Kenney v. Abraham

90 P.2d 713, 199 Wash. 167
CourtWashington Supreme Court
DecidedMay 19, 1939
DocketNo. 27338. Department Two.
StatusPublished
Cited by14 cases

This text of 90 P.2d 713 (Kenney v. Abraham) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kenney v. Abraham, 90 P.2d 713, 199 Wash. 167 (Wash. 1939).

Opinion

Millard, J.

Ivan H. Abraham entered into a written contract with A. L. Kenney to construct for the latter a one-story brick veneer cottage in Spokane according to certain plans and specifications prepared *168 by a firm of architects employed by Kenney. The plans and specifications required the contractor

“ . . . to lay out his work and be responsible for the same, and see that everything is done in a workmanlike manner, according to the best building practice.”

The building contractor was required by the specifications to

“. . . excavate as shown to be necessary by the drawings for the basement, for all areas, footings, etc. Care shall be taken to excavate to the exact depth required as in no case shall any footings start on filled ground.”

Kenney agreed with Abraham, at the time they entered into the contract for the construction of the house, to dispense with the supervisory services of an architect. The contractor discovered, when making the excavation for the foundation, that the lot on which the house was to be built was a filled lot. The contractor testified that, on making his discovery of the character of the soil, and before he laid the foundation of the house, he made telephonic request of the owner to call at the building site and look at the soil; that the foundation of the house was constructed sixteen inches higher than specified by the plans, which change was made pursuant to agreement with Kenney.

The concrete for the foundation was poured on filled ground, loose rock, pine needles, and decaying vegetable matter; and as a result the foundation of the house, shortly after Kenney moved into the building, settled to such an extent that the interior walls of the building were cracked open, and, under the evidence, the building was damaged to such an extent as to require the expenditure of approximately the original cost of construction to repair the same.

An action was instituted by Kenney against Abra *169 ham to recover damages for breach of the building contract. The cause was tried to the court, which found, among other things, that defendant breached the contract in that he did not excavate to the depth required by the drawings and specifications, or until solid earth was obtained on which the concrete walls should be constructed, but placed the foundation walls on surface fill composed of loose dirt, rotted leaves, pine needles, etc., and as a result the foundation walls of the building settled out of level after the foundations were poured. The trial court further found that the contractor failed to construct the building in compliance with the contract, which required the contractor to see that “everything is done in workmanlike manner, according to the best building practice.”

“The Court further finds that the defendants failed to construct said building in compliance with the contract, requiring defendants to see that ‘everything is done in workman-like manner according to the best building practice.’ That the best building practice does not permit foundation to rest on made or filled ground, and finds further that the specifications themselves expressly say: ‘ Care shall be taken to excavate to the exact depth required as in no case shall any footing start on filled ground.’ The Court finds that the foundation was started on filled ground and therefore contrary to this provision of the contract. The defendant, Ivan H. Abraham, himself testified that he discovered that the ground was filled and that he so informed the plaintiffs, owners, and told them that he would not go on with the work until the plaintiffs directed him to do so. This statement was denied in toto by the plaintiff and the Court finds that the defendant failed to establish this claim by the preponderance of the evidence.”

The court further found that the defects in the building as contracted by the contractor are so many and so serious that the contractor’s liability can only be measured by the difference in the value of the house *170 in its present condition and what the value of the house would have been if there had not been these defects; that Kenney owes the contractor on the contract, for the construction of the building, $939.50, which amount should be deducted from $3,472.35 (the damage sustained by Kenney by reason of the failure on the part of the contractor to build the house in accordance with the contract, plans and specifications), leaving a balance of $2,532.85, for which Kenney is entitled to judgment. Judgment was entered accordingly against Abraham and wife in favor of Kenney and wife. The defendants appealed.

Counsel for appellants contend that respondents furnished the plans, specifications, and a prospectus, which the contractor followed in building the house; therefore, the contractor cannot be held liable in damages for the defects occurring in the house due to the plans, specifications, and prospectus furnished by the owner. Among the many authorities cited by appellants in support of the foregoing is the following note preceding the authorities listed, under the subject of responsibility of construction contractor for defects or insufficiency of work attributable to plans and specifications furnished by the contractee, in 88 A. L. R. 798.

“The rule has become well settled, in practically every American jurisdiction in which the matter has been involved, that a construction contractor who has followed plans and/or specifications furnished by the contractee, his architect or engineer, and which have proved to be defective or insufficient, will not be responsible to the contractee for loss or damage which results — at least after the work is completed — solely from the defective or insufficient plans or specifications, in the absence of any negligence on the contractor’s part, or any express warranty by him as to their being sufficient or free from defects.” (Italics ours.)

*171 The weakness in the position of appellants is that the foundation of the house was not built in accordance with the plans and specifications. Had the plans been followed, the foundation walls would have been sixteen inches deeper down into the soil. Appellant contractor admitted that the foundation of the house as contracted was sixteen inches higher than specified in the plans. While he testified that the plans were changed under an oral agreement with the respondents, the latter denied that they had agreed to the change. The trial court’s memorandum opinion reads in part as follows:

“It is in evidence (and it rests in common sense as well) that the best building practice does not permit a foundation to rest on made or filled ground. The specifications themselves expressly say: ‘Care shall be taken to excavate to the exact depth required as in no case shall any footing start on filled groundDefendant contractor himself testified that he discovered that the ground was filled and says he so informed the plaintiff owner and said that he would not go on with the work until the plaintiff directed him to do so. This is denied in toto by the plaintiff and I must find that the defendant has failed to establish this claim by the preponderance of the evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lake Hills Invs., LLC v. Rushforth Constr. Co., Inc.
494 P.3d 410 (Washington Supreme Court, 2021)
Eastlake Construction Co. v. Hess
686 P.2d 465 (Washington Supreme Court, 1984)
Gadbois v. Leb-Co. Builders, Inc.
458 A.2d 555 (Superior Court of Pennsylvania, 1983)
Brougham v. Swarva
661 P.2d 138 (Court of Appeals of Washington, 1983)
Worthington v. Worthington
440 P.2d 478 (Washington Supreme Court, 1968)
Valley Construction Co. v. Lake Hills Sewer District
410 P.2d 796 (Washington Supreme Court, 1966)
Schmechel v. Ron Mitchell Corp.
406 P.2d 962 (Washington Supreme Court, 1965)
Odgers v. Held
362 P.2d 261 (Washington Supreme Court, 1961)
Hoye v. Century Builders, Inc.
329 P.2d 474 (Washington Supreme Court, 1958)
Forrester v. Craddock
317 P.2d 1077 (Washington Supreme Court, 1957)
Bernbaum v. Hodges
261 P.2d 968 (Washington Supreme Court, 1953)
Becwar v. Bear
246 P.2d 1110 (Washington Supreme Court, 1952)

Cite This Page — Counsel Stack

Bluebook (online)
90 P.2d 713, 199 Wash. 167, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kenney-v-abraham-wash-1939.