City of Marshall v. City of Casey

532 N.E.2d 1121, 177 Ill. App. 3d 1065, 127 Ill. Dec. 292, 1989 Ill. App. LEXIS 4
CourtAppellate Court of Illinois
DecidedJanuary 9, 1989
Docket4-88-0550
StatusPublished
Cited by13 cases

This text of 532 N.E.2d 1121 (City of Marshall v. City of Casey) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Marshall v. City of Casey, 532 N.E.2d 1121, 177 Ill. App. 3d 1065, 127 Ill. Dec. 292, 1989 Ill. App. LEXIS 4 (Ill. Ct. App. 1989).

Opinion

JUSTICE SPITZ

delivered the opinion of the court:

Plaintiff City of Marshall appeals from the order of the circuit court of Clark County dismissing its three-count amended complaint against the defendants, City of Casey and City of Martinsville. Plaintiff’s amended complaint involves allegations centered around three sets of written contracts.

On June 11, 1964, the parties hereto entered into a written contract with Midwestern Gas Transmission Co. (hereinafter Midwestern) whereby the three cities would be supplied natural gas. This contract was superseded by a new contract on May 24, 1983, and then again by yet another contract entered into on April 15, 1985. Under the terms of these contracts, the three cities, collectively referred to as “Buyer,” are to receive from Midwestern the quantities of gas specified and to pay Midwestern at the rate calculated pursuant to the terms of the contract. For clarity, this first set of contracts will be referred to as the “Midwestern agreement.”

Prior to contracting with Midwestern, Casey and Marshall entered into a second contract called a “Transportation Agreement,” which was dated February 5, 1962. By this transportation agreement, Marshall agreed to transfer and deliver to Casey all the natural gas requirements of Casey and Marshall, not to exceed the combined total peak day allocations approved by the Federal Power Commission (FPC). The point of delivery was a metering station constructed and maintained by Marshall. Casey agreed to pay one cent per thousand cubic feet (Mcf) as recorded on the meter identified as the “Casey meter.” Marshall was to bill this charge monthly.

This transportation agreement was amended January 1, 1974. The amendment recites that Casey and Marshall had “fully complied with all of the terms, conditions and provisions” of the 1962 agreement, but they decided to amend that earlier agreement in order to more nearly equalize between the parties the costs and expenses being incurred in connection with the transportation of natural gas. The amendment raised the fee Casey was to pay Marshall to 3.3$ per Mcf.

A third contract was entered into by the three cities with regard to the purchase, distribution, and payment for natural gas supplied by Midwestern. This contract, dated June 8, 1964, set forth the procedure to be used to determine the amount each city was to pay Midwestern for the gas supplied. At the end of each billing period, representatives of each city were to jointly read the respective meters, and it is from these readings that the amount of gas used by each city during each billing period is to be determined. In order to determine the amount of gas delivered to Marshall, the agreement provided that the total volume of gas delivered by Midwestern, as measured at the “Marshall meter,” was to be reduced by the amount recorded on the Casey meter. The amount delivered to Casey was to be established by the volume recorded on the Casey meter, less the volume shown on the “Martinsville meter” (installed by Casey near Martinsville). Deliveries to Martinsville are measured by the volume recorded on the Martinsville meter. Midwestern was to bill Marshall, with a copy going to Casey and Martinsville as well. Casey and Martinsville were then to deliver payment to Marshall which was, in turn, to remit all their payments to Midwestern.

With regard to the instant litigation, Marshall considers paragraph 4 of the June 8, 1964, agreement to be significant. Paragraph 4 states:

“4. The amount which each city shall owe to Midwestern for each billing period shall be determined by applying the rates, as specified in the contract between the municipalities and Midwestern, and as approved by the Federal Power Commission, to the meter reading for such billing period.”

Marshall initially filed a complaint on February 28, 1986, consisting of two counts against Casey only. Subsequently, Marshall filed an amended complaint on April 9, 1987, containing two counts. Count I was directed against Casey and Martinsville. Count II was directed against the City of Casey alone. Marshall later added count III, directed against Casey and Martinsville.

Under count I of the amended complaint, Marshall sought recovery from the defendants under an implied, equitable contribution theory based on the Midwestern agreements. Count II asks the court to require Casey to pay Marshall $3,863.74 for unpaid transportation costs occasioned by plaintiff’s failure to utilize a factor of supercompressibility in measuring the amount of gas transported between March 1, 1976, and April 30, 1985. Count III seeks recovery for breach of the June 8, 1964, written contract because, according to Marshall: (1) paragraph 4 of said contract requires the rates to be those specified in the Midwestern agreement, as approved by the FPC and as applied to the meter readings; (2) article IV of the Midwestern agreement provides that the legally effective rate shall be that contained in Midwestern’s rate schedule as filed with the FPC, together with the general terms and conditions applicable thereto; and (3) volume one, general terms and conditions, paragraph III, subparagraph 2, of the Federal Energy Regulatory Commission Gas Tariffs provides for a supercompressibility factor to be applied in the determination of the volume and value of gas delivered by the seller.

In addition to the complaint, the record contains the plaintiff’s answer to a request for admission of facts. Plaintiff admits: (1) the “Casey meter,” was purchased and installed by plaintiff; (2) the “Casey meter” is owned by plaintiff and has been maintained by plaintiff at all times; (3) the volume of natural gas delivered to Casey and Martinsville has been recorded on the “Casey meter,” which is read by plaintiff; and (4) the City of Casey has remitted payment in each billing period for natural gas deliveries made to it as contemporaneously measured by the data recorded on the “Casey meter.”

On the motions of both defendants, made pursuant to sections 2—615 and 2—619 of the Code of Civil Procedure (Ill. Rev. Stat. 1987, ch. 110, pars. 2—615, 2—619), the trial court dismissed the complaint with prejudice because all three counts are barred by the respective statute of limitations and count I fails to state a cause of action for equitable contribution based on the underlying relationship of the parties as governed by the written contracts. In this appeal, the first question which must be addressed is whether the facts alleged in the three counts of plaintiff’s amended complaint state a cause of action against defendants.

While the trial court’s order dismissed only count I for failing to state a cause of action, the sufficiency of each of the counts was attacked by the defendants in their motions, and even though the trial court did not rely on this ground to dismiss counts II and III, a reviewing court may consider whether the judgment is justified for any reason or ground appearing of record. (Farmers State Bank v. Webel (1983), 113 Ill. App. 3d 87, 446 N.E.2d 525.) In considering motions to dismiss pursuant to section 2—615, all well-pleaded facts in the complaint are taken as true and the only question is whether the complaint is legally sufficient. Johnson v. Nationwide Business Forms, Inc.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Archon Construction Co. Inc. v. U.S. Shelter, LLC
2017 IL App (1st) 153409 (Appellate Court of Illinois, 2017)
Braye v. Archer-Daniels-Midland Co.
659 N.E.2d 430 (Appellate Court of Illinois, 1995)
Campbell v. AC EQUIPMENT SERVICES CORPORATION, INC.
610 N.E.2d 745 (Appellate Court of Illinois, 1993)
Martin v. See
598 N.E.2d 321 (Appellate Court of Illinois, 1992)
General Electric Capital, Corp. v. Equifax Services, Inc.
797 F. Supp. 1432 (N.D. Illinois, 1992)
McGee v. Ractian Construction Co.
596 N.E.2d 1261 (Appellate Court of Illinois, 1992)
Wilson v. Franklin Life Insurance
596 N.E.2d 1173 (Appellate Court of Illinois, 1992)
Bankier v. First Federal Savings & Loan Association of Champaign
588 N.E.2d 391 (Appellate Court of Illinois, 1992)
Stone v. City of Arcola
536 N.E.2d 1329 (Appellate Court of Illinois, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
532 N.E.2d 1121, 177 Ill. App. 3d 1065, 127 Ill. Dec. 292, 1989 Ill. App. LEXIS 4, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-marshall-v-city-of-casey-illappct-1989.