Builder's Concrete v. Faubel & Sons, Inc.

373 N.E.2d 863, 58 Ill. App. 3d 100, 15 Ill. Dec. 517, 1978 Ill. App. LEXIS 2263
CourtAppellate Court of Illinois
DecidedMarch 13, 1978
Docket77-187
StatusPublished
Cited by49 cases

This text of 373 N.E.2d 863 (Builder's Concrete v. Faubel & Sons, Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Builder's Concrete v. Faubel & Sons, Inc., 373 N.E.2d 863, 58 Ill. App. 3d 100, 15 Ill. Dec. 517, 1978 Ill. App. LEXIS 2263 (Ill. Ct. App. 1978).

Opinion

Mr. PRESIDING JUSTICE STENGEL

delivered the opinion of the court:

Plaintiff, Builder’s Concrete Co. of Morton, brought this breach of contract action against defendant, Fred Faubel and Sons, Inc., to recover unpaid rent and the cost of repairing certain vehicles which plaintiff leased to defendant under a written agreement. Defendant counterclaimed seeking liquidated damages for plaintiff’s refusal to convey the property under an option to purchase clause. After a bench trial the Circuit Court of Tazewell County denied plaintiff’s claim for unpaid rent, but awarded plaintiff the costs of repair. Defendant’s counterclaim was denied. Cross-appeals are taken from the trial court’s rulings.

The basic facts of the case are not in dispute. On August 1, 1974, plaintiff Builders, and defendant Faubel, entered into a written contract whereby plaintiff agreed to lease to defendant a number of trucks, a truck shed and various other pieces of equipment for use in defendant’s ready-mix concrete business. The specified duration of the lease was one year with defendant to make payments of *8,500 on August 1, and a like sum on the first day of each succeeding month. The parties agreed that the fair rental value of the property was *3,500 monthly and the additional *5,000 was to be paid to prevent repossession of the property by plaintiff’s secured creditors. Included in the contract was an option to purchase clause under which defendant, upon proper notice to plaintiff, could elect to purchase the leased property and apply 58.82% (*5,000) of each rent payment toward the purchase price. It was further provided that should plaintiff, after demand, refuse to convey the property, defendant would be entitled to liquidated damages amounting to 58.82% of the total payments made. Terms of the agreement required defendant to provide full maintenance and insurance coverage on the leased vehicles. The lease, which was prepared by defendant, made time of the essence and provided that upon default by the lessee, the lessor was to recover as liquidated damages 50% of the rent due during the unexpired tenure of the agreement.

Defendant was late with each of its first four monthly payments; the August payment was made on September 30, the September and October payments on October 10 and the November payment on November 4. Each payment was accepted by plaintiff when tendered. An insurance premium on the vehicles was due in October. Defendant did not pay the premium, but the agent who supplied the insurance did, based on defendant’s guarantee that the payment would be forthcoming. At no time during the life of the lease was the property uninsured. On November 26, 1974, defendant received a letter from plaintiff which stated:

“Based on recent management decisions by your company, Builders Concrete and Material, Inc. refuses to transfer any assets to your company, Fred Faubel & Sons, Inc.”

The letter further demanded that defendant return all of the leased property to plaintiff’s Morton location by December 31, 1974. On December 5, defendant tendered its December rent which was accepted by plaintiff. Defendant also paid the October insurance premium and on December 31, complied with plaintiff’s demand by returning all of the leased property to plaintiff’s place of business in Morton.

Plaintiff initiated the instant action in January 1976, alleging that defendant breached the contract by failing to make timely rent and insurance premium payments. Plaintiff sought liquidated damages totaling 50% of the unpaid rent as well as *1,650 as the costs of repairing two vehicles which it claimed were inoperable when returned by defendant. Defendant denied breaching the contract and counterclaimed to recover 58.82% of the money it had paid plaintiff as liquidated damages for plaintiff’s refusal to convey the property. The trial court found that defendant did not breach the contract and denied plaintiff’s claim for unpaid rent. However, defendant’s counterclaim was also denied on the grounds the defendant did not demand conveyance of the property after receiving plaintiff’s November 26 letter. Plaintiff was allowed to recover *1,461.57 as the costs of repairing two of the leased vehicles. On appeal, each party contests the denial of its claim for liquidated damages and defendant also challenges the award of costs of repair to plaintiff.

We must first determine the effect of plaintiff’s November 26 letter to defendant in which plaintiff disclaimed any intention of conveying the leased property and demanded that defendant return same to plaintiff by December 31, 1974. Plaintiff contends the letter was a justified rescission of the agreement based on defendant’s breaches of contract. Cited as breaches justifying rescission are defendant’s tardiness in making the first four rent payments and defendant’s failure to pay the October insurance premium. Plaintiff’s argument places particular emphasis on the contract provision making time of the essence. Defendant, on the other hand, denies being in breach of contract and claims that plaintiff’s letter constituted an anticipatory repudiation by plaintiff of its contractual duties. Defendant notes that all rent was paid up to date on November 26, and the property was fully insured.

It is well established that a party may terminate or rescind a contract because of substantial nonperformance or breach by the other party. (Forest Preserve Real Estate Improvement Corp. v. Miller (1942), 379 Ill. 375, 41 N.E.2d 526.) The determination of what constitutes substantial nonperformance justifying rescission is for the trier of fact. (Sampson v. Marra (2d Dist. 1951), 343 Ill. App. 245,98 N.E.2d523.) The trial judge in this case, sitting without a jury, determined that defendant was not in breach of contract on November 26, and we see no reason to disturb that determination. By accepting the late rent payments, plaintiff waived any objection to their tardiness. (Cottrell v. Gerson (1939), 371 Ill. 174, 20 N.E.2d 74.) This is true notwithstanding the contract clause making time of the essence. (12 Ill. L. & Prac. Contracts §412 (1955).) Furthermore, defendant’s failure to make timely payment of the October insurance premium need not be considered as a substantial nonperformance of its contractual obligation since defendant did guarantee payment, and the property remained fully insured. This arrangement may not have met the precise expectations of the parties to the contract, but it did fulfill the parties’ mutual goal of protecting the leased property. It was not error for the trial court to find that defendant sufficiently performed its part of the bargain, and to deny plaintiff’s claim for unpaid rent.

Having determined that defendant did not breach the contract, the next question is whether plaintiff breached the contract by renouncing its duty to convey the leased property. Defendant contends plaintiff’s November 26 renunciation was an anticipatory repudiation and that, when acted upon by defendant on December 31, the repudiation became a breach of contract by plaintiff. We agree. Unless justified, a definite statement to the promissee that the promissor will not perform its contractual duties constitutes an anticipatory repudiation. (Stonecipher v. Pillatsch (2d Dist. 1975), 30 Ill. App.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pinkert v. Boardwalk Birch Companies, LLC.
2023 IL App (1st) 221953-U (Appellate Court of Illinois, 2023)
Calvin Horne v. Electric Eel Manufacturing Com
987 F.3d 704 (Seventh Circuit, 2021)
GK Development, Inc. v. Iowa Malls Financing Corporation
2013 IL App (1st) 112802 (Appellate Court of Illinois, 2014)
GK Development, Inc. v. Iowa Malls Financing Corporation
2013 IL App (1st) 112802 (Appellate Court of Illinois, 2014)
Arlington LF, LLC v. Arlington Hospitality, Inc.
637 F.3d 706 (Seventh Circuit, 2011)
In Re Arlington Hospitality, Inc.
368 B.R. 702 (N.D. Illinois, 2007)
Tower Investors, LLC v. 111 East Chestnut Consultants, Inc.
864 N.E.2d 927 (Appellate Court of Illinois, 2007)
Highlands Ranch University Park, LLC v. Uno of Highlands Ranch, Inc.
129 P.3d 1020 (Colorado Court of Appeals, 2005)
Pope Ex Rel. Pope v. Economy Fire & Cas.
779 N.E.2d 461 (Appellate Court of Illinois, 2002)
Pope v. Economy Fire & Casualty Co.
Appellate Court of Illinois, 2002
Horbach v. Kaczmarek
988 F. Supp. 1126 (N.D. Illinois, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
373 N.E.2d 863, 58 Ill. App. 3d 100, 15 Ill. Dec. 517, 1978 Ill. App. LEXIS 2263, Counsel Stack Legal Research, https://law.counselstack.com/opinion/builders-concrete-v-faubel-sons-inc-illappct-1978.