King County, V. Walsh Construction Company Ii, Llc.

Court of Appeals of Washington·Decided July 3, 2023·No. 83787-7·Published

Opinion

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

KING COUNTY, No. 83787-7-I Respondent,

DIVISION ONE

v.

PUBLISHED OPINION

WALSH CONSTRUCTION COMPANY II, LLC, an Illinois limited liability company; and TRAVELERS CASUALTY AND SURETY COMPANY OF AMERICA, a foreign insurance corporation,

Appellants.

FELDMAN, J. — This appeal arises out of a public works contract that required Walsh Construction Company II to construct and install a conveyance pipeline for King County. After the pipeline broke, the County paid Walsh to repair it and then sued Walsh for those costs. Relevant here, the trial court dismissed with prejudice “[a]ny defense based on alleged defective design.” Because the trial court misinterpreted the pertinent provisions of the parties’ agreement and misapplied controlling precedent, we reverse and remand.

I.

In November 2013, the County solicited bids to construct the South Magnolia Combined Sewer Overflow Control Project. The purpose of the project

was to diverge and limit the discharge of overflow wastewater into Elliott Bay during significant storm events. After Walsh submitted the lowest bid, the County awarded Walsh a contract (hereinafter “the Contract”) for the construction of an underground pipeline to convey overflow wastewater toward a diversion structure and storage tank. Walsh signed the Contract on April 7, 2014.

The Contract includes a provision entitled “Correction of Work or Damaged Property,” which states as follows:

If material, equipment, workmanship, or Work proposed for, or incorporated into the Work, does not meet the Contract requirements or fails to perform satisfactorily, the County shall have the right to reject such Work by giving the Contractor written Notice that such Work is either defective or non-conforming.

1. The County, at its option, shall require the Contractor, within a designated time period as set forth by the County, to either a. Promptly repair, replace or correct all Work not performed in accordance with the Contract at no cost to the County; or

b. Provide a suitable corrective action plan at no cost to the County.

The Contract defines the term “Work,” listed above, to include “the labor, materials, equipment, supplies, services, other items, and requirements of the Contract necessary for the execution, completion and performance of all work within the Contract by the Contractor to the satisfaction of King County.”

Although Walsh agreed that it would repair, replace, or correct all Work not performed in accordance with the Contract at no cost to the County if the material, equipment, workmanship, or Work failed to perform satisfactorily, it was not responsible for the design of the pipeline. Addressing that issue, section 3.2 of the General Terms and Conditions states that the “Contractor will not be

required to provide professional services which constitute the practice of architecture and engineering except to the extent provided for in the technical specifications and drawings.”

Walsh began installing the pipeline in September 2014. On January 5, 2016, the County issued a Certificate of Substantial Completion. In September 2016, the County discovered that the pipeline was malfunctioning. Following investigation, the County determined the pipeline had fractured, allowing soil and other debris into the pipe. On February 8, 2017, the County notified Walsh that the break in the pipeline was preventing overflows from flowing through the pipeline to the new storage facility and that the “Work has been found not to conform to [sic] Contract.”

Having found that the Work did not conform to the Contract, the County directed Walsh to develop a corrective action plan and submit the plan to the County as soon as possible. Walsh responded, contrary to the County’s assertion, that “the root cause of the break is due to a design issue” and refused to repair the non-functioning pipeline unless the County paid it to do so. To expedite the repairs, the County agreed to advance funds to Walsh subject to mutual reservations of rights under which the County could seek reimbursement from Walsh. Walsh ultimately provided a corrective action plan and performed the work to replace the broken pipeline with a new pipeline. The County incurred costs in excess of $20 million to repair and replace the damaged pipeline.

In September 2020, the County sued Walsh alleging breach of contract and breach of warranty. The County alleged that the “Work failed to perform

satisfactorily due to the physical and other damage to the Project and to the Conveyance Pipe” and “Walsh breached the Construction Contract by not repairing, replacing or correcting the physically damaged Work that failed to perform satisfactorily at no cost to King County.” Walsh, in turn, denied liability and asserted as an affirmative defense (among other defenses) that the County’s “claims are limited or barred by the application of the Spearin doctrine.”

The U.S. Supreme Court recognized the Spearin doctrine in United States v. Spearin, 248 U.S. 132, 54 Ct.Cl. 187, 39 S. Ct. 59 (1918). Succinctly stated, the doctrine holds that where “‘[A] contractor is required to build in accordance with plans and specifications furnished by the owner, the [owner] impliedly guarantees that the plans are workable and sufficient.’” Lake Hills Investments, LLC v. Rushforth Construction Co., Inc. 198 Wn.2d 209, 218, 494 P.3d 410 (2021) (quoting Ericksen v. Edmonds School Dist. No. 15, 13 Wn.2d 398, 408, 125 P.2d 275 (1942)). The Spearin doctrine “has [since] been adopted in nearly all jurisdictions,” including Washington. Id. (internal quotation marks omitted).

The County filed a motion for summary judgment seeking (among other relief) dismissal of Walsh’s Spearin defense. The County asserted that any implied warranty of design adequacy was displaced by the Correction of Work or Damaged Property provision in the Contract. The trial court granted the County’s motion and dismissed with prejudice “[a]ny defense based on alleged defective design.” Walsh moved for reconsideration, which the trial court denied. The court subsequently granted Walsh’s motion to certify the summary judgment

ruling for discretionary review under RAP 2.3(b). This court granted Walsh’s motion for discretionary review.

II.

The question presented here is whether the Correction of Work or Damaged Property provision in the Contract (quoted above) displaces “[a]ny defense based on alleged defective design,” including Walsh’s Spearin defense, as the trial court ruled. Our Supreme Court squarely addressed a similar issue in Shopping Center Management Company v. Rupp, 54 Wn.2d 624, 343 P.2d 877 (1959) (hereinafter Rupp), which the County cites in support of its argument. The court there held that “in the absence of an express warranty, a contractor is not liable for the loss or damage resulting from the defective plans and specifications prepared by the other party to the contract.” Id. at 631. The court explained that where the language of an express warranty goes beyond warranting the work and also warrants that the materials and equipment installed by the contractor will “operate satisfactorily under the plans and specifications of the owner,” the contractor’s express warranty of satisfactory operation displaces the owner’s implied warranty of design adequacy. Id. at 632-33.

Free access — add to your briefcase to read the full text and ask questions with AI

King County, V. Walsh Construction Company Ii, Llc., (Wash. Ct. App. 2023).

King County, V. Walsh Construction Company Ii, Llc. (King County, V. Walsh Construction Company Ii, Llc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United States v. Spearin
248 U.S. 132 (Supreme Court, 1918)
Shopping Center Management Co. v. Rupp
343 P.2d 877 (Washington Supreme Court, 1959)
Nishikawa v. US EAGLE HIGH, LLC
158 P.3d 1265 (Court of Appeals of Washington, 2007)
Ericksen v. Edmonds School District No. 15
125 P.2d 275 (Washington Supreme Court, 1942)
Port of Seattle v. Puget Sound Sheet Metal Works
213 P. 467 (Washington Supreme Court, 1923)
Nishikawa v. U.S. Eagle High, LLC
138 Wash. App. 841 (Court of Appeals of Washington, 2007)
Grant County Port District No. 9 v. Washington Tire Corp.
349 P.3d 889 (Court of Appeals of Washington, 2015)
Lake Hills Invs., LLC v. Rushforth Constr. Co., Inc.
494 P.3d 410 (Washington Supreme Court, 2021)