Premier Electrical Construction Co. v. City of Chicago

512 N.E.2d 44, 159 Ill. App. 3d 98, 111 Ill. Dec. 140, 1987 Ill. App. LEXIS 2944
CourtAppellate Court of Illinois
DecidedJuly 29, 1987
Docket86-2931
StatusPublished
Cited by5 cases

This text of 512 N.E.2d 44 (Premier Electrical Construction Co. v. City of Chicago) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Premier Electrical Construction Co. v. City of Chicago, 512 N.E.2d 44, 159 Ill. App. 3d 98, 111 Ill. Dec. 140, 1987 Ill. App. LEXIS 2944 (Ill. Ct. App. 1987).

Opinion

PRESIDING JUSTICE McNAMARA

delivered the opinion of the court:

Plaintiff Premier Electrical Construction Company appeals from an order dismissing its breach of contract action against defendant city of Chicago for failure to state a cause of action. The underlying contract dispute concerns plaintiff’s right as a general contractor to substitute a type of equipment different than the equipment specified in the contract without defendant’s approval.

On November 16, 1984, defendant advertised for sealed bids for a construction contract to improve the airfield lighting control tower at O’Hare International Airport. On May 7, 1985, defendant awarded the contract to plaintiff. Defendant directed plaintiff to begin work on June 3,1985, and to complete the project on December 5,1985.

On May 22, 1985, defendant asked plaintiff for a list of its material suppliers for approval. On June 12, 1985, plaintiff submitted the list, specifying Texas Instruments as supplier of various lighting equipment, and requesting defendant’s approval of the list. On June 19, 1985, defendant sent plaintiff a document acknowledging receipt of the list of suppliers. The document indicates under “Disposition” that defendant “will keep this information on file.” Under “Action Required — Conditions of Approval,” the document states that equipment must be in full compliance with the contract plans and specifications, and that the acknowledgement “does not relieve you, as general contractor, from any responsibility for compliance with the terms of this contract.”

On July 23, 1985, plaintiff submitted shop drawings and product information to defendant, again listing Texas Instruments as the supplier of certain lighting equipment. On August 14, 1985, defendant wrote to plaintiff, informing it that the Texas Instruments equipment could not be substituted for the Cutler-Hammer, Eaton Corporation lighting equipment required by the contract. An August 15, 1985, mailgram to defendant requested a detailed explanation of its rejection of plaintiff’s proposed supplier.

On August 19, 1985, defendant wrote to plaintiff, rejecting Texas Instruments as a supplier on the basis that plaintiff had failed to submit the proper documentation seeking approval 14 days prior to bid opening, as required by section L — 100.2.8 of the contract, which provides:

“Any exception, change or modification of the requirements of the specifications contained hereinafter will be cause for unequivocal rejection of the manufacturer’s offered equipment. However, in order to allow sufficient time for the engineer to evaluate the type and quality of equipment and system competency being offered under this Item by the manufacturers, any manufacturer intending to bid shall submit in writing to the Commissioner of Public Works — City of Chicago, fourteen (14) days prior to the date set for the opening bids on this project the following descriptive literature and drawings for all equipment being offered under this item:
1. Specifications, literature and drawings showing general dimensions of all equipment offered.
2. Interconnections, and wiring arrangements for such equipment, accessories and systems.
3. Shop drawings showing the individual system schematics of the equipment.
4. List of all equipment offered.
5. Furnish written guarantee that this equipment will perform equally or better as the designed system per technical specifications.”

Defendant directed plaintiff to submit documentation for the specified system by September 11, 1985. Failure to do so would indicate plaintiff’s “unwillingness to pursue and complete this project prior to the completion date of December, 1985.”

On September 6, 1985, defendant notified plaintiff that the matter had been referred to defendant’s purchasing agent for a final decision. On October 30, 1985, the purchasing agent informed plaintiff that the Texas Instruments system was not acceptable because it was not specified in the contract, and because plaintiff had not sought defendant’s approval for an “equal” either prior to or at the time of the bid opening. Plaintiff was given 10 days from receipt of the letter to comply with the contract specification or be considered in default of the contract. Plaintiff received the letter on November 4,1985.

Plaintiff initially appealed to the Federal Aviation Administration, which found that defendant had not violated any Federal law or regulation by specifying a brand name “or equal” in its contract.

On November 12, 1985, plaintiff filed an action against defendant and the FAA in Federal district court, alleging violation of Federal procurement regulations and breach of contract. On December 2, 1985, the district court dismissed defendant as a party in that case for lack of Federal jurisdiction.

On December 3, 1985, plaintiff filed this action seeking injunctive and declaratory relief. On December 4, plaintiff filed a motion for a temporary restraining order (TRO) to enjoin defendant from declaring plaintiff in default on the contract or employing another contractor to complete the work. On December 4, the trial court denied the motion.

On December 5, 1985, plaintiff delivered a written notice to defendant stating that it would use the Cutler-Hammer, Eaton Corporation equipment as specified in the contract. The letter stated that such performance was “under PROTEST.” Plaintiff requested an additional $239,639 as compensation for the contract “change.” Plaintiff also requested an extension of time for completion of the project. Finally, plaintiff informed defendant that “[sjhould the system fail to perform, we suggest that you look to your engineers for resolution.” Later that day, defendant served plaintiff with notice declaring plaintiff to be in default on the contract pursuant to the 10-day notice issued on October 30, 1985. Plaintiff again stated it would install the equipment as requested by defendant, but defendant refused the offer.

On December 16, 1985, plaintiff again filed an unsuccessful motion for TRO. Plaintiff also filed an amended complaint, adding allegations concerning defendant’s refusal to permit plaintiff to install the requested equipment. On June 13, 1986, the amended complaint was dismissed. Plaintiff filed a second amended complaint on July 11, 1986, and on September 25, 1986, the trial court dismissed the complaint without leave to refile.

Plaintiff contends that the trial court erred in dismissing its complaint for failure to state a cause of action. Pleadings should be liberally construed, but the complaint must allege facts necessary to state a cause of action. (Parrillo v. 1300 Lake Shore Drive Condominium (1981), 103 Ill. App. 3d 810, 431 N.E.2d 1221.) Basic legal deficiencies in a pleading cannot be aided by a general rule of liberal construction. (Consentino v. Price (1985), 136 Ill. App. 3d 490, 483 N.E.2d 297

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Unterschuetz v. City of Chicago
803 N.E.2d 988 (Appellate Court of Illinois, 2004)
Nuccio v. Chicago Commodities, Inc.
628 N.E.2d 1134 (Appellate Court of Illinois, 1993)
Fireman's Fund Mortgage Corp. v. Zollicoffer
719 F. Supp. 650 (N.D. Illinois, 1989)
City of Marshall v. City of Casey
532 N.E.2d 1121 (Appellate Court of Illinois, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
512 N.E.2d 44, 159 Ill. App. 3d 98, 111 Ill. Dec. 140, 1987 Ill. App. LEXIS 2944, Counsel Stack Legal Research, https://law.counselstack.com/opinion/premier-electrical-construction-co-v-city-of-chicago-illappct-1987.