All States Home Improvement v. Beltz

CourtCourt of Appeals of Kansas
DecidedApril 17, 2026
Docket128851
StatusUnpublished

This text of All States Home Improvement v. Beltz (All States Home Improvement v. Beltz) is published on Counsel Stack Legal Research, covering Court of Appeals of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
All States Home Improvement v. Beltz, (kanctapp 2026).

Opinion

NOT DESIGNATED FOR PUBLICATION

No. 128,851

IN THE COURT OF APPEALS OF THE STATE OF KANSAS

ALL STATES HOME IMPROVEMENT, LLC, Appellee,

v.

KELLY BELTZ, Appellant.

MEMORANDUM OPINION

Appeal from Sedgwick District Court; KATHLEEN N. WATSON, magistrate judge. Submitted without oral argument. Opinion filed April 17, 2026. Reversed and remanded with directions.

Joshua S. Albin, of Adams Jones Law Firm, P.A., of Wichita, for appellant.

Michael A. Priddle, of Law Office of Michael A. Priddle, LLC, of Wichita, for appellee.

Before HILL, P.J., PICKERING and BOLTON FLEMING, JJ.

PER CURIAM: All States Home Improvement, LLC (All States), filed a breach of contract action against Kelly Beltz, alleging default on a contract for a bathroom remodel. Beltz answered, claiming the contract had been rescinded. After some initial discovery, All States filed a motion for summary judgment, which a magistrate judge granted.

On appeal, Beltz argues that genuine issues of material fact should have precluded summary judgment. We agree. Whether Beltz ever received a notice that required him to rescind the contract in writing remained in dispute. And a genuine issue of material fact

1 also remained as to the amount of damage suffered by All States since it did not complete the project. Accordingly, we reverse and remand for trial.

FACTUAL AND PROCEDURAL BACKGROUND

On February 13, 2024, All States entered into a contract with Kelly Beltz to complete a bathroom remodeling project. The contract was signed by Beltz and a representative of All States, Megan Napolitano-Robe. The total contract price was $14,341, to be paid at $204.92 per month over 120 months, with payments starting 30 days after project completion.

On July 23, 2024, All States filed a petition in district court alleging Beltz was in default under the contract. It claimed that Beltz had not paid the sum owed and All State had suffered damages because it had purchased materials, paid for labor, and paid commissions related to the contract. Beltz answered, claiming he had properly rescinded the contract.

On September 26, 2024, All States filed a motion for summary judgment. At the time All States filed its motion, discovery was not complete. As a result, on October 17, 2024, Beltz asked for additional time to answer the motion so that he could review All States' discovery responses. An agreed order was filed the following day, allowing Beltz to file his response to the summary judgment motion within 30 days of receiving All States' discovery responses. All States' discovery was provided to Beltz on October 21, 2024. On November 20, 2024, Beltz asked for an additional seven days to file his response to All States' motion for summary judgment. All States objected, stating Beltz did not provide reasons for needing additional time and the requested extension would not give All States proper time to reply prior to the hearing on the motion for summary judgment. Beltz responded by filing a motion asking for an additional extension through December 4, 2024, and also requesting a continuance of a December 6, 2024, hearing on

2 the summary judgment motion. Ultimately, Beltz filed his response to the motion for summary judgment on December 2, 2024. On December 3, 2024, All States filed a reply to Beltz' response to the motion for summary judgment.

A hearing was held on the summary judgment motion on December 6, 2024. The magistrate judge began the proceeding by stating, "Let's then start with the plaintiff's motion for summary judgment. And I'm going to just note that more time to respond to the summary—the request for more time to respond to that are going to be denied based off of the proffer that the defendant's ready to move forward." All States responded to the magistrate judge that it believed Beltz' response was untimely and that the motion should therefore be considered uncontroverted. But the magistrate judge denied All States' request, stating, "I think since everybody's here, it's worth it to hear. . . the legal arguments." The court considered the merits of the motion for summary judgment.

All States argued there were no controverted material facts precluding summary judgment. It claimed Beltz entered a contract with All States, failed to rescind it in writing, and did not pay under the terms of the contract. All States asserted it provided Beltz with a "3 Day Rescission Notice" at the time the contract was signed, and that form required written notice to cancel the contract. In response, Beltz admitted that he knew he needed to cancel the contract within three days but believed he had done so. Beltz claimed he was not aware the rescission needed to be in writing and denied receiving the "3 Day Rescission Notice" form from All States. Beltz also contested damage as All States did not complete the project. Beltz questioned whether All States ordered supplies after Beltz orally rescinded the contract. Beltz argued that these genuine issues of material fact precluded summary judgment.

On January 13, 2025, the magistrate judge signed an order allowing Beltz' attorney to withdraw from the case. By the time the judge signed the order, Beltz' attorney had been suspended from the practice of law, and the court had directed All States to send the

3 order to Beltz directly pursuant to Kansas Supreme Court Rule 170 (2025 Kan. S. Ct. R. at 230). Counsel for All States mailed the proposed order to Beltz on January 8, 2025. On January 23, 2025, counsel for All States filed a Rule 170 certificate noting that Beltz had filed no objections to the proposed order. On January 23, 2025, the magistrate judge signed the order. In the order, the magistrate judge first found that Beltz entered into a written agreement with All States on February 13, 2024.

As to rescission, the order stated:

"The written contract signed by Defendant expressly provided that 'the owner may cancel the transaction at any time up to midnight of the third business day after the date the owners sign this contract. See attached Notice of Rescission Form.[] The owners acknowledge receiving a copy of the Notice of Rescission Form. The owners acknowledge receipt of a copy of this agreement and the terms and conditions.' Exhibit D to Plaintiff's motion which was signed by Defendant on February 13, 2024. The affidavits of Plaintiff (Exhibits B and C) clearly show that the Notice of Rescission Form was given to Defendant as part of Exhibit D, that Defendant acknowledged receipt of the Notice of Rescission form, that Defendant authorized Plaintiff to do the work in Exhibit D and that Defendant accepted the terms and conditions of the written contract in Exhibit D. Defendant did not maintain any file or documents relating to the Plaintiff to dispute this fact. Defendant's Responses to Requests for Production, ¶ 2, 3. As a result, there is no genuine issue of material fact."

The court further found,

"As a result, the Court does not find the Defendant's bare allegation as to not knowing he had to provide written notice of rescission (which is contrary to his signed written agreement) or that he provided verbal rescission within three days of the cont[r]act, despite no evidence thereof, to be credible or sufficient to meet Defendant's burden to set forth specific facts showing that there is a genuine issue for trial as to those dispositive matters for which he carries the burden of proof."

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hammig v. Ford
785 P.2d 977 (Supreme Court of Kansas, 1990)
National Restoration Co. v. Merit General Contractors, Inc.
208 P.3d 755 (Court of Appeals of Kansas, 2009)
Carrothers Construction Co. v. City of South Hutchinson
207 P.3d 231 (Supreme Court of Kansas, 2009)
– GFTLenexa, LLC v. City of Lenexa –
453 P.3d 304 (Supreme Court of Kansas, 2019)
Stechschulte v. Jennings
298 P.3d 1083 (Supreme Court of Kansas, 2013)
State v. Daniels
554 P.3d 629 (Supreme Court of Kansas, 2024)

Cite This Page — Counsel Stack

Bluebook (online)
All States Home Improvement v. Beltz, Counsel Stack Legal Research, https://law.counselstack.com/opinion/all-states-home-improvement-v-beltz-kanctapp-2026.