Lindbrook Construction, Inc. v. Mukilteo School District No. 6

458 P.2d 1, 76 Wash. 2d 539, 1969 Wash. LEXIS 682
CourtWashington Supreme Court
DecidedAugust 21, 1969
Docket39335
StatusPublished
Cited by16 cases

This text of 458 P.2d 1 (Lindbrook Construction, Inc. v. Mukilteo School District No. 6) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lindbrook Construction, Inc. v. Mukilteo School District No. 6, 458 P.2d 1, 76 Wash. 2d 539, 1969 Wash. LEXIS 682 (Wash. 1969).

Opinions

Hill, J.

There are on this appeal 10 assignments of [540]*540error; 4 relate to claimed errors in the findings of fact made by the trial court; 5 relate to a failure to make, findings proposed by the defendant-appellant; and 1 relates to the trial court’s conclusion of law No. 2:

That judgment should be entered in favor of the plaintiff and against the defendant in the sum of $42,834.20 together with plaintiff’s taxable costs.

The findings of fact give a succinct statement of what the controversy is all about. The plaintiff is a construction company; the defendant is a school district. Findings of fact Nos. 3 to 8 inclusive are as follows:

That on or about the 17th day of July, 1963, plaintiff submitted to defendant its bid for the grading and drainage work at the site of the Lake Stickney Elementary School, Mukilteo, Snohomish County, Washington. That defendant furnished Specifications, Drawings and other contract documents to plaintiff for use in the preparation of its bid.

(Finding of fact No. 3)

That the specifications, drawings and other contract documents furnished plaintiff by defendant showed the work to be performed and made specific representations with respect to the conditions to be encountered, the source and amount of cut and fill, the depth of required excavation and that the fill material required would be available from areas of proposed cuts. That plaintiff reasonably relied upon said representations in the preparation and submission of its bid.

(Finding of fact No. 4)

That plaintiff was awarded the contract for said work upon its lump sum' bid óf $33,617.00 and proceeded with the performance of the work as directed by thé defendant through its authorized agents. That in the performance of the work plaintiff encountered unanticipated conditions at substantial variance with the conditions represented. by the contract documents necessitating extra work as'íóllows:
(a) Extensive shortage of fill material from areas of proposed cuts requiring plaintiff to open and utilize a borrow pit operation;
[541]*541(b) Extra excavation, fill and select fill in the building area;
(c) Extra excavation and fill in the south parking area;
(d) Extra excavation, fill and gravel for the interceptor ditch; and
(e) Extra excavation and fill in the drainfield. That the said extra work required plaintiff to obtain and utilize additional and heavier equipment, caused the work to extend into the fall and winter months resulting in increased weather and moisture problems and caused plaintiff to remain on the job for more than double the time which would have been required to complete the work as .originally represented by the contract documents.

(Finding of fact No. 5)

That plaintiff gave notice to defendant of such changed conditions within a reasonable time after they were first observed and claimed an equitable adjustment for the extra work involved. That at all times defendant had knowledge of the conditions encountered and the extra work performed by plaintiff and defendant directed plaintiff to proceed with the said extra work.

(Finding of fact No. 6)

That the extra work plaintiff was required to perform by reason of the changed conditions and defendant’s directions as hereinabove set forth was and is of the reasonable value of $39,355.09. That in addition thereto defendant has withheld from plaintiff on the basic contract price the sum of $3,479.11 which amount is due, owing and unpaid.

(Finding of fact No. 7)

That defendant has waived any claim for liquidated damages against plaintiff by its actions in directing the extra work, making payments during the alleged delay and leading plaintiff to believe that no liquidated damages would be assessed.

(Finding of fact No. 8)

As these findings indicate, on a contract for $33,617 the extras, as found by the trial court, amounted to $39,355.09. This seems extraordinary, but the School District, rather [542]*542than questioning the cost figures of the contractor1 and presenting any of its own, urged that what the contractor was claiming to be extra work because of changed conditions was actually within the contract.

The findings go directly to the heart of the controversy and, contrary to the contention of the School District, find that in the performance of the work the contractor encountered unanticipated conditions at substantial variance with the conditions represented in the contract documents, which necessitated extra work; that the contractor gave notice of such changed conditions and claimed an equitable adjustment for the extra work; and that the School District at all times had knowledge of the changed conditions and directed the plaintiff to proceed with the extra work.

Although the School District assigns error to four of these findings (4, 5, 6 and 7) there is substantial (though conflicting) evidence to sustain them. These findings bring the case within our holding Bignold v. King County, 65 Wn.2d 817, 399 P.2d 611 (1965). The conclusion of law (quoted on page 540) to which error is assigned necessarily follows from the findings made.

The School District strenuously urges that Articles 25 and 26 of the contract preclude any recovery. Article 25, in part, provides:

Should conditions encountered below the surface of the ground be at variance with the conditions indicated by the drawings and specifications the contract sum shall be equitably adjusted upon claim by either party made within a reasonable time after the first observance of the conditions.

Article 26 provides:

If the Contractor claims that any instructions by draw[543]*543ings or otherwise involve extra cost under this contract, he shall give the Architect written notice thereof within a reasonable time after the receipt of such instructions, and in any event before proceeding to execute the work, and the procedure shall then be as provided for changes in the work. No such claim shall be valid unless so made.

It is the School District’s position that there was no variance, but if it be assumed that conditions were at variance with the drawings and specifications, that no written notice having been given before proceeding to do the extra work, there can be no recovery.

The trial court held squarely notice in writing had been waived, saying:

It is clear to this Court that the architect knew of this work, that he directed that it proceed, and at such time he indicated he did not feel that such was an extra; so I do not feel the failure to give written notice set forth in the contract would apply. The fact he was never informed of the actual extra, in my opinion, would not have added anything. I feel failure of notice had been waived in the manner he handled such orders.

Bignold v. King County, supra, supports the trial court in that position. See also American Sheet Metal Works, Inc. v. Haynes,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mike M. Johnson, Inc. v. Spokane County
150 Wash. 2d 375 (Washington Supreme Court, 2003)
Mike M. Johnson, Inc. v. County of Spokane
78 P.3d 161 (Washington Supreme Court, 2003)
Absher Construction Co. v. Kent School District No. 415
890 P.2d 1071 (Court of Appeals of Washington, 1995)
Hensel Phelps Construction Co. v. King County
787 P.2d 58 (Court of Appeals of Washington, 1990)
Northern Improvement Co. v. South Dakota State Highway Commission
25 Cont. Cas. Fed. 82,625 (South Dakota Supreme Court, 1978)
Stender v. Twin City Foods, Inc.
510 P.2d 221 (Washington Supreme Court, 1973)
State v. Vidal
508 P.2d 158 (Washington Supreme Court, 1973)
Rodgers v. Danforth
486 S.W.2d 258 (Supreme Court of Missouri, 1972)
Ocean Spray Cranberries, Inc. v. Doyle
500 P.2d 79 (Washington Supreme Court, 1972)
Johnson v. Harrigan-Peach Land Development Co.
489 P.2d 923 (Washington Supreme Court, 1971)
Lindbrook Construction, Inc. v. Mukilteo School District No. 6
458 P.2d 1 (Washington Supreme Court, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
458 P.2d 1, 76 Wash. 2d 539, 1969 Wash. LEXIS 682, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lindbrook-construction-inc-v-mukilteo-school-district-no-6-wash-1969.