City of Durham v. REIDSVILLE ENGINEERING COMPANY

120 S.E.2d 564, 255 N.C. 98, 1961 N.C. LEXIS 564
CourtSupreme Court of North Carolina
DecidedJune 16, 1961
Docket666
StatusPublished
Cited by14 cases

This text of 120 S.E.2d 564 (City of Durham v. REIDSVILLE ENGINEERING COMPANY) is published on Counsel Stack Legal Research, covering Supreme Court of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
City of Durham v. REIDSVILLE ENGINEERING COMPANY, 120 S.E.2d 564, 255 N.C. 98, 1961 N.C. LEXIS 564 (N.C. 1961).

Opinion

DeNNy, J.

The additional defendants are relying upon two exceptions and the assignments of error based thereon as follows: (1) That the Judge of the Superior Court erred in overruling their demurrer in that the cross-action of the Casualty Company does not state facts sufficient to constitute a cause of action; and (2) that the Judge of the Superior Court erred in overruling the demurrer to the amended cross-action of the Casualty Company in that there is a misjoinder of parties and causes of action.

With respect to the first assignment of error, it was stipulated that the pertinent portions of the contract referred to in the pleadings are to be considered as a part of the cross-action for purposes of determining whether or not the court below committed error in overruling the demurrer of the additional defendants. We must, therefore, look to the contract itself to determine the duties of the parties, rather than to the general allegations set out in the cross-action filed by the Casualty Company. Williamson v. Miller, 231 N.C. 722, 58 S.E. 2d 743.

In the last cited case this Court said: “Since the contract is made a part of the complaint, and is alleged as the sole basis of recovery, the Court will look to its particular provisions rather than the more broadly stated allegations in the complaint, or the conclusions of the pleader as to its character and meaning. Upon proper construction of these writings depends the propriety of the judgment overruling the demurrer.” Ferrell v. Highway Commission, 252 N.C. 830, 115 S.E. 2d 34.

An examination of the contract reveals that it was executed by the Construction Company as party of the first part and the City as party of the second part. It is true that the Proposal, which became the contract, and included the plans and the specifications, was prepared by Piatt and Davis, Engineers, for the City; but they did not execute the contract, nor in any way bind themselves as surety for the Construction Company. The last paragraph of the contract states: “The acceptance of this Proposal by the City Council for and on behalf of the City of Durham, N. C., party of the second part, as evidenced by the signature of the properly authorized officers of said City, shall be held to be a mutual agreement as to each and every clause of this Proposal and to constitute a contract between the parties hereto.”

The contract also provides that the contractor “agrees to be responsible for the entire work herein contemplated until its completion *102 and final acceptance * * Neither does any inspection prior to the issuance of certificates for progress payments or final payment appear to be required by the terms of the contract.

As to the progress payments, the contract provides simply that “the Engineer will once a month make an approximate estimate in writing of the work done and materials furnished or apparatus delivered or installed from the beginning of the work.”

Regarding the final payment, the contract provides: “That whenever in the opinion of the Engineer the work proposed shall have been completely performed on the part of the party of the first part the Engineer will proceed * * * to measure up the work and will make out the final estimate for the same, and will certify the same * *

It is provided in the contract that where the word “Engineer” is used it shall be held to mean Piatt and Davis, the Supervising Engineers, or any authorized assistant acting within the scope of the particular duties entrusted to him.

The contract provides further that “inspection of the work at any time shall not relieve the party of the first part (the Construction Company) of any obligation to do sound and reliable work * * * and * * * that any omission to disapprove of any work by the Engineer * * * shall not be construed to be an acceptance of any imperfect, unsightly, or defective work.”

With respect to the duties and responsibilities of the additional defendants under the terms of the contract, the contract provides: “That the Engineer shall decide the meaning and intent of any portion of these specifications or of the plans where same may be found to be obscure or at variance or in dispute and shall have the right to correct any errors or omissions therein when such corrections are necessary to the proper fulfillment of the intention of said plans and specifications and that the Engineer shall have the final decision on all matters of dispute involving the character of the work, the compensation to be made therefor or any other question arising upon this Proposal after its acceptance.”

We hold that, with respect to the interpretation of the meaning and intent of the plans and specifications, as well as to the authorization that additional work not expressly authorized in the contract but which the Engineers may deem necessary to the fulfillment of the terms of the contract and the proper completion of the job, which authority is expressly granted to the Engineers in the contract, together with their decision on all matters of dispute involving the character of the work, compensation for extra work, etc., the Engineers in making such decisions under the terms of the contract would be acting in the capacity of arbitrators and could not be held liable in damages *103 to either party to the contract in the absence of bad faith. Stevenson v. Watson (1879, Eng.), L.R. 4 C.P. Div. 148; Chambers v. Goldthorpe (1901, Eng.), 1 KB. 624, 4 B.R.C. 833-C.A.; Corey v. Eastman, 166 Mass. 279, 44 N.E. 217, 55 Am. St. Rep. 401; Wilder v. Crook, 250 Ala. 424, 34 So. 2d 832. Other cases are to the effect that the Supervising Architect or Engineer may be held liable to the building owner for damages resulting from negligently certifying the completion of the work. Palmer v. Brown, 127 Cal. App. 2d 44, 273 P. 2d 306; Bump v. McGrannahan, 61 Ind. App. 136, 111 N.E. 640; Lindeburg v. Hodgens, 89 Misc. 454, 152 N.Y.S. 229; Pierson v. Tyndall (Tex. Civ. App., 1894), 28 S.W. 232; School District v. Josenhans, 88 Wash. 624, 153 P. 326. See Annotations, 43 A.L.R. 2d 1227. However, the question of the liability of these additional defendants to the City is not presented for determination on this appeal.

In the case of Bump v. McGrannahan, supra, the Court held that an architect may be held liable to the owner where he “agreed and undertook to supervise the construction * * * and determine * * * when any payments were due * * * according to the plans and specifications and contracts previously entered into * * * and to see that the work was done in accordance therewith”; where he wrongfully authorized payments to be made that were not due; and where the owner “paid out money he should have retained * * * and * * * was damaged to the extent of the money so paid out by him.” The Court said further: “It is not claimed * * * that appellants (architects) undertook to construct, or to guarantee the completion of, the building at the contract price, and their liability would not therefore arise by reason of the failure of the contractor to complete the building according to the contract * * * .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

RPR & Associates v. O'Brien/Atkins Associates, P.A.
24 F. Supp. 2d 515 (M.D. North Carolina, 1998)
William v. American Ass'n of Blood Banks
676 A.2d 1036 (Supreme Court of New Jersey, 1996)
RPR & ASSOCIATES v. O'Brien/Atkins Associates
921 F. Supp. 1457 (M.D. North Carolina, 1995)
Feichtinger v. Conant
893 P.2d 1266 (Alaska Supreme Court, 1995)
Bolton Corp. v. T. A. Loving Co.
380 S.E.2d 796 (Court of Appeals of North Carolina, 1989)
Shoffner Industries, Inc. v. W. B. Lloyd Construction Co.
257 S.E.2d 50 (Court of Appeals of North Carolina, 1979)
Davidson & Jones, Inc. v. County of New Hanover
255 S.E.2d 580 (Court of Appeals of North Carolina, 1979)
McKinney Drilling Co. v. Nello L. Teer Co.
248 S.E.2d 444 (Court of Appeals of North Carolina, 1978)
Ballou v. Basic Construction Co.
407 F.2d 1137 (Fourth Circuit, 1969)
O. G. Thompson & Sons, Inc. v. Koury Hosiery Mills, Inc.
161 S.E.2d 655 (Court of Appeals of North Carolina, 1968)
Blecick v. School District No. 18 of Cochise County
406 P.2d 750 (Court of Appeals of Arizona, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
120 S.E.2d 564, 255 N.C. 98, 1961 N.C. LEXIS 564, Counsel Stack Legal Research, https://law.counselstack.com/opinion/city-of-durham-v-reidsville-engineering-company-nc-1961.