Lake Hills Invs., LLC v. Rushforth Constr. Co., Inc.

494 P.3d 410
Washington Supreme Court·Decided September 2, 2021·No. 99119-7·Published·Cited by 7 cases

Opinion

FILE THIS OPINION WAS FILED FOR RECORD AT 8 A.M. ON

SEPTEMBER 2, 2021

IN CLERK’S OFFICE SUPREME COURT, STATE OF WASHINGTON SEPTEMBER 2, 2021 ERIN L. LENNON

SUPREME COURT CLERK

IN THE SUPREME COURT OF THE STATE OF WASHINGTON

LAKE HILLS INVESTMENTS, LLC, a )

Washington limited liability company, ) No. 99119-7 )

Respondent, )

)

v. ) En Banc )

RUSHFORTH CONSTRUCTION CO., INC. )

d/b/a AP RUSHFORTH, a Washington )

corporation; and ADOLFSON & PETERSON )

INC., a Minnesota corporation, )

)

Petitioners. ) Filed : September 2, 2021 _______________________________________ )

MADSEN, J.—Lake Hills Investments LLC sued AP Rushforth (AP) for breach of contract, alleging, among other things, that the work AP conducted on the Lake Hills Village project was defective. AP counterclaimed that Lake Hills underpaid them. At trial, an affirmative defense instruction (jury instruction 9) was given, stating that “AP has the burden to prove that Lake Hills provided the plans and specifications for an area of work at issue, that AP followed those plans and specifications, and that the [construction] defect resulted from defects in the plans or specifications. If you find from

your consideration of all the evidence that this affirmative defense has been proved for a particular area, then your verdict should be for AP as to that area.” 1 Clerk’s Papers (CP) at 348-49. Lake Hills Inv., LLC v. Rushforth Constr. Co., 14 Wn. App. 2d 617, 631, 472 P.3d 337 (2020).

The Court of Appeals held that this instruction understated AP’s burden of proof and allowed the jury to find that if any part of the construction defect resulted from Lake Hills’ plans and specifications, then the jury could find for AP. The court concluded that the error was not harmless, reversed, and remanded for a new trial. We reverse the Court of Appeals.

BACKGROUND

Lake Hills contracted with AP to construct Lake Hills Village, a mixed-use property consisting of multiple buildings, including a King County library branch, two retail-office-residential buildings, three commercial buildings, some townhouses, an elevator tower, and a pedestrian bridge.

The project was built in phases. Phase 1 involved the library and an office building (building A). Phase 2C called for part of an underground garage, which included a ground concrete slab, a concrete topping slab on the parking garage for the aboveground parking lot, and the foundation for the two mixed-use buildings and a commercial building (buildings B, C, and D, respectively). Phase 3 consisted of the physical structures for buildings B, C, and D. Phase 4 involved townhouses. Under phase 5A, the elevator tower, the pedestrian bridge, the rest of the underground parking

garage, and a retail space under building A were constructed. Phase 5B completed the construction plans with building F. AP was the general contractor for phases 2C, 3, 5A, and 5B.

Every phase of the project had its own substantial completion date and liquidated damages were assessed for any delays past the substantial completion date. All phases that AP was contracted to build (phases 2C, 3, 5A, and 5B) were delayed. In November 2014, Lake Hills sent a letter to AP notifying AP that because it was behind schedule and there was defective work on the site, such as excessive cracking in the concrete garage floor slab, AP was in breach of contract. AP asserted that the construction delays and defects stemmed from Lake Hills providing a defective “concept” rather than viable plans and specifications. Lake Hills filed suit against AP, alleging, among other claims, that AP had performed defective work in eight areas. 1 AP stopped working on Lake Hills Village and filed its own breach claim, alleging underpayment.

The trial lasted two months. Using a special verdict form, the jury returned a mixed verdict. On the question of whether AP had rendered defective work as to any area of work, the jury answered yes. It awarded damages in six of eight areas of claimed defects. The jury also found Lake Hills had breached the contract in several respects. 2

1 Lake Hills’ second breach of contract claim alleged that AP delayed the construction of each of the four phases of work and failed to substantially complete each phase in the time required by the contract. Its third breach of contract claim alleged that AP improperly stopped work before completing all the work required by contract, including corrections to unfinished work. These claims are not before this court. 1 CP at 344. 2 The jury also found that each phase of the project was completed past its substantial completion date and that Lake Hills was responsible for the majority of the days the project was delayed, that

The net judgment to AP was $9.2 million, including $5.8 million in attorney fees and costs.

The Court of Appeals reversed based on jury instruction 9, the affirmative defense of defective plans or specifications. The court held that jury instruction 9 misstated the law governing AP’s affirmative defense because a construction defect must result “solely” from the defective or insufficient plans or specifications. The court concluded the error in the affirmative defense instruction prejudiced Lake Hills. Relying on Kenney v. Abraham, 199 Wash. 167, 170, 90 P.2d 713 (1939), and other Washington cases, 3 the court reasoned that “a party must perform its duties and a failure to perform entitles the injured party to damages proximately caused by the breach” with limited exceptions. 4 Lake Hills, 14 Wn. App. 2d at 630. A defective plans affirmative defense, the court noted, can relieve a breaching general contractor of its liability if a contractor can prove an alternate proximate cause. The court noted that “AP’s affirmative defense theory was that a single cause, defective plans or specifications, injured Lake Hills. To be relieved of all liability for its breaches, AP had to prove Lake Hills’ defective designs ‘solely’ caused the plaintiff’s damages.” Id. at 631. The Court of Appeals acknowledged that “including ‘solely’ may not be the only way to clarify the precise burden of proof for a

AP was not responsible for stopping work, and that Lake Hills had breached the contract by underpaying AP. 1 CP at 371-77. 3 Md. Cas. Co. v. City of Seattle, 9 Wn.2d 666, 116 P.2d 280 (1941); White v. Mitchell, 123 Wash. 630, 634-35, 213 P. 10 (1923); Valley Constr. Co. v. Lake Hills Sewer Dist., 67 Wn.2d 910, 915-16, 410 P.2d 796 (1966). 4 MICHAEL T. CALLAHAN ET AL., CONSTRUCTION DISPUTES: REPRESENTING THE CONTRACTOR § 20.02 (4th ed. 2020).

defective plans affirmative defense.” Id. at 631 n.43. But, the court held that some modifier was required because otherwise any evidence of a defect in the plans and specifications could allow AP to avoid all liability for the affected project area even if AP’s negligence caused some of the damage.

AP appealed, and Lake Hills cross appealed. We granted review only on jury instruction 9. Multiple amici submitted briefing. 5 ANALYSIS

A. The Affirmative Defense The heart of this case is whether jury instruction 9 correctly stated the standard for the affirmative defense of defective plans and specifications.

An appellate court reviews a trial court’s decision to give a jury instruction “‘de novo if based [on] a matter of law, or for abuse of discretion if based [on] a matter of fact.’” Hendrickson v. Moses Lake Sch. Dist., 192 Wn.2d 269, 274, 428 P.3d 1197 (2018) (internal quotation marks omitted) (quoting Taylor v. Intuitive Surgical Inc., 187 Wn.2d 743, 767, 389 P.3d 517 (2017)). “‘Prejudice is presumed if the instruction contains a clear misstatement of law[. However,] prejudice must be demonstrated if the instruction is merely misleading.’” Paetsch v. Spokane Dermatology Clinic, PS, 182 Wn.2d 842, 849, 348 P.3d 389 (2015) (quoting Anfinson v. FedEx Ground Package Sys.,

Free access — add to your briefcase to read the full text and ask questions with AI

Lake Hills Invs., LLC v. Rushforth Constr. Co., Inc., 494 P.3d 410 (Wash. 2021).

494 P.3d 410 (Lake Hills Invs., LLC v. Rushforth Constr. Co., Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Verduzco v. King County
Washington Supreme Court, 2026
Krystina Carson, V. Matthew Ashbach, M.d. Et Ano
Court of Appeals of Washington, 2025
Zachary Gibson, V. Holly Lyon
Court of Appeals of Washington, 2025
Eric S. Behnke, V. At&t, Inc.
Court of Appeals of Washington, 2024
King County, V. Walsh Construction Company Ii, Llc.
Court of Appeals of Washington, 2023
David Duncan, V. Boeing Company
Court of Appeals of Washington, 2023
State of Washington v. Mark Reynolds Worth
Court of Appeals of Washington, 2021