Creme De La Creme (Kansas), Inc. v. R&R International, Inc.

85 P.3d 205, 32 Kan. App. 2d 490, 2004 Kan. App. LEXIS 189
CourtCourt of Appeals of Kansas
DecidedFebruary 27, 2004
Docket89,286
StatusPublished
Cited by6 cases

This text of 85 P.3d 205 (Creme De La Creme (Kansas), Inc. v. R&R International, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Creme De La Creme (Kansas), Inc. v. R&R International, Inc., 85 P.3d 205, 32 Kan. App. 2d 490, 2004 Kan. App. LEXIS 189 (kanctapp 2004).

Opinion

Marquardt J.;

Alpine Electrical Construction, Inc. (Alpine) appeals the trial court’s order that its mechanic’s lien filed against Creme de la Creme (Kansas), Inc. (CDLC) was not timely. We affirm.

In January 1999, CDLC contracted with R&R International, Inc. (R&R) for the construction of a new daycare facility. Later that month, R&R contracted with Alpine for a fee of $148,638 for the electrical work at tire facility.

On September 1, 1999, Alpine received a letter from R&R asking for final billings for all contract work and change orders. Joel Ford, Alpine’s project manager at the site, responded by collecting paperwork and making certain that everything was in order. On September 20, 1999, Alpine submitted its final bill to R&R. The bill stated that Alpine’s work was 100 percent complete.

Timecards for September 23 and 24,1999, show that Ernie Cota and Mike Black, employees of Alpine, spent 6 and 6.5 hours respectively at the CDLC job site. On these 2 days, the men ran power to the monument sign, placed wire cages over emergency lights in the gymnasium, and installed flagpole light sensors, time clocks, and trippers. Alpine filed a mechanic’s lien against CDLC *492 on December 23,1999, for the unpaid balance of $57,274.51, plus accrued interest.

In March 2000, CDLC filed this lawsuit against R&R and most of the subcontractors who worked on the project because R&R failed to pay the subcontractors. As a result, numerous mechanics’ liens were filed against CDLC. Alpine answered and included a counterclaim against CDLC and a cross-claim against R&R. Alpine was later awarded judgment against R&R for $69,954.17. Collection of that judgment is not part of this lawsuit.

In November 2000, CDLC filed a motion for summary judgment claiming that Alpine’s mechanic’s lien was not timely filed. Alpine responded by filing a motion for summary judgment. The trial court considered the matter of summary judgment and ruled that it could not conclude as a matter of law Alpine’s mechanic’s lien was not timely filed and denied CDLC’s motion for summary judgment. The trial court considered the matter of Alpine’s mechanic’s hen at an evidentiary hearing in January 2002. After Alpine presented its evidence, CDLC moved for judgment as a matter of law. CDLC’s motion was granted. The trial court found that most of the work performed by Alpine on September 23 and 24, 1999, was done as a courtesy and, thus, could not be used to extend the time in which to file a mechanic’s lien. The trial court ruled that the testimony concerning the installation of the photocells was inconsistent and that work could not be used to extend the time in which to file a mechanic’s lien. Alpine timely appeals.

Alpine claims that its time for filing a mechanic’s lien was extended because of its work consisting of: (1) tying in and internally wiring the monument sign; (2) installing time clocks and trippers; (3) installing wire guards for emergency lights located in the gymnasium; and (4) installing photocell lighting on the flagpoles.

On appeal, Alpine argues that the trial court erred by finding that the work performed was done as a courtesy.

Our standard of review requires us to determine whether the trial court’s findings are supported by substantial competent evidence and whether the findings are sufficient to support the trial court’s conclusions of law. Manhattan Mall Co. v. Shult, 254 Kan. 253, 254, 864 P.2d 1136 (1993). Substantial evidence is such legal *493 and relevant evidence as a reasonable person might accept as sufficient to support a conclusion. Unrau v. Kidron Bethel Retirement Services, Inc., 271 Kan. 743, 747, 27 P.3d 1 (2001).

Under K.S.A. 2003 Supp. 60-1103(a)(l), a subcontractor’s mechanic’s hen must be filed within 3 months after the date supplies, material, or equipment was last furnished or labor was performed by the claimant. There is no dispute that Alpine was a subcontractor of R&R and that Alpine’s mechanic’s lien was filed on December 23, 1999.

The requirements for a mechanic’s lien must be strictly met. It is only after the lien has attached that the mechanic’s hen provisions are liberally construed. J. Walters Constr. Co. v. Greystone South Partnership, 15 Kan. App. 2d 689, 691, 817 P.2d 201 (1991). Mechanics’ hens are statutory and can only be acquired in the manner prescribed in the statute. Those claiming a mechanic’s lien have the burden of bringing themselves clearly within the provisions of the statute. Security Benefit Life Ins. Corp. v. Fleming Companies, Inc., 21 Kan. App. 2d 833, 838, 908 P.2d 1315 (1995), rev. denied 259 Kan. 928 (1996).

The test for determining timeliness of a mechanic’s hen is whether the final work was necessary under the terms of the original contract to complete the job and to comply with the requirements of the contract. Stickney v. Murdock Steel & Engineering, Inc., 212 Kan. 653, 656, 512 P.2d 339 (1973).

A determination of whether labor and material were furnished within the statutory period, but after the contract had been substantially completed, constitutes a question of fact. Mere delay in completing a contract does not invalidate a lien where there is no bad faith or unnecessary delay. Where the contractor has not completed the work under the contract, the building cannot be considered as having been completed as to the contractor or any subcontractor. 53 Am. Jur. 2d, Mechanics’ Liens § 201, p. 241.

When a building is substantially complete and is accepted by the owner, the contractor cannot thereafter perform some omitted part of the contract and thereby extend the period for filing the Hen. For the purpose of complying with a statutory deadline for filing a *494 lien, work includes remedial work if done pursuant to the original contract. 53 Am. Jur. 2d, Mechanics’ Liens § 201, p. 242.

Tying in power to the monument sign

We hasten to note that our inquiry on this matter is made more difficult by the fact that even though the agreement between R&R and Alpine included in the record on appeal was a standard printed agreement between contractor and subcontractor, the specific items of work to be performed under the contract were apparently set out on drawings that are not included in the record on appeal. An appellant has the duty to designate a record sufficient to establish the claimed error. Without an adequate record, the claim of alleged error fails. Unrau, 271 Kan. at 777.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tarlton v. MILLER'S OF CLAFLIN, INC.
227 P.3d 23 (Court of Appeals of Kansas, 2010)
National Restoration Co. v. Merit General Contractors, Inc.
208 P.3d 755 (Court of Appeals of Kansas, 2009)
Alliance Steel, Inc. v. Piland
187 P.3d 111 (Court of Appeals of Kansas, 2008)
Tradesmen International, Inc. v. Wal-Mart Real Estate Business Trust
129 P.3d 102 (Court of Appeals of Kansas, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
85 P.3d 205, 32 Kan. App. 2d 490, 2004 Kan. App. LEXIS 189, Counsel Stack Legal Research, https://law.counselstack.com/opinion/creme-de-la-creme-kansas-inc-v-rr-international-inc-kanctapp-2004.