This text of 178 P. 823 (McConnell v. Gordon Construction Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McConnell v. Gordon Construction Co., 178 P. 823, 105 Wash. 659, 1919 Wash. LEXIS 622 (Wash. 1919).

Opinion

Mackintosh, J.

The respondent, Gordon Construction Company, at Seattle, on November 3, 1909, wrote to the appellant at Denver, Colorado, a letter offering to construct for him a building substantially a reproduction of one then situated at the Alaska-Yukon-Pacific Exposition, in Seattle. This letter contained the following:

“We will furnish drawings and specifications by Harry Weatherwax . . . and furnish all material and labor and construct for you the ‘Monitor and Merrimac’ building, as per Weatherwax’s plans . . . We will build in a substantial and workmanlike manner the ‘Monitor and Merrimac’ building, which will be a substantial reproduction of the ‘Monitor and Merrimac’ building on the ‘Pay Streak’, AY.-P. Exposition, with some additions and changes, as follows: ... ”

The offer contained in this letter was accepted by the appellant, and the respondent construction company proceeded with the construction of the building, having furnished a bond guaranteeing’ the faithful performance of the contract with the respondent insurance company as surety. The construction company completed the building and turned the same over to the appellant. Ten days later the building suddenly collapsed. The appellant reconstructed the building, and instituted this action to recover the cost of such reconstruction, and the damages resulting from the collapse.

The appellant’s complaint was based upon his allegation that the construction company had improperly [661]*661constructed the footings under the three columns supporting the two trusses which carried the principal weight of the structure; that, according to the plans and specifications, these footings should have had a hearing surface of twenty square feet; whereas, in fact, they were originally constructed with a bearing surface of only sixteen square feet and subsequently new concrete was added to make them of the required area, and the columns supporting the trusses were then placed directly over the union between the old and new concrete, which resulted in the breaking of the footings at the point of union. The construction company admitted the collapse of the building, and in a general denial denied the allegations of negligence; and, as an affirmative defense, alleged that the collapse was caused by the addition of two tons of weight upon the trusses by reason of changes of construction ordered by the appellant. This affirmative matter was denied in the reply.

The appellant’s testimony was taken by depositions, and several months were consumed in preparing the case for trial, and during this time and while the appellant’s testimony was being produced before the jury, the respondent construction company gave no intimation that any other issue than that especially raised by the pleadings was to be presented. The construction company, however, was allowed, when presenting its defense, to introduce evidence that the plans were inherently defective in that the trusses were insufficient, as designed, to carry the weight which, of necessity, they must bear. This testimony was introduced over the objection of the appellant that the construction company, having furnished the plans, was liable for any defects therein, and would be responsible for the collapse of the building if it were [662]*662occasioned by the inadequacy of such plans. Further objection was made to the introduction of this evidence upon the ground that it had not been affirmatively pleaded as a defense. The construction company was also allowed to introduce evidence showing an additional weight of seventeen tons to have been placed upon the trusses, this weight having been imposed by changes not contemplated by the plans but ordered during the construction of the work by the appellant. Objection was made to this testimony on the ground that the affirmative defense only claimed that an additional weight of two tons had been added. A verdict was returned against the appellant, and in favor of the respondent upon a counterclaim which had been interposed for extra work done.

The testimony introduced respecting the adequacy of the plans should have been excluded for two reasons; the first being that the contract between the parties having called for the furnishing of the plans by the respondent construction company, thereby that company vouched for the adequacy of the plans and cannot now raise any question thereto. Where either party to a building contract agrees to furnish, and does furnish, the plans for a building, he thereby guarantees their sufficiency for the purpose. Huetter v. Warehouse & Realty Co., 81 Wash. 331, 142 Pac. 675, L. R. A. 19150 671. The respondent offered the testimony upon the theory — which the trial court adopted—that the word “furnish,” as used in the contract, was so indefinite or ambiguous as to allow the production of parol testimony to explain it, and under this ruling the respondent construction company was allowed to show that the appellant was familiar with the plans at the time the contract was entered into; and that, as a matter of fact, instead of the respond[663]*663ent furnishing the plans, the appellant himself was furnishing them. The word used is an ordinary word of common use and has a well defined, easily understood meaning, and to allow parol testimony to explain it, would he to violate the fundamental rule in regard to the varying of the terms of a written contract. The court was in error in the admission of testimony in this respect and in submitting to the jury the question of the interpretation to he placed upon the contract in regard to the furnishing of the plans. The contract having stipulated for the plans to be furnished by the respondent construction company, it cannot now question the adequacy of such plans.

The second reason why this testimony was inadmissible is that assigned by the appellant in his objection' to it. The case had been at issue under the pleadings as framed by the parties for many months, both parties had attended "and taken depositions, and the trial had proceeded to the point where the respondents were about to introduce their testimony before the appellant was apprised of the fact that any defense other than that suggested in the affirmative defense was to be relied upon. If the defense of inadequacy of the plans had been otherwise admissible, it was of the same nature as the defense that the collapse of the building was occasioned by the additional weight imposed by reason of the appellant’s changes of construction. If these were matters which could not properly be raised by general denial, then each of them should have been pleaded as an affirmative defense. If, however, they were both issues presentable under the general denial, as is claimed by the respondents, then the fact that one of them was specially plead, and the presentation of the other was neither specially made in the pleadings nor in any [664]*664way called to the attention of the opposing party until the opportunity to guard against the defense had virtually passed and this had resulted in so embarrassing the appellant in the trial of his case, then the respondents, in good conscience, should not be permitted to pursue such a course of conduct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pickens v. Cunningham
22 Pa. D. & C.3d 40 (Mercer County Court of Common Pleas, 1981)
Rosell v. Silver Crest Enterprises
436 P.2d 915 (Court of Appeals of Arizona, 1968)
Hoye v. Century Builders, Inc.
329 P.2d 474 (Washington Supreme Court, 1958)
Baerveldt & Honig Construction Co. v. Szombathy
289 S.W.2d 116 (Supreme Court of Missouri, 1956)
Ericksen v. Edmonds School District No. 15
125 P.2d 275 (Washington Supreme Court, 1942)
Phifer v. Burton
251 P. 127 (Washington Supreme Court, 1926)
McConnell v. Gordon Construction Co.
233 P. 926 (Washington Supreme Court, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
178 P. 823, 105 Wash. 659, 1919 Wash. LEXIS 622, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcconnell-v-gordon-construction-co-wash-1919.