First Savings & Trust Co. v. Milwaukee County

148 N.W. 22, 158 Wis. 207, 1914 Wisc. LEXIS 290
Wisconsin Supreme Court·Decided October 6, 1914·Published·Cited by 15 cases

Opinions

The following opinion was filed June 17, 1914:

RaeNes, J.

The plaintiff’s appeal raises the question whether certain findings of "fact adverse to it are against the clear preponderance of the evidence.

The defendant’s appeal raises a like question. Defendant also contends that many of the findings of fact and conclusions of law were based on an erroneous conception of the law and on an erroneous construction of the contract involved, and that the conclusions of law are not supported by the facts found, conceding that there is sufficient support in the evidence, for the findings of fact made. Logically the legal [225]*225propositions should be first disposed of, because if they are settled so as to eliminate any of the findings of fact or conclusions of law we are not concerned with the quantum of evidence to support these findings that is contained in the record. The legal questions raised in fact affect the integrity of many of the findings of fact and most of the conclusions of law.

Construction of the viaduct statute.

The most comprehensive claim made is that under ch. 444, Laws of 1903 (the viaduct statute), and particularly sec. 5 thereof, it was the duty of the county to have prepared complete plans and specifications and to advertise for bids and let the contract to the lowest bidder, and that after bids were received and the lowest bid accepted, neither the engineer in charge, the committee that represented the county board, nor the board itself, could make any deviation from or addition to the plans or specifications, but the viaduct would have to be built in accordance therewith.

It is argued inter alia that when the county let the contract to the lowest bidder, to be performed in accordance with the plans and specifications, it had exhausted its power under the statute, and that to hold otherwise would enable the county to evade the provisions of the law requiring the contract to be let to the lowest bidder. The following cases, among others, are relied on: Kneeland v. Milwaukee, 18 Wis. 411, 417; Kneeland v. Furlong, 20 Wis. 437; Ricketson v. Milwaukee, 105 Wis. 591, 598, 81 N. W. 864; State ex rel. O’Donnell v. Benzenberg, 108 Wis. 435, 84 N. W. 858; Board of Comm’rs v. Bunting, 111 Ind. 143, 12 N. E. 151, 152. 2 Dillon, Mun. Corp. (5th ed.) § 791, and 3 McQuillin, Mun. Corp. § 1206, are also cited.

The statute, after requiring that plans and specifications shall be prepared and the contract let to the lowest bidder, provides that the county board shall “enter upon the con[226]*226struction of sucli viaduct, bridge and approaches in conformity thereto.” It is this provision wbicb it is insisted precludes the county from making any subsequent changes. '

There is some force in the contention, but it cannot prevail. Undoubtedly it was the duty of the county to cause to be prepared substantially complete plans and specifications before advertising for bids. It should also exercise good faith in making changes and could not make them simply for the purpose of favoring a contractor or of evading the statute. But neither our architects nor engineers have arrived at that stage of perfection where they can design great structures and unerringly provide for every detail' of their construction. They overlook things, and occasionally they make mistakes* where they do not overlook. Sometimes these mistakes'may be serious. Then, too, we are moving all the time whether we are progressing or not. New and advanced ideas even in the matter of concrete construction might well be worked out during the life of the contract sued on. If the plans proved to be inefficient in some important detail, it would be serious indeed if the county were required to go on spending its money on what might prove to be a worthless structure, when the waste and loss could have been avoided at a moderate cost, or possibly at no cost at all. We cannot think the legislature ever intended to create such an intolerable situation. The statute in terms does not prohibit changes being made. It merely requires the county to “enter upon the construction” of the viaduct in conformity to the plans and specifications adopted. There is no practical difference between the contention here made by the defendant and that made by the plaintiff in Mueller v. Eau Claire Co. 108 Wis. 304, 308, 84 N. W. 430, where the court held that the right existed to make changes under a statute similar to the one under consideration. More attention has been paid to this question perhaps than it deserves, but if held good it would defeat most of the claims made by the plaintiff, and it was argued at the [227]*227bar and in the brief at considerable length and, we have no doubt, in entire good faith, by the attorney for the county.

Power of the county board to delegate the broad powers which it attempted to delegate to its committee.

As will be seen by a reference to the resolution set forth in the statement of facts, the county board attempted at least to confer on the committee all powers which it might itself exercise over questions arising out of the viaduct contract during construction. The committee was given carte blanche and there was little or no interference with it by the board.

The defendant contends (1) that the resolution, having been adopted over eight months -before the contract was signed, cannot be construed as giving the committee power to do the things which the board reserved the right to do in the contract, such as the right to modify the contract as provided in sec. 8 thereof. (2) The power attempted to be delegated rested in the county board, under sec. 652, Stats., if it existed, and the board could only empower the committee to report to it under sec. 668, Stats. (3) The powers attempted to be delegated could not be conferred, because they were not merely ministerial, but called for the exercise of judgment and discretion and were in fact legislative. Sec. 668 provides :

“Any county board may, by resolution designating the purposes and prescribing the duties thereof and manner of reporting, authorize their chairman to appoint before the first day of November in any year -a committee or committees from the members of the county board elect, and the committees so appointed shall perform the duties and report as prescribed in such resolution.”

This section does not restrict the power of the committees appointed to making investigations and reporting recommendations. It does not undertake to define what power is conferred on committees. Whenever they are authorized to do [228]*228an act they must very properly report to the board what they have done.

Sec. 652 provides that the powers of a county as a body corporate can only be exercised by the county board or in pursuance of a resolution or ordinance by them adopted. This section contemplates that some powers of a county board may be exercised by a committee pursuant to resolution. No attempt is made to define the extent of this power of delegation.

It would seem particularly appropriate that the board should give broad powers to its committee, if it was authorized by law to do so. The contract was a large and important one. It extended over a very considerable length of time. Disputes and differences were almost constantly arising between the engineer and the contractor.

Free access — add to your briefcase to read the full text and ask questions with AI

First Savings & Trust Co. v. Milwaukee County, 148 N.W. 22, 158 Wis. 207, 1914 Wisc. LEXIS 290 (Wis. 1914).

148 N.W. 22 (First Savings & Trust Co. v. Milwaukee County) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

John E. Gregory & Son, Inc. v. A. Guenther & Sons Co.
432 N.W.2d 584 (Wisconsin Supreme Court, 1988)
Opinion No. Oag 44-85, (1985)
74 Op. Att'y Gen. 227 (Wisconsin Attorney General Reports, 1985)
Opinion No. Oag 55-77, (1977)
66 Op. Att'y Gen. 198 (Wisconsin Attorney General Reports, 1977)
(1972)
61 Op. Att'y Gen. 214 (Wisconsin Attorney General Reports, 1972)
Cunningham Brothers, Inc. v. City of Waterloo
117 N.W.2d 46 (Supreme Court of Iowa, 1962)
Home Owners Construction Co. v. Borough of Glen Rock
169 A.2d 129 (Supreme Court of New Jersey, 1961)
Thomsen-Abbott Construction Co. v. City of Wausau
100 N.W.2d 921 (Wisconsin Supreme Court, 1960)
Ericksen v. Edmonds School District No. 15
125 P.2d 275 (Washington Supreme Court, 1942)
First Wisconsin National Bank v. Town of Catawba
197 N.W. 1013 (Wisconsin Supreme Court, 1924)
Park v. City of Milwaukee
192 N.W. 1012 (Wisconsin Supreme Court, 1923)
Nelson v. City of Eau Claire
185 N.W. 168 (Wisconsin Supreme Court, 1921)
Tomlinson v. Ashland County
173 N.W. 300 (Wisconsin Supreme Court, 1919)
People ex rel. McMahon v. Davis
209 Ill. App. 117 (Appellate Court of Illinois, 1917)
Sterling Engineering & Construction Co. v. Berg
152 N.W. 851 (Wisconsin Supreme Court, 1915)