Ericksen v. Edmonds School District No. 15

125 P.2d 275, 13 Wash. 2d 398
CourtWashington Supreme Court
DecidedApril 30, 1942
DocketNo. 28579.
StatusPublished
Cited by30 cases

This text of 125 P.2d 275 (Ericksen v. Edmonds School District No. 15) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ericksen v. Edmonds School District No. 15, 125 P.2d 275, 13 Wash. 2d 398 (Wash. 1942).

Opinion

Steinert, J.

Plaintiff, a general contractor, brought suit against defendant, a school district, to recover damages alleged to have been sustained by him by reason of defendant’s breach of a contract under which plaintiff had been authorized by defendant to construct for it certain additions to its high school building. At the conclusion of plaintiff’s evidence, the court, on motion of defendant, dismissed the action with prejudice and entered judgment accordingly. Plaintiff appealed.

In the latter part of October, 1938, the respondent school district advertised for bids for the construction of certain additions to its high school building located in Edmonds, Washington. Appellant was the successful bidder, and on November 9, 1938, he entered into a written contract with respondent for the performance of such work. By express provision, the contract included: (1) the advertisement for bids, (2) a document entitled “Information For Bidders,” (3) the accepted proposal, (4) an agreement with a schedule of prices attached, (5) documents setting forth general and special conditions, (6) the specifications, and (7) the plans. We will have occasion a little later to refer in some detail to various portions of some of these documents, but for the present it is sufficient to say that by the terms of the contract appellant agreed to con *400 struct the school building additions, in accordance with the plans and specifications and such modifications thereof as should become necessary, for the sum of $177,527, increased or decreased proportionately by any modifications required. He further agreed to complete the construction within two hundred ninety-five consecutive calendar days from the date on which he should receive a start order from the architect, and to allow the owner by way of liquidated damages the sum of ten dollars for each calendar day thereafter that the work should remain uncompleted.

Immediately following the signing of the contract, appellant received from the architect a start order authorizing him to commence the work on the following day, November 10, 1938. Appellant was thus obligated to complete the work on or before August 31, 1939. -The work was not completed, however, until November 10, 1939, seventy-one days beyond the agreed time.

The building, as constructed, was finally accepted by respondent on January 5, 1940, and appellant was thereupon paid the balance of the amount owing him under the terms of the contract, less the sum of seven hundred ten dollars which respondent retained as liquidated damages for the excess period of seventy-one days required for the completion of the work. Prior to this settlement, however, appellant had claimed damages in the sum of $40,090.24, alleged to have been caused by respondent’s acts hereinafter more specifically related. Respondent rejected the claim and stood upon the terms of the contract. Appellant thereupon commenced this action to recover the above amount, on the theory that the contract had been breached by respondent. Later, by trial amendment, appellant sought also to recover the retained amount of seven hundred ten dollars.

*401 The general ground upon which appellant bases his appeal is that during the whole period of the construction respondent, through its architect who had prepared the plans and specifications and who was in charge of the building operation, “slowed down and retarded the reasonable progress and prompt performance of the work by appellant in its proper order and sequence.” The specific claim now made by appellant is that respondent, through its architect, breached the contract in the following respects:

“1. The plans furnished by respondent were erroneous and incomplete as to necessary dimensions and details, which were not timely corrected or supplied by respondent;
“2. The plans were also erroneous and incomplete as to essential starting points for the work, and the work, until they were corrected and supplied, could not be properly commenced, but respondent ordered and required appellant to commence and proceed with the work while the plans were in such condition;
“3. Respondent required appellant to employ too many workmen, more than could be used to advantage on the work, and to work all parts of the building at the same time; and
“4. Respondent interfered with appellant’s workmen by directly taking up matters with them and giving them orders, contrary to good building practice.”

As an additional ground, it is contended that respondent’s acts were unreasonable, arbitrary, and capricious.

Appellant filed in the cause a bill of particulars in which he set forth in detail the manner in which his work had been “hindered, impeded, retarded and obstructed,” reciting over three hundred instances of alleged errors and omissions in the architect’s plans and specifying the extent to which he had been required to employ additional workmen. Owing to the fact that this action was dismissed by the trial court at the conclusion of appellant’s case, we have before *402 us only the evidence which he adduced. The testimony covers almost twelve hundred pages and substantiates in great degree appellant’s claims as to the existence of errors and omissions in the plans. The record includes expert testimony to the effect that the time taken by respondent’s architect in supplying the needed corrections was unreasonable, arbitrary, and capricious.

At this point we advert to the contract, which, as stated before, is made up of a series of enumerated documents. The “Information For Bidders” contained this provision:

“Interpretation of Proposed Contract Documents —If any person contemplating submitting a bid for the proposed contract is in doubt as to the true meaning of any part of the plans, specifications, or other proposed contract documents, he may submit to the Architect a written request for an interpretation thereof. The person submitting the request will be responsible for its prompt delivery. Any interpretation of the proposed documents will be made only by Addendum duly issued and a copy of such Addendum will be mailed or delivered to each person receiving a set of such documents. The Owner will not be responsible for any other explanations or interpretations of the proposed documents.”

The “Proposal” submitted by the appellant contained these recitals:

“That he [appellant] has carefully examined the Contract Documents relating to the work bid on herein and now on file at the office of William Mallis, Architect, Seattle, Washington:
“That he has personally inspected the actual location of the work and all other local conditions affecting it:
“That he submits the proposal subject to the terms and conditions of the above-mentioned Contract Documents: and
*403 “That he has satisfied himself as to the quantities and conditions, and understands that in signing this proposal he waives all right to plead any misunderstanding regarding the same.
“He proposes and agrees:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
E.D. Washington, 2026
King County, V. Walsh Construction Company Ii, Llc.
Court of Appeals of Washington, 2023
Lake Hills Invs., LLC v. Rushforth Constr. Co., Inc.
494 P.3d 410 (Washington Supreme Court, 2021)
United States v. Associated Indemnity Company
969 F.2d 83 (Fifth Circuit, 1992)
Ceco Corp. v. Carson Concrete Corp.
691 F. Supp. 850 (E.D. Pennsylvania, 1988)
Bates & Rogers Construction Corp. v. Greeley & Hansen
486 N.E.2d 902 (Illinois Supreme Court, 1985)
Bates & Rogers Construction Corp. v. North Shore Sanitary District
414 N.E.2d 1274 (Appellate Court of Illinois, 1981)
Weston v. New Bethel Missionary Baptist Church
598 P.2d 411 (Court of Appeals of Washington, 1979)
Nelse Mortensen & Co. v. Group Health Cooperative
566 P.2d 560 (Court of Appeals of Washington, 1977)
City of Seattle v. Dyad Construction, Inc.
565 P.2d 423 (Court of Appeals of Washington, 1977)
S. L. Rowland Construction Co. v. Beall Pipe
540 P.2d 912 (Court of Appeals of Washington, 1975)
Franklin Contracting Co. v. State
338 A.2d 875 (New Jersey Superior Court App Division, 1975)
Siefford v. Housing Auth. of City of Humboldt
223 N.W.2d 816 (Nebraska Supreme Court, 1974)
V. C. Edwards Contracting Co. v. Port of Tacoma
514 P.2d 1381 (Washington Supreme Court, 1973)
Tyee Construction Co. v. Pacific Northwest Bell Telephone Co.
472 P.2d 411 (Court of Appeals of Washington, 1970)
F. S. Jones Construction Co. v. Duncan Crane & Rigging, Inc.
468 P.2d 699 (Court of Appeals of Washington, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
125 P.2d 275, 13 Wash. 2d 398, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ericksen-v-edmonds-school-district-no-15-wash-1942.