Wahlcometroflex, Inc. v. Westar Energy, Inc.

773 F.3d 223, 85 U.C.C. Rep. Serv. 2d (West) 312, 2014 U.S. App. LEXIS 22581, 2014 WL 6790720
CourtCourt of Appeals for the Tenth Circuit
DecidedDecember 2, 2014
Docket13-3268
StatusPublished
Cited by3 cases

This text of 773 F.3d 223 (Wahlcometroflex, Inc. v. Westar Energy, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wahlcometroflex, Inc. v. Westar Energy, Inc., 773 F.3d 223, 85 U.C.C. Rep. Serv. 2d (West) 312, 2014 U.S. App. LEXIS 22581, 2014 WL 6790720 (10th Cir. 2014).

Opinions

KELLY, Circuit Judge.

This case involves a dispute over the meaning and application of a liquidated damages provision under Kansas law. The district court held that Defendant Westar Energy, Inc. (Westar) did not need to establish that Plaintiff Wahlcometroflex Inc.’s (Wahlco) late delivery of equipment actually delayed Westar’s production schedule in order to recover contractual liquidated damages. Wahlcometroflex, Inc. v. Westar Energy, Inc., No. 11-4017-EFM, 2013 WL 5774846 (D.Kan. Oct. 25, 2013). We have jurisdiction over Wahlco’s appeal under 28 U.S.C. § 1291, and we affirm.

Background

Westar is an electric company based in Topeka, Kansas that owns several sources of electricity, including the Jeffrey Energy Center (JEC). The JEC is a coal-fired power plant composed of three units: Unit 1, Unit 2, and Unit 3. In 2005, Westar began a project to upgrade the JEC’s existing flue gas desulfurization (FGD) system.

Wahlco is a Delaware corporation that designs and manufactures a number of products including FGD dampers. On December 22, 2006, Westar and Wahlco entered into a contract under which Wahlco agreed to manufacture and deliver dampers (Equipment) to Westar for Units 1, 2, and 3. The total contract price was $6,229,185.50. The contract provided that the Equipment was to be delivered by the “Latest Allowable Date[s]”: August 29, 2007 for Unit 1; July 29, 2008 for Unit 2; and March 16, 2008 for Unit 3.

Article 2 of the contract addressed liquidated damages in the event Wahlco did not make timely delivery. In an introductory paragraph, the agreement provided:

[Westar] and [Wahlco] recognize that schedule of delivery of documents and Equipment and Material is critical to this Contract and that [Westar] will suffer financial loss if such Work is not completed within the period of time specified. [Wahlco] shall pay [Westar] in accordance with the following paragraphs for each day of schedule delay.

App. 272. The following paragraphs explain specifically: “In the event [Wahlco] has not delivered each piece of Equipment and Material ... by the latest allowable delivery date ... [Wahlco] shall pay [Westar] one and one half percent (1.5%) of the total Contract Price per week for every week beyond the latest allowable delivery date.” Id. The total liquidated damages for late delivery of Equipment were “not [to] exceed ten percent of the total Contract Price.” Id.

Further, the agreement stated that “time is of the essence” and that Westar “will sustain damage if [Wahlco] fails to ... complete Equipment and Material deliveries within the dates specified.” Id. at 271. It further provided that the liquidated damages were “not penalties” and that “damages are difficult or impossible to determine, otherwise obtaining an adequate remedy is inconvenient and the liquidated damages constitute a reasonable [226]*226approximation of the harm or loss to [Westar].” id

Wahlco completed delivery of the equipment for Unit 1 on November 15, 2007, two-and-a-half months after the “latest allowable date” for delivery. It delivered the equipment for Unit 2 on October 3, 2008, two months late. And, it delivered the equipment for Unit 3 on August 1, 2008, over four months late. Id at 288. Because of these late deliveries, Westar withheld $367,511.28 of the contract price pursuant to the liquidated damages provision.

On February 11, 2011, Wahlco filed suit in Kansas federal district court to recover this amount. Westar answered and counterclaimed seeking a declaratory judgment that it was entitled to retain or recover liquidated damages totaling $622,918.55 (Count I) and bringing a breach of contract claim for the same amount (Count II).

The district court ordered discovery to be conducted in two phases. Phase 1 permitted limited discovery on the legal issue of Count I of Westar’s counterclaim and directed that, following discovery, both parties were to submit cross-motions for summary judgment as to that claim. No discovery was conducted on the issue whether Wahlco’s late delivery actually delayed Westar’s project.

The parties filed cross-motions for summary judgment on Count I of Westar’s counterclaim addressing whether Westar was required to prove actual delay to its project schedule to recover liquidated damages. The district court granted Westar’s motion for partial summary judgment, holding that Westar did not need to establish delay to recover liquidated damages. Wahlcometroflex Inc. v. Westar Energy, Inc., No. 11-4017-EFM/JPO, 2012 WL 2366693 (D.Kan. June 21, 2012). The court explained that the contract unambiguously required Wahlco to pay liquidated damages in the event of late delivery regardless of delay to the project. Id at *3. It further explained that, under Carrothers Construction Co. v. City of South Hutchinson, 288 Kan. 743, 207 P.3d 231 (2009), the liquidated damages clause was valid — not an unenforceable penalty — because it was reasonable in light of the anticipated damages at the time the contract was signed. Id at *4. Under Kansas law, the court explained, courts do not inquire as to actual damages with the “benefit of hindsight.” Id Thereafter, the district court granted Westar’s motion for summary judgment, rejected Wahlco’s invitation to reconsider its previous ruling and entered final judgment in favor of Westar. Wahlco then appealed.

Discussion

We review the district court’s grant of summary judgment de novo. Mumby v. Pure Energy Sens. (USA), Inc., 636 F.3d 1266, 1269 (10th Cir.2011). Summary judgment is appropriate where a movant establishes “there is no genuine dispute as to any material fact” and that “the movant is entitled to judgment as a matter of law.” Fed.R.Civ.P. 56(a). We view the evidence, and make all reasonable inferences therefrom, in the light most favorable to the non-moving party. LifeWise Master Funding v. Telebank, 374 F.3d 917, 927 (10th Cir.2004).

Wahlco argues that summary judgment was inappropriate for three reasons. First, it contends that its contract with Westar required a showing of project delay to trigger the liquidated damages provision. Aplt. Br. 9. Second, it contends that under Kansas law, Westar must establish that Wahlco’s breach of contract caused the event for which liquidated damages were designed to compensate — i.e., delay to Westar's project schedule. Id. at 12-17. [227]*227Finally, Wahlco argues the liquidated damages provision should be construed to require a showing of delay; otherwise, it amounts to an unenforceable penalty. Id. at 17-23. We address each argument in turn.

A. Does the Contract Require Project Delay for Liquidated Damages ?

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mera v. Barr
District of Columbia, 2024
Avant v. Doke
E.D. Oklahoma, 2023

Cite This Page — Counsel Stack

Bluebook (online)
773 F.3d 223, 85 U.C.C. Rep. Serv. 2d (West) 312, 2014 U.S. App. LEXIS 22581, 2014 WL 6790720, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wahlcometroflex-inc-v-westar-energy-inc-ca10-2014.