Butkovich & Sons v. State Bk. of St. Charles

379 N.E.2d 837, 62 Ill. App. 3d 810, 20 Ill. Dec. 4, 1978 Ill. App. LEXIS 3077
CourtAppellate Court of Illinois
DecidedAugust 3, 1978
Docket76-581
StatusPublished
Cited by6 cases

This text of 379 N.E.2d 837 (Butkovich & Sons v. State Bk. of St. Charles) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Butkovich & Sons v. State Bk. of St. Charles, 379 N.E.2d 837, 62 Ill. App. 3d 810, 20 Ill. Dec. 4, 1978 Ill. App. LEXIS 3077 (Ill. Ct. App. 1978).

Opinion

Mr. JUSTICE WOODWARD

delivered the opinion of the court:

George Butkovich & Sons, Inc., building contractors, filed suit to foreclose a mechanics lien for work performed on defendant Hubert Grane, Jr’s home at 33 Mockingbird Lane, Oak Brook, Illinois.

On May 16, 1969, the parties entered into a contract under which plaintiff would provide and perform the following:

“Excavating, backfilling, no hauling, concrete, caissons, caisson rebars, masonry S70/M, steel, gravel for drive, flat work, fibre glass water proofing, glass blocks, cleaning, basement windows, install under ground garbage cans furnished by owner, meet grade provisions according to Oakbrook standards, chimney.
Concrete mortar for brick sills.
Rear patio square footage as per plan — shape to be decided by owner.”

The contract further provided:

“WE [plaintiff] PROPOSE to furnish labor and material— complete in accordance with above specifications, and subject to conditions found on both sides of this agreement, for the sum of Nineteen thousand two hundred ninety — dollars (*19,290.00) Payment to be made as follows:
*10,000 upon completion of foundation and delivery of brick
*5,000.00 upon completion of brick work
Balance 30 days after completion of contract.”

Defendant paid the first *10,000 due on the contract but subsequently disputes arose concerning plaintiff’s performance; no further payments were made and plaintiff then commenced this action in which it claims the balance of the contract price plus payment for extras. Following a bench trial, the trial court found in favor of plaintiff and against defendant and awarded plaintiff *10,000 in damages. Defendant appeals.

Defendant contends that the finding of the trial court that plaintiff has substantially performed under the contract was contrary to the manifest weight of the evidence. We agree and reverse and remand this case for a new trial.

The ordinary rule applied in cases involving building contracts is that a builder is not required to perform perfectly, but rather, he is held only to a duty of substantial performance in a workmanlike manner. (Watson Lumber Co. v. Guennewig (1967), 79 Ill. App. 2d 377, 226 N.E.2d 270.) The purchaser who receives substantial performance of the building contract must pay the contract price less a credit as compensation for any deficiencies existing in what he received as to what strict performance would have given him. J-M Builders v. McIntyre (1978), 56 Ill. App. 3d 714, 372 N.E.2d 420.

On the other hand, a contractor whose work amounts to less than substantial performance has no right to the contract price; in that situation, the builder’s right is, under a theory of quantum meruit, a right to recover only reasonable compensation for value received by the purchaser over and above the injury suffered by the builder’s breach. (Brewer v. Custom Builders Corp. (1976), 42 Ill. App. 3d 668, 356 N.E.2d 565.) What will be considered substantial performance of a building contract is difficult to define and whether substantial performance has been given will depend on the relevant facts of each case. (Brewer v. Custom Builders Corp.) We shall therefore proceed to examine those facts in connection with this case.

Turning first to the omissions from the contract as alleged by defendant, it is undisputed that plaintiff failed to install water stops. According to plaintiff, a water stop could be caulking or a solid material poured up against a wall with fresh concrete; according to defendant, a water stop is a piece of usually vinyl material, nonporous in nature that is placed in between the cement floor and the foundation wall. The parties in general did agree that the purpose of water stops is to prevent water from coming in.

While admitting that the water stops were not installed, plaintiff argues that the contract makes no reference to water stops, that water stops are mentioned only in the specifications for the house. Further, that there was no testimony that the absence of water stops contributed to the water in defendant’s premises.

While the trial court found nothing in the evidence to show that defendant’s water problem was proximately caused by the lack of water stops, the real question here is whether plaintiff did comply with the terms of the contract. The contract itself does not enumerate that water stops were to be installed; however, the contract here, which is set out above, is in quite general terms and would be difficult, if not impossible, to carry out without the use of the specifications, which, according to plaintiff, did require the installation of water stops. Further, the supplemental conditions provide in part:

“The contract and documents shall consist of the specifications, the drawings, the proposal form and the Owner-Contractor Agreement. # ” ””

Finally, there was testimony that prior to entering into the contract, the parties held lengthy discussions on the potential water problem in connection with the plans and specifications for defendant’s residence.

Defendant contends that while the plans called for the installation of wire mesh and reinforcing wire under all floors, plaintiff failed to install reinforcing wire mesh in the basement floor. Plaintiff argues that the reinforcing mesh, like the water stops, was not mentioned in the contract, and that defendant offered no testimony that any damage was suffered as a result of such an omission. However, John Butkovich, supervisor for plaintiff, testified that page three of the specifications calls for reinforcing wire; it was placed in the garage floor, but he did not know about the basement floor; as a rule they do not put it in the basement floor.

Next, defendant contends that plaintiff failed to recess the glass blocks. Butkovich testified that the plans did call for a four-inch recess of the glass blocks, but that he was unable to do so because the carpenter had placed studs in the drywall in such a way that the glass blocks could not be recessed. However, he also stated that he did not believe he had called this to the defendant’s attention.

The plans also called for the installation of underground garbage cans, which were never installed. According to plaintiff, defendant had obtained the wrong sized cans and told plaintiff he would contact plaintiff to finish up the work, which defendant never did.

Defendant also alleged instances of the poor quality of plaintiff’s workmanship. Defendant contends that a particularly serious error was plaintiff’s failure to comply with the plans supplied by defendant’s structural engineer, A. C. Alexander.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

M.J. Oldenstedt Plumbing Co. v. K Mart Corp.
629 N.E.2d 214 (Appellate Court of Illinois, 1994)
Evans and Associates, Inc. v. Dyer
615 N.E.2d 770 (Appellate Court of Illinois, 1993)
Folk v. Central National Bank & Trust Co.
567 N.E.2d 1 (Appellate Court of Illinois, 1991)
Stone v. City of Arcola
536 N.E.2d 1329 (Appellate Court of Illinois, 1989)
Luczak Brothers, Inc. v. Generes
451 N.E.2d 1267 (Appellate Court of Illinois, 1983)
Mayfield v. Swafford
435 N.E.2d 953 (Appellate Court of Illinois, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
379 N.E.2d 837, 62 Ill. App. 3d 810, 20 Ill. Dec. 4, 1978 Ill. App. LEXIS 3077, Counsel Stack Legal Research, https://law.counselstack.com/opinion/butkovich-sons-v-state-bk-of-st-charles-illappct-1978.