' Page. For this reason Page asserts that he is entitled to recover from Smith and/or his surety, Globe Indemnity Company, any amount charged against him for the failure to fully complete the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carrothers Construction Co. v. City of South Hutchinson
207 P.3d 231 (Supreme Court of Kansas, 2009)
Wesley Dahl v. Morris L. Beall
Court of Appeals of Texas, 1994
Perini Corp. v. Greate Bay Hotel & Casino, Inc.
610 A.2d 364 (Supreme Court of New Jersey, 1992)
Mursor Builders, Inc. v. Crown Mountain Apartment Associates
467 F. Supp. 1316 (Virgin Islands, 1978)
Texas Construction Associates, Inc. v. Balli
558 S.W.2d 513 (Court of Appeals of Texas, 1977)
Lanphier Construction Co. v. Fowco Construction Co.
523 S.W.2d 29 (Court of Appeals of Texas, 1975)
Allaben v. State
418 S.W.2d 517 (Court of Criminal Appeals of Texas, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
367 S.W.2d 307, 6 Tex. Sup. Ct. J. 455, 1963 Tex. LEXIS 605, Counsel Stack Legal Research, https://law.counselstack.com/opinion/page-v-travis-williamson-county-water-control-improvement-district-no-1-tex-1963.