National Restoration Co. v. Merit General Contractors, Inc.

208 P.3d 755, 41 Kan. App. 2d 1010, 2009 Kan. App. LEXIS 551
CourtCourt of Appeals of Kansas
DecidedMay 22, 2009
Docket99,936
StatusPublished
Cited by2 cases

This text of 208 P.3d 755 (National Restoration Co. v. Merit General Contractors, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
National Restoration Co. v. Merit General Contractors, Inc., 208 P.3d 755, 41 Kan. App. 2d 1010, 2009 Kan. App. LEXIS 551 (kanctapp 2009).

Opinion

*1012 Green, J.:

This case concerns the validity of a mechanic’s lien filed by Wichita Sheet Metal Supply, Inc. (WSM) under K.S.A. 60-1103(a)(1). The mechanic’s lien statement filed by WSM named Merit Construction Company, Inc., as the general contractor on a construction project when Merit General Contractors, Inc., a separate entity, was the actual general contractor. The trial court determined that the mechanic’s lien was fatally defective and unenforceable due to WSM naming the wrong general contractor. As a result, the trial court granted summary judgment in favor of Merit General Contractors, Inc.

On appeal, WSM raises a variety of arguments as to why the trial court erred in granting summary judgment to Merit General Contractors, Inc. Nevertheless, we agree with the trial court’s decision. It is uncontroverted in this case that WSM failed to name the proper general contractor in its mechanic’s lien statement, as required by K.S.A. 60-1103(a)(1). It is further uncontroverted that WSM had actual knowledge that Merit General Contractors, Inc., was the general contractor on the construction project several months before WSM filed its mechanic’s lien. With such knowledge, WSM, by acting in a reasonably diligent manner, could have verified that Merit General Contractors, Inc., was indeed the general contractor and could have properly named it on the mechanic’s hen statement. Based on the uncontroverted facts, WSM’s arguments that it should be excused from the contractor-naming requirement of K.S.A. 60-1103(a)(1) are meritless.

Finally, in its reply brief, WSM raises a new issue concerning its right to recover on a payment bond executed by Inland Insurance Company (Inland) and Merit General Contractors, Inc. Nevertheless, because WSM never raised the bond issue in its initial appellate brief filed with this court, we are unable to consider WSM’s argument. Accordingly, we affirm the trial court’s decision to grant summary judgment in favor of Merit General Contractors, Inc.

Merit General Contractors, Inc., was the general contractor on a commercial construction project known as Dillon’s Store’s Supermarket #79, located at 14301 Metcalf Avenue in Overland Park (hereinafter referred to as the Dillon’s project). Goss Service Company, Inc. (Goss), was a subcontractor supplier to Merit General *1013 Contractors, Inc., on the Dillon s project. From April 2003 through August 7, 2003, WSM provided materials to Goss for the Dillon’s project.

On June 30, 2003, Shelley Hart, WSM’s credit manager, signed a lien waiver form on behalf of WSM. The hen waiver form stated that WSM had been paid by Goss “for all materials in the amount of $2000 and/or labor by us to your firm up to and including 6-30-03 for use on the Dillons #79 and do hereby release all hen rights.” The hen waiver form was directed to and clearly named “Merit General Contractors, Inc.” As of June 30, 2003, Goss owed WSM $77,792.59, plus interest and allowable attorney fees, in unpaid invoices for die Dillon’s project.

In the summer and early fall of 2003, Hart contacted Goss because it was past due on its payments to WSM for materials provided for die Dillon’s project. In her affidavit, Hart stated that she ‘"understood Pat Larson, one of the principals of Goss, to refer to the general contractor for the Project as "Merit Construction’ as did Mike Legero, the branch manager at All American Supply.”

After receiving a hen waiver and final release, Hart wrote to Stan Bachman, the president of Merit, on September 24, 2003. The parties have not pointed to the hen waiver and final release in the record. In her letter, Hart notified Bachman that WSM was unable to sign the hen waiver and final release as there was a substantial amount due for materials on the Dillon’s project. Moreover, Hart stated that WSM would exercise its right to file a mechanic’s hen unless a substantial reduction of the debt had been made before October 24, 2003.

According to Bachman, Merit General Contractors, Inc., relied upon the hen waiver signed by WSM on June 30, 2003, when releasing payment to Goss. Moreover, Bachman stated in his affidavit that Merit General Contractors, Inc., had no knowledge that WSM was owed any money by Goss other than the $2,000 that WSM had acknowledged receiving in its June 30,2003, hen waiver. Bachman further stated that had Merit General Contractors, Inc., known that WSM was owed money by Goss, it would not have released payment to Goss.

*1014 In responding to Hart’s September 24, 2003, letter, Bachman wrote that WSM had signed the waiver form in which it had waived its lien rights for all materials shipped on or before June 30, 2003; that many of the invoices after June 30, 2003, were for hand tools or equipment purchases that were not “lienable” as they were not incorporated into tire Dillon’s project; and that WSM’s total included materials that were not incorporated into the work on the Dillon’s project. Bachman concluded his letter to Hart by stating that if WMS chose to file a lien, Merit General Contractors, Inc., would consider the hen “fraudulent and slanderous.”

Bachman’s letter was written on stationery that had “MERIT” in large letters at the top of the page. The stationery also had the headings “GENERAL CONTRACTORS,” “DESIGN/BUILD,” and “CONSTRUCTION MANAGERS” across the top of the page underneath the name “MERIT.”

In December 2003, WSM filed a mechanic’s hen on the Dillon’s property for $97,029.90, plus interest, costs, and fees, which was for materials furnished through August 7, 2003, under WSM’s contract with Goss. Hart executed the mechanic’s hen statement on behalf of WSM. In the mechanic’s hen statement, Merit Construction Company, Inc., was named as the general contractor on the Dillon’s project. When questioned about this hen during his deposition, Legero testified that he vaguely remembered Hart calling him and asking for die information, such as address, general contractor, and building permit number, that she needed for the hen. When questioned whether he filed a lot of hens, Legero testified that he filed more liens “than I would like to” and that it was “standard procedure in our business.” WSM has five branches of business with offices in surrounding states.

On December 22, 2003, a letter from WSM with an attached copy of the mechanic’s hen was dehvered to Merit Construction Company, Inc., do Stan Bachman, President, by certified mail restricted delivery. Bachman signed for the letter.

In February 2004, National Restoration Company (National) commenced the instant case by filing a petition to foreclose its mechanic’s hen on the Dillon’s property. WSM was named as a defendant in the action by virtue of WSM’s mechanic’s hen on the *1015 Dillon’s property. In March 2004, WSM filed its answer, counterclaim, and cross-claims relating to its mechanic’s lien.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

All States Home Improvement v. Beltz
Court of Appeals of Kansas, 2026
Kaufman v. Oldenettel
Court of Appeals of Kansas, 2020
Kuri v. Addictive Behavioral Change Health Group
Court of Appeals of Kansas, 2017

Cite This Page — Counsel Stack

Bluebook (online)
208 P.3d 755, 41 Kan. App. 2d 1010, 2009 Kan. App. LEXIS 551, Counsel Stack Legal Research, https://law.counselstack.com/opinion/national-restoration-co-v-merit-general-contractors-inc-kanctapp-2009.