Scoccolo Const., Inc. v. City of Renton

103 P.3d 1249
CourtCourt of Appeals of Washington
DecidedJanuary 10, 2005
Docket51730-9-I
StatusPublished
Cited by6 cases

This text of 103 P.3d 1249 (Scoccolo Const., Inc. v. City of Renton) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Scoccolo Const., Inc. v. City of Renton, 103 P.3d 1249 (Wash. Ct. App. 2005).

Opinion

103 P.3d 1249 (2005)

SCOCCOLO CONSTRUCTION, INC., a Washington corporation, for the use and benefit of CURB ONE, INC., a Washington corporation, Respondent/Cross-Appellant,
v.
CITY OF RENTON, a municipal corporation, Appellant/ Cross-Respondent.

No. 51730-9-I.

Court of Appeals of Washington, Division One.

January 10, 2005.

John P. Mele, Roger Mykleburst, Ryan Swanson & Cleveland PLLC, Seattle, WA, Lawrence J. Warren, Warren Barber & Fontes PS, Renton, WA, for Appellant.

Jeffrey G. Poole, Scott A. Marks, Poole & Associates PC, Seattle, WA, for Respondent.

PUBLISHED IN PART

KENNEDY, J.

The City of Renton appeals the jury verdict and the trial court's order on prejudgment interest and attorney fees and costs in this contract dispute with Scoccolo Construction Company over damages for delays in the completion of a street widening project. Following this court's reversal of the trial court's earlier decision granting partial summary *1250 judgment to Renton,[1] the trial court ruled that because Renton had franchise agreements authorizing it to compel Puget Sound Power and Light and TCI Cable to relocate their utilities at their own expense during a street widening project such as this one, those franchisees were "persons acting for" Renton under RCW 4.24.360 as a matter of law. The trial court ruled, therefore, that a contract provision limiting Scoccolo's remedies for delays caused by utility companies was void. Renton argues, and we agree, that the trial court erred by ruling as a matter of law that the power and cable companies were "persons acting for" Renton within the meaning of RCW 4.24.360, by virtue of their franchise agreements with Renton.[2]

FACTS

Following a public bid process, the City of Renton awarded Scoccolo Construction Company, Inc., a contract to widen Park Avenue North, a main city street. The project involved removal and relocation of utility poles, lines, and related equipment by Puget Sound Power and Light, U.S. West Communications, and TCI Cable. The construction contract provided that Scoccolo would coordinate relocation efforts with the utilities, and included the following provision labeled TP 1-07.17: "No additional compensation will be made to the Contractor for reason of delay caused by actions of any utility company and the Contractor shall consider such costs to be incidental to the other items of the contract." Clerk's Papers at 164.

Renton had previously entered into a franchise agreement with Puget Sound Power giving Renton the authority to compel Puget to relocate utilities at Puget's cost and expense in public works projects such as the one here at issue. Renton also contracted with Puget Sound Power specifically for the Park Avenue North project to replace the existing overhead distribution power system with an underground system.

After the project was completed, Scoccolo filed suit against Renton claiming that the failure of Puget Sound Power, TCI Cable and U.S. West to complete their removal and relocation work in a timely manner delayed Scoccolo's work, and seeking money damages from Renton. Renton sought, and the trial court granted, partial summary judgment dismissing Scoccolo's "delay claims based on delays caused by utilities," as barred by the contract clause limiting additional compensation for reason of delay caused by actions of utility companies. The parties agreed to dismiss all remaining claims without prejudice under CR 41, in order to obtain appellate review of the partial summary judgment.

In Scoccolo Constr., Inc. v. City of Renton, 102 Wash.App. 611, 616-17, 9 P.3d 886 (2000) (Scoccolo I) this court determined that because, as pleaded, Scoccolo's claims were based on Renton's acts or failures to act, the contractual provision, even if valid, did not bar the claims, and reversed the summary judgment order.

Following Scoccolo I, Renton again sought partial summary judgment, this time purporting to "address only liability for the actions or inactions of Puget Power, U.S. West and TCI Cable and not what Renton may or may not have done." Clerk's Papers at 72. Renton argued that "the contract repeatedly, clearly and unequivocally places the costs arising from any utility delays on Scoccolo." Id. at 73. Renton argued that RCW 4.24.360 does not void the contract terms because the utilities were not Renton's agents, Renton did not have control over the utilities, and Renton's franchise and underground wiring agreements with Puget Sound Power did not create an agency relationship or allow Puget to act for Renton, or allow Renton to control Puget, and was simply entered in response to Washington Utilities and Transportation Commission requirements. Renton also argued that Scoccolo failed to present evidence that the utilities failed to perform their work at a time, in a sequence, or for durations that were different from Scoccolo's anticipation at *1251 the time it bid on the project or made its schedule.

In response, Scoccolo argued that this court's holding in Scoccolo I prevented summary judgment on the same issue, that the utilities were contractors acting for Renton, that RCW 4.24.360 rendered void the contractual bar to recovery based on delay of the utilities with which Renton had franchise agreements and contracts, and that material issues of fact remained regarding Scoccolo's scheduling of the project.

The trial court denied Renton's motions for summary judgment and reconsideration. By order filed June 10, 2002, the trial court determined:

Based upon the Franchise Agreement between the City of Renton and Puget Sound Power and Light (Puget Sound Energy), Puget Sound Power and Light was acting for the City of Renton on the Park Avenue Project for purposes of RCW 4.24.360 and, therefore, the provision of TP 1-07.17 in the Contract for the Park Avenue North Improvements precluding damages "for reason of delay caused by the actions of any utility company" is void as to Puget Sound Power and Light.

Clerk's Papers at 372.

The trial court later denied Renton's motions for partial summary judgment regarding the other utilities, determined that TCI was also acting for Renton based on a newly discovered franchise agreement, and determined that genuine issues of material fact remained as to whether Scoccolo's work was delayed.

At trial, the jury was instructed as follows:

The Court has determined that Puget Power and TCI were "acting for" the City of Renton. It is your duty to determine if U.S. West was "acting for" the City of Renton on the Park Avenue Project. US West was acting for the City of Renton if it was acting "in place of", "in the interest of", or "in favor of" Renton.

Instruction 12, Clerk's Papers at 939.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

SCOCCOLO CONST. v. City of Renton
145 P.3d 371 (Washington Supreme Court, 2006)
Scoccolo Construction, Inc. v. City of Renton
158 Wash. 2d 506 (Washington Supreme Court, 2006)
Watch v. Skagit County
120 P.3d 56 (Washington Supreme Court, 2005)
Blinn v. BEATRICE COMMUNITY HOSPITAL AND HEALTH CENTER, INC.
13 Neb. Ct. App. 459 (Nebraska Court of Appeals, 2005)
Blinn v. Beatrice Community Hospital & Health Center, Inc.
696 N.W.2d 149 (Nebraska Court of Appeals, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
103 P.3d 1249, Counsel Stack Legal Research, https://law.counselstack.com/opinion/scoccolo-const-inc-v-city-of-renton-washctapp-2005.