Scoccolo Construction, Inc. v. City of Renton

102 Wash. App. 611
CourtCourt of Appeals of Washington
DecidedSeptember 18, 2000
DocketNo. 46284-9-I
StatusPublished
Cited by6 cases

This text of 102 Wash. App. 611 (Scoccolo Construction, Inc. v. City of Renton) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Scoccolo Construction, Inc. v. City of Renton, 102 Wash. App. 611 (Wash. Ct. App. 2000).

Opinion

Baker, J.

— Scoccolo Construction, Inc. (Scoccolo) appeals an adverse summary judgment order in its suit against the City of Renton (Renton) to recover damages due to delays in the completion of a public works contract. A clause in the construction contract provided that Scoccolo, as the contractor, would bear the risk of any delays caused by the actions of any utility company. Scoccolo’s claim is based on delays incurred in the relocation of utilities necessary for completion of its work. Scoccolo contends that summary judgment based upon the contract clause was inappropriate because Renton is liable for damages caused by its own actions that contributed to delays related to the relocation of utilities. Scoccolo further contends that RCW 4.24.360 renders the clause unenforceable because it “purports to waive, release, or extinguish the rights of a contractor, subcontractor, or supplier to damages or an equitable adjustment arising out of unreasonable delay in performance which delay is caused by the acts or omissions of the contractee or persons acting for the contractee.” On cross appeal, Renton contends that the trial court abused its discretion in awarding it only $10,000 in attorney fees under the contract when it requested attorney fees and costs totaling $216,414.81. We reverse the summary judgment order because the contractual clause does not insulate Renton from liability for its own actions, and consequently vacate the attorney fees award.

I

Scoccolo Construction, Inc. was awarded a contract with the City of Renton to widen Park Avenue, a main city street. The contract provided that the relocation of utilities would be effected by the relevant utility companies, not Scoccolo, although Scoccolo was required to coordinate relocation [613]*613efforts with the utility companies. The contract further provided that:

No additional compensation will be made to [Scoccolo] for reason of delay caused by actions of any utility company and the Contractor shall consider such costs to be incidental to the other items of the contract.

A franchise agreement between Renton and Puget Sound Power & Light Co. (Puget) gave Renton the authority to compel Puget to relocate utilities at Puget’s cost and expense. Because the project included replacement of the existing overhead power distribution system with an underground power distribution system, Renton contracted with Puget to perform the relocation in exchange for Renton’s payment of the undergrounding cost. That contract did not supersede the franchise agreement. Scoccolo claims that Puget did not complete its obligations under the contract with Renton in a timely manner, which delayed Scoccolo’s work on Park Avenue.

Scoccolo filed suit against Renton to recover damages due to delays in the contract, and Renton moved for partial summary judgment to “dismiss all of plaintiff’s claims based upon delays caused by utilities” in light of the contractual language which provided that Scoccolo would not receive additional compensation due to delays caused by the actions of any utility company. Renton’s motion raised only two arguments: (1) that the contract specifically places the burden and risk of utility-caused delays on Scoccolo; and (2) that courts regularly enforce contract clauses such as the one at issue here. At oral argument the parties agreed that the relief Renton sought, as well as the trial court’s understanding of that request, encompasses all claims where the actions of a utility company contributed to the delay in any manner.

Scoccolo argued, inter alia, that summary judgment was inappropriate because: (1) Renton knew that Puget was delaying Scoccolo’s work, but did not exercise its right to direct Puget to complete the work or to have others com[614]*614píete the work if Puget failed to perform; (2) Renton breached its implied duty to cooperate with Scoccolo and facilitate the completion of the project; and (3) the contractual language precluding additional compensation due to delays caused by the actions of utility companies is invalid under RCW 4.24.360, which states:

Any clause in a construction contract, as defined in RCW 4.24.370,[1] which purports to waive, release, or extinguish the rights of a contractor, subcontractor, or supplier to damages or an equitable adjustment arising out of unreasonable delay in performance which delay is caused by the acts or omissions of the contractee or persons acting for the contractee is against public policy and is void and unenforceable.

Renton’s reply memorandum did not address Scoccolo’s first or second arguments but did address interpretation of RCW 4.24.360, contending that the statutory language “persons acting for the contractee” implicated only a contractee’s agents, and that there was no proof of an agency relationship between Renton and the utility companies. The trial court granted Renton’s motion, ordering that “plaintiff’s delay claims based on delays caused by utilities are dismissed with prejudice.” The parties then agreed to dismiss all remaining claims in order to obtain appellate review of the partial summary judgment order, and Renton was awarded attorney fees in the amount of $10,000. Scoccolo appeals the trial court’s summary judgment order, while Renton cross-appeals the trial court’s award of attorney fees in light of the City’s request for attorney fees and costs totaling $216,414.81.

II

Contracting parties may ordinarily allocate risks as they [615]*615see fit.2 The default rule in Washington with respect to the clause at issue here is expressed in the companion cases of Nelse Mortensen & Co. v. Group Health Cooperative of Puget Sound,3 and Christiansen Brothers v. State,4 which were unanimously decided on the same day by our State Supreme Court.

In Mortensen, contractors brought suit against a hospital owner for damages caused by delays in the remodeling of and adding to the hospital, where the delays were caused by the hospital’s owner and architect.5 The contract provided that no damages could be recovered for delay caused by the owner.6 The court in Mortensen held that where delays in the completion of a construction contract were within the contemplation of the parties, then no recovery for those delays is allowed if the contract forecloses such a remedy.7 The court cited with approval this court’s holding that:

if owner-caused delay in construction was of a nature contemplated by the parties and specific provisions of their contract provide a remedy, or the contract otherwise supplies a means of compensation for such delay, then the delay cannot be deemed unreasonable to the extent the contract terms should be abandoned in favor of quantum meruit recovery.[8]

In Christiansen,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SCOCCOLO CONST. v. City of Renton
145 P.3d 371 (Washington Supreme Court, 2006)
Scoccolo Construction, Inc. v. City of Renton
158 Wash. 2d 506 (Washington Supreme Court, 2006)
Scoccolo Const., Inc. v. City of Renton
103 P.3d 1249 (Court of Appeals of Washington, 2005)
Scoccolo Construction, Inc. v. City of Renton
125 Wash. App. 150 (Court of Appeals of Washington, 2005)
Mike M. Johnson, Inc. v. Spokane County
150 Wash. 2d 375 (Washington Supreme Court, 2003)
Mike M. Johnson, Inc. v. County of Spokane
78 P.3d 161 (Washington Supreme Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
102 Wash. App. 611, Counsel Stack Legal Research, https://law.counselstack.com/opinion/scoccolo-construction-inc-v-city-of-renton-washctapp-2000.