Stone v. City of Arcola

536 N.E.2d 1329, 181 Ill. App. 3d 513, 130 Ill. Dec. 118, 1989 Ill. App. LEXIS 412
CourtAppellate Court of Illinois
DecidedMarch 31, 1989
Docket4-88-0627
StatusPublished
Cited by43 cases

This text of 536 N.E.2d 1329 (Stone v. City of Arcola) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stone v. City of Arcola, 536 N.E.2d 1329, 181 Ill. App. 3d 513, 130 Ill. Dec. 118, 1989 Ill. App. LEXIS 412 (Ill. Ct. App. 1989).

Opinion

JUSTICE SPITZ

delivered the opinion of the court:

This action was brought by plaintiff E.R. Stone, d/b/a Stone Heavy Equipment Company, against defendant City of Areola (City) to recover monies held by defendant which plaintiff claims to be due to plaintiff under a construction contract. Plaintiff’s two-count complaint alleges breach of contract (count I) and equitable restitution based on a theory of unjust enrichment and implied contract (count II).

Defendant counterclaimed to recover damages caused by plaintiff’s delay in completing the contract and failure to perform all work required by the contract. Following a bench trial conducted in the circuit court of Douglas County, judgment was entered in favor of plaintiff and against defendant on both the complaint and counterclaim.

Plaintiff is a contractor engaged in the construction of public utilities. Plaintiff submitted a $1,273,000 bid to construct a portion of defendant’s new sanitary sewage facility. Plaintiff’s bid was accepted on July 6, 1981, and plaintiff signed the acceptance of notice of the award on July 20,1981.

The agreement provided that plaintiff would commence work within 10 calendar days after the date of the notice to proceed and would complete the same within 365 calendar days unless the period for completion was extended. After Stone submitted a performance bond and a payment bond, defendant issued a notice to proceed which designated the date of completion of all work as July 20, 1982. However, on the copy of the notice to proceed that was received by plaintiff, the date of completion of the work was changed to read July 30, 1982. Stone did not change the completion date on the notice to proceed which was included with the copy of his contract documents, and the trial court specifically found that no evidence was submitted to explain this discrepancy.

At the hearing, Stone testified the work immediately fell behind schedule because of rain that started on August 10. By a letter to defendant’s mayor, Jack Chaney, dated September 3, 1981, Stone asked defendant to consider an extension of the construction and completion date because “August has been an abnormally wet month.” Stone does not recall ever receiving any response to his letter.

Thereafter, the work continued behind schedule on the project. After a work stoppage for the winter, plaintiff started pumping water from the lagoons into a road ditch. Stone testified that in early April he had a conversation with Chaney in which the mayor told him that complaints were being received from a farmer about drainage from the lagoon site flooding his field. The farmer was concerned about his crop and asked that the pumping cease. After this conversation, plaintiff stopped pumping water from the lagoons and proceeded to lay an outfall sewer from the sewer plant. This sewer was part of the contract, but now had to be completed out of sequence. Plaintiff resumed pumping water from the lagoons into the outfall sewer on April 20, 1982.

Chaney, when called as an adverse witness, initially denied he ever went to the plant site and instructed Stone to cease pumping water. Chaney did recall going to the site and talking with Stone on one occasion and asking his cooperation on some matter but Chaney had no recollection of the exact conversation. Chaney further stated he had no authority to tell Stone to stop doing anything. Under further examination, Chaney did recall asking Stone that he cooperate by not pumping water into the ditch and causing a problem for the City downstream.

Stone also testified there were some difficulties resulting from variations from the plans and the actual way the facility had to be constructed. These conflicts specifically involved elevations for the structures, dimensions on the building, and piping. There were contradictions in the paint and finish specifications for the clarifier, and changes were made with regard to the control building and the chemical feed location. Stone worked out these problems with the engineers in the field. According to his testimony, sometimes small items are just negotiated or trade-offs are made. However, Stone felt that this particular job contained more contradictions than usual and he sustained some delays as a result of resolving contradictions. Plaintiff’s expert, Michael Murphy, testified the contradictions in the plans, in his opinion, caused somewhere between 35 to 60 days’ delay.

James B. Upchurch, engineer for defendant on this project, testified there were several field adjustments made during the period of construction. He stated field adjustments are made in every type of construction project. Specifically, Upchurch testified there was a field adjustment made in connection with the floor of the first clarifier which resulted because the concrete used did not pass specifications. Consequently, Upchurch let plaintiff add an extra four inches of concrete to the top of the base so that he did not have to tear out the old base. There were also some bad concrete reports on the floor of the building at the old plant. Since he did not think this was significant, he did not require anything to be done. He determined concrete footings for the sludge drying beds were not necessary and, even though these footings were shown on the original plans and specifications, plaintiff was allowed to dispense with pouring these footings. At least 60 days were saved by not having to replace the bad concrete on the first clarifier, one week by not having to replace any of the bad concrete in the maintenance building at the old treatment plant, and two or three days by not having to put footings in some of the sludge drying beds. Other minor field adjustments were made on the project, but most of the field adjustments were made as a result of requests from plaintiff to facilitate the work.

Stone sent a letter to Chaney dated July 2, 1982, which referred to his letter of September 1981 and stated there had not been a sufficient number of favorable days or conditions to reestablish the original schedule and completion date. Therefore, plaintiff requested the completion date be extended 90 days. Chaney responded with a letter dated August 2, 1982, approving a 60-day extension of time from July 19, 1982, to and including September 17, 1982, for completion of the work. This letter stated defendant would take the necessary steps to enforce the contract, including the provision for liquidated damages in the amount of $200 per day for each day beyond September 17, 1982, the work remained uncompleted. The letter further stated the city council had reviewed plaintiff’s request and had determined there had been an abnormally large amount of rainfall during the term of the contract which had been a condition beyond plaintiffs control within the meaning of section 15 of the general conditions of the contract.

On September 18, 1982, Stone mailed a letter to Chaney referring to the previous letters and reviewing the request for a 90-day extension. Stone did not recall receiving any correspondence with regard to that request but testified he knew it was denied. Stone did not make any further written requests for an extension of time. He did appear before the city council at a meeting in early February of 1983, explained to the council the situation and tried to describe the events leading up to the current status of the job. Stone then orally requested a time extension.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Phonco Communications, Inc v. Chicago Central Food Mart, Inc
2022 IL App (1st) 210559-U (Appellate Court of Illinois, 2022)
Carrothers Construction Co. v. City of South Hutchinson
207 P.3d 231 (Supreme Court of Kansas, 2009)
G.M. Harston Construction Co. v. City of Chicago
371 F. Supp. 2d 949 (N.D. Illinois, 2005)
A.E.I. Music Network, Inc. v. Business Computers, Inc.
290 F.3d 952 (Seventh Circuit, 2002)
Maness v. Santa Fe Park Enterprises., Inc.
700 N.E.2d 194 (Appellate Court of Illinois, 1998)
Maness v. Santa Fe Park Enterprises
Appellate Court of Illinois, 1998
People v. Hunt
261 Ill. App. 3d 165 (Appellate Court of Illinois, 1994)
In Re JP
633 N.E.2d 27 (Appellate Court of Illinois, 1994)
In Interest of JJ
615 N.E.2d 827 (Appellate Court of Illinois, 1993)
People v. Johnson
246 Ill. App. 3d 143 (Appellate Court of Illinois, 1993)
Stewart v. Thrasher
610 N.E.2d 799 (Appellate Court of Illinois, 1993)
University of Illinois v. Continental Casualty Co.
599 N.E.2d 1338 (Appellate Court of Illinois, 1992)
Perini Corp. v. Greate Bay Hotel & Casino, Inc.
610 A.2d 364 (Supreme Court of New Jersey, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
536 N.E.2d 1329, 181 Ill. App. 3d 513, 130 Ill. Dec. 118, 1989 Ill. App. LEXIS 412, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stone-v-city-of-arcola-illappct-1989.