Roy Strom Excavating & Grading Co. v. Miller-Davis Co.

509 N.E.2d 105, 149 Ill. App. 3d 1093, 108 Ill. Dec. 679, 1986 Ill. App. LEXIS 3143
CourtAppellate Court of Illinois
DecidedNovember 6, 1986
Docket85-0986
StatusPublished
Cited by1 cases

This text of 509 N.E.2d 105 (Roy Strom Excavating & Grading Co. v. Miller-Davis Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Roy Strom Excavating & Grading Co. v. Miller-Davis Co., 509 N.E.2d 105, 149 Ill. App. 3d 1093, 108 Ill. Dec. 679, 1986 Ill. App. LEXIS 3143 (Ill. Ct. App. 1986).

Opinion

JUSTICE JOHNSON

delivered the opinion of the court:

Illinois Building Authority (IBA), defendant, counterdefendant, appeals from that portion of the trial court’s order that granted the claims filed against it by Miller-Davis Company (Miller-Davis), defendant-counterplaintiff, and Roy Strom Excavating and Grading Company, Inc. (Strom), plaintiff-counterdefendant. Miller-Davis appeals that part of the trial court’s order that granted Strom’s claims against it and denied its counterclaims against Strom.

The sole issue presented for review by IBA is whether the Court of Claims has exclusive jurisdiction to hear claims filed against it that arose from the contract between it and Miller-Davis.

Miller-Davis presents the following arguments for review: (1) whether the court erred in granting Strom’s request for prejudgment interest; (2) whether exculpatory clauses in the contract take precedence over a change-conditions clause in the contract between it and Strom; (3) whether pertinent provisions of the contract required Strom to perform a soil analysis; and (4) whether Strom is responsible for extra costs incurred (by Miller-Davis) due to Strom’s alleged failure to perform backfilling, pursuant to terms of the contract.

We affirm in part and reverse in part.

This lawsuit concerns claims arising from the construction of an instructional unit at the College of Du Page in Glen Ellyn. On July 24, 1970, IBA, as owner, awarded Miller-Davis the general contract to construct the unit. Miller-Davis then subcontracted the excavating and backfilling work to Strom for $575,000, pursuant to a written contract.

Upon its commencement of work on the project, Strom immediately encountered unforeseen soil problems. Poor soil conditions on the jobsite continued to plague the project, precipitating a substantial increase in the amount of time, labor, materials, and equipment estimated to complete the project. As a result of Strom’s delay in completing its portion of the project, other parts of the project were also delayed.

Testimony at trial revealed that discovery of peat and unstable soil conditions was unexpected by all parties concerned. Miller-Davis’ project superintendent, Harry Langlois, testified that in analyzing the contract documents and the borings, he did not see anything indicating peat pockets anywhere. Similarly, John Coletta, Miller-Davis’ project engineer, testified that the unstable soil conditions were not foreseen by Miller-Davis because they did not appear on the soil-boring logs supplied by IBA.

G.E Murphy & Associates, not a party to this action, was hired to design the building in question. G.F. Murphy engaged Soil Testing Services, not a party to this action, to perform subsurface-soil borings, tests, and analyses on the property that was to become the building site. IBA supplied the boring logs to bidders for the general contract. Upon awarding the general contract, the results of the soil-boring logs were incorporated into the contract between IBA and Miller-Davis. Miller-Davis, in turn, supplied the soil-boring logs to bidders for its excavation and backfilling subcontract. Strom was awarded the subcontract and the results of the soil-boring logs were incorporated into the contract between Strom and Miller-Davis.

Due to the unstable soil conditions, Strom made changes in material use, equipment use, and excavating procedures. The job was structured by Strom in accordance with the information provided on the soil-boring logs, which Miller-Davis furnished. Thus, the soil-boring logs were the primary source in determining the cost of completing the project, what would be required to complete it, and how it would be completed.

As a result of the extra costs incurred due to the unstable soil conditions, Strom, pursuant to a change-conditions clause in the contract, requested additional compensation from Miller-Davis. Miller-Davis did grant Strom some additional compensation, but not all it had requested. The record is not clear as to whether the additional compensation was granted pursuant to the change-conditions clause.

Miller-Davis requested Strom to compensate it for extra costs incurred due to Strom’s delay in completing its portion of the project and indemnification from IBA on Strom’s claims against it. After a thorough hearing on the various claims and counterclaims, the trial court issued a 69-page order. It is from portions of that order that the parties appeal.

IBA v. Miller-Davis and Strom

IBA contends that the trial court should have dismissed all claims filed against it by Strom and Miller-Davis. IBA argues that because the claims were founded on a contract between it and Miller-Davis the claims should have been filed in the Court of Claims. We agree.

Any claims against a State agency founded upon a contract must be filed in the Court of Claims. The Court of Claims has exclusive jurisdiction. (Talandis Construction Corp. v. Illinois Building Authority (1978), 60 Ill. App. 3d 715, 717, 377 N.E.2d 237, 239.) Miller-Davis and Strom argue that, for purposes of this suit, IBA should not be considered a State agency since at the time it entered into the contract it was not a State agency.

Miller-Davis and Strom are correct in stating that when the contract was entered into IBA was not a State agency. However, subsequent to the signing of the contract, IBA, by legislative action, was made a State agency. (See People ex rel. Resnik v. Curtis & Davis, Architects & Planners, Inc. (1978), 58 Ill. App. 3d 28, 373 N.E.2d 772, aff’d (1980), 78 Ill. 2d 381, 400 N.E.2d 918.) The issue, therefore, is whether the legislation will be applied retroactively to contracts entered into before such legislation was enacted.

In Talandis Construction Corp. v. Illinois Building Authority (1978), 60 Ill. App. 3d 715, 719, 377 N.E.2d 237, 241, the court considered whether the legislation would be applied retroactively. After an extensive and thorough analysis of the issue, the court determined that IBA’s status as a State agency would be applied retroactively to any contracts entered into before the legislation making IBA a State agency was enacted. The court reasoned that there was nothing in the statutory scheme of the legislation that indicated an intent to withdraw circuit court jurisdiction only for determinations made since a certain date. It further reasoned that the legislation’s declaration that IBA is a State agency implied that actions against IBA founded in contract had to be pursued in the Court of Claims. (60 Ill. App. 3d 715, 720, 377 N.E.2d 237

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stone v. City of Arcola
536 N.E.2d 1329 (Appellate Court of Illinois, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
509 N.E.2d 105, 149 Ill. App. 3d 1093, 108 Ill. Dec. 679, 1986 Ill. App. LEXIS 3143, Counsel Stack Legal Research, https://law.counselstack.com/opinion/roy-strom-excavating-grading-co-v-miller-davis-co-illappct-1986.