School District No. 172 v. Josenhans

153 P. 326, 88 Wash. 624, 1915 Wash. LEXIS 1141
CourtWashington Supreme Court
DecidedDecember 15, 1915
DocketNo. 12549
StatusPublished
Cited by6 cases

This text of 153 P. 326 (School District No. 172 v. Josenhans) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
School District No. 172 v. Josenhans, 153 P. 326, 88 Wash. 624, 1915 Wash. LEXIS 1141 (Wash. 1915).

Opinion

Per, Curiam.

Sometime in the summer of 1911, appellants, architects in the city of Seattle, entered into an oral contract with the directors of the respondent school district (hereinafter referred to as the respondents) to draw the plans for a two-story frame schoolhouse to be erected at Cedar Falls, to receive bids and award the contract for the construction thereof, and to exercise a certain supervision over the work the exact nature of which is in dispute. For drawing the plans, they were to receive three per cent of the contract price of the building; for receiving bids and awarding the contract, one-half of one per cent; and for making inspection, $10 and expenses for each trip. The plans were drawn in August, 1911, the contract awarded on September 7, and the building completed, with the exception [626]*626of the finishing of the second story, which the contract provided was to be roughed in only, some time between November 20 and 23, 1911.

On the evening of January 13, 1913, the upper story of the building collapsed under the weight of snow which had accumulated on the roof, leaving the first story standing practically unharmed, except for some damage to the plastering. Soon after the collapse, the directors built a temporary roof over the remaining first story, and commenced this action to recover from the appellants damages for the failure of the building, alleging that the collapse was due wholly to the negligence of appellants in the preparation of the plans and superintending the construction of the building; the specific charge being that the plans and specifications did not provide for, and the building did not have when completed, a roof sufficiently strong to carry the load which it should reasonably have been foreseen it would be obliged to carry. The trial court found that the negligence of the appellants was the cause of the collapse, and awarded damages of $1,100.

The issues raised on this appeal are almost entirely questions of fact; consequently it will be necessary to discuss the evidence at considerable length. A logical disposition of the issues would seem to require answers to the following questions:

(1) Was the building faultily planned and constructed?

(2) If so, were the appellants responsible for the faulty construction ?

(3) Did any acts of the directors contribute to the collapse and release the appellants from liability?

(4) Was the collapse due to the alleged faulty construction or to unusual conditions which the appellants could not reasonably have been expected to foresee ? ■

(5) Did the court correctly determine the damages?

I. The only particular in which it is claimed the construction was faulty is that the roof was insufficiently braced. [627]*627The roof was an ordinary hip roof, covering a structure 83 feet by 32 feet, with gables approximately thirty feet wide at the center, both front and back, and at the intersection of the ridge boards of the main roof and of the gables, was a belfry. The evidence of inferior construction was that an insufficient number of collar beams had been used on the rafters, thus allowing the roof to spread apart under the weight of snow and push out the side walls. The respondents’ witnesses testified that there were only four or five collar beams used, and these were placed near the apex of the voof. The only requirement in the specifications for collar beams was that they should be of 2x6 timber. Mr. Allen testified that, in the absence of any specification requiring a definite number to be used, this would indicate a collar beam on every pair of common rafters; while Mr. Cronin, the contractor, testified this would indicate collar beams wherever necessary. Witnesses for the school district testified that the roof without collar beams would not be strong enough to withstand the load it should be expected to carry; while Mr. Allen testified that, even without collar beams, it would stand up under any except an extraordinary load. The trial court found that the roof did not have adequate support, and we do not find that his conclusion is not supported by the preponderance of the evidence.

II. The next consideration is whether the appellants were responsible for the faulty construction. They contend that the roof as planned was strong enough for the building, and that they did not agree to superintend the construction to the extent of guaranteeing that the building was put up according to the plans and specifications. The respondents contend that the contract was that the appellants were to inspect the building as often as necessary, while the appellants contend that they were to inspect only when called upon by the directors, and that the certificates of completion issed during the progress of the work were issued only to enable the contractor to secure his money, and not as evi[628]*628dence that the work had been satisfactorily completed. The contract between the contractor and the school district provided that the contractor should perform all the work to the satisfaction of the architects, and, as this contract was drawn by the appellants for the directors, we feel that the trial court was justified in concluding that the appellants were to make whatever inspection was necessary, and that the final certificate was evidence that the work had been completed to their satisfaction, although the bill rendered by the appellants upon the completion of the work showed that but two trips of inspection had been made, the second over a week before the building was finished.

III. On behalf of the appellants, it was shown that the respondents knew that the roof was not provided with collar beams, and that they should have known that the lack of them rendered the roof unsafe, but that this was not called to the attention of the appellants. If we accept the finding that the architects were paid for and did superintend the construction of the building, and that they certified the building as completed in accordance with the plans and specifications, then the respondents would be entitled to rely on the sufficiency of the construction, and although they may have detected what seemed to them to be faulty' construction, they would be justified in relying on the appellants’ judgment that it was a proper construction, as they had engaged the appellants to see that the construction was correct. Nor does the fact that the respondents knew that the roof was spreading shortly before the collapse, and that they took no steps to remove the snow, excuse the appellants, as it is not shown that respondents knew of any immediate danger, but were relying on the roof as constructed being sufficient to sustain its load.

IV. However, all these facts will not avail the respondents unless the strain to which the roof was subjected was one which the appellants should reasonably have expected, as all the evidence that the building was negligently constructed [629]*629must rest on an ultimate finding that it collapsed under a load which appellants should have anticipated. The exact depth of snow on the roof at the time of the collapse was not stated by any of the witnesses, but respondents’ witnesses testified that on other roofs it was approximately nine inches deep, and about ten inches on the ground. The appellants introduced the records of the U. S. Weather Department for the western slope of the Cascades, to show that unusual' snow conditions prevailed at Cedar Falls on January 13, 1913, when the building collapsed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell v. Jones
523 A.2d 982 (District of Columbia Court of Appeals, 1987)
Jarrard v. Seifert
591 P.2d 809 (Court of Appeals of Washington, 1979)
Roland A. Wilson v. Forty-O-Four Grand Corp.
246 N.W.2d 922 (Supreme Court of Iowa, 1976)
City of Durham v. REIDSVILLE ENGINEERING COMPANY
120 S.E.2d 564 (Supreme Court of North Carolina, 1961)
Pastorelli v. Associated Engineers, Inc.
176 F. Supp. 159 (D. Rhode Island, 1959)
Dehoney v. Gjarde
236 P. 290 (Washington Supreme Court, 1925)

Cite This Page — Counsel Stack

Bluebook (online)
153 P. 326, 88 Wash. 624, 1915 Wash. LEXIS 1141, Counsel Stack Legal Research, https://law.counselstack.com/opinion/school-district-no-172-v-josenhans-wash-1915.