Eastern Tunneling Corp. v. Southgate Sanitation District

487 F. Supp. 109
CourtDistrict Court, D. Colorado
DecidedMarch 27, 1980
DocketCiv. A. 77-K-997
StatusPublished
Cited by9 cases

This text of 487 F. Supp. 109 (Eastern Tunneling Corp. v. Southgate Sanitation District) is published on Counsel Stack Legal Research, covering District Court, D. Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eastern Tunneling Corp. v. Southgate Sanitation District, 487 F. Supp. 109 (D. Colo. 1980).

Opinion

MEMORANDUM OPINION AND ORDER

KANE, District Judge.

This is a diversity action brought by plaintiff contractor, Eastern Tunneling Corporation (“ETC”), against Southgate Sanitation District, a public corporation organized under the laws of the State of Colorado, for additional amounts of work performed under a contract for the construction of the Orchard Tunnel, a sanitary sewage tunnel. The case is currently before the court on defendant’s motion for summary judgment.

The district awarded the construction contract in question to plaintiff after plaintiff submitted the lowest bid for the work at $1,919,520. In order for plaintiff to construct the tunnel in question it was necessary for it to undertake a certain amount of excavation of dirt and rock. Prior to bidding, the defendant district engaged a private firm to undertake subsurface investigations which were done by taking borings at selected locations. Upon undertaking the excavation, plaintiff allegedly discovered that the level of rock was substantially higher than had been represented by the borings, and was therefore required to expend an additional $593,371 in order to complete the excavation. Plaintiff also claims that it expended $45,000 in extra costs in seeking “equitable adjustment,” and $500,-000 in lost business opportunities.

The defendant contends that it is not liable for any additional expenses incurred by the plaintiff since the contract specified that the subsurface information provided was not intended as a representation or warranty and that defendant was not liable for any inaccuracy contained in that information.

The defendant also argues that the contract clearly places the burden of risk for differing soil conditions upon the plaintiff and that the plaintiff should therefore be made to absorb the costs for miscalculations.

Plaintiff relies on the doctrine of “equitable adjustment” for its claims. It argues *112 that delays in construction because of changed subsurface conditions gave rise to its claims in this action. Plaintiff does not characterize its claims for extra work under the contract, but for additional amounts of work necessary to complete the project where the additional work resulted from subsurface conditions that differed from those reasonably anticipated based on all the materials prepared and submitted to prospective bidders by defendant.

In its motion for summary judgment, defendant urges that as a matter of law and contract interpretation, plaintiff cannot recover under the theory of “equitable adjustment” and that plaintiff cannot recover damages for loss of business for breach of contract under Colorado law. Both parties agree that Colorado law governs the construction of this contract.

I EQUITABLE ADJUSTMENT

In support of its theory of equitable adjustment, plaintiff cites federal Court of Claims cases dealing with government contracts which as a matter of course contain a “changed conditions” clause. This type of clause is sometimes called a “differing site conditions” clause. Such clauses provide for “equitable adjustment” when the site conditions substantially differ from those anticipated by the contracting parties. 1 Plaintiff admits that the contract at bar does not contain such a clause.

Despite the absence of such a clause in the Orchard Tunnel Project, plaintiff claims that contract provision GP 8-7 is equitable adjustment. GP 8-7 provides:

DETERMINATION AND EXTENSION OF CONTRACT TIME FOR COMPLETION. The Contractor shall perform fully, entirely, and in a satisfactory and acceptable manner the work contracted, within the number of days stipulated in the Proposal and Contract. Time will be assessed against the Contractor beginning with the actual date the work is started when this is in accordance with the Notice to Proceed. If the Contractor does not begin the work within the limit as designated in the Notice to Proceed, the calendar days shall start on the first calendar day after the expiration of the ten (10) day limit as stated in the Notice to Proceed. In adjusting the contract time for the completion of the project, all strikes, lockouts, unusual delays in transportation, or any condition over which the Contractor has no control, and also any suspensions ordered by the Engineer for causes not the fault of the Contractor, shall be excluded from the computation of the contract time for completion of the work. If the satisfactory execution and completion of the contract shall require work or material in greater amounts or quantities than those set forth in the contract, then the contract time shall automatically be increased in the same proportion as the cost of the additional work bears to the original work contracted for. No allowances will be made for delays or suspensions of the prosecution of the work due to the fault of the Contractor. In order to secure an extension of time for delays beyond his control, the Contractor shall within ten (10) days from the beginning of any such delay notify the Owner in writing of the cause of the delay and extend the time for completing the work when, in his judgment, the findings of fact justify such an extension, and his finding of fact thereon shall be final and conclusive. (Emphasis added.)

Since the construction of an unambiguous contract presents a question of law, the court must first determine whether GP 8-7 constitutes a “changed conditions” *113 clause enabling plaintiff to recover for equitable adjustment. See Grant Inv. Co. v. Fuller, 171 Colo. 86, 464 P.2d 859 (1970); Western Colo. Power Co. v. Gibson Lumber & Coal Co., 65 Colo. 288, 176 P. 318 (1918). GP 8-7 differs substantially from the standard changed conditions clause set forth in footnote one. First, GP 8-7 makes no reference to changed soil conditions. Second, it does not provide for an equitable adjustment in payment in the event that differing soil conditions are encountered. GP 8-7 clearly and unambiguously provides for extension of time for completion if the contractor encounters any condition over which he has no control. The sole remedy in this event is for the contractor to secure a written extension of time. The clause further provides that the findings of the project owner, defendant, are conclusive and final. Although plaintiff attempted to secure extensions of time under this clause, defendant determined that these extensions were unwarranted. It is settled under Colorado law

that where parties to a contract designate one who is authorized to determine questions relating to the execution of the contract, and stipulate that his determination shall be final and conclusive, both parties are conclusively bound by his determination of such matter, except in ease of fraud or gross mistake, implying bad faith or failure to exercise an honest judgment * * * Town of Sterling v. Hurd, 44 Colo. 436, 446, 98 P. 174, 177 (1908).

Since plaintiff does not allege that defendant’s denial of an extension under this provision was made in bad faith, it is clear that the remedy for extension is the sole remedy under GP 8-7.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Warren Wexler v. United States
961 F.2d 221 (Tenth Circuit, 1992)
Clevco, Inc. v. Municipality of Metropolitan Seattle
799 P.2d 1183 (Court of Appeals of Washington, 1990)
Green Construction Co. v. Kansas Power & Light Co.
717 F. Supp. 738 (D. Kansas, 1989)
McDevitt & Street Co. v. Marriott Corp.
713 F. Supp. 906 (E.D. Virginia, 1989)
Cook v. Oklahoma Board of Public Affairs
1987 OK 22 (Supreme Court of Oklahoma, 1987)
Pinkerton and Laws Co., Inc. v. Roadway Exp., Inc.
650 F. Supp. 1138 (N.D. Georgia, 1986)
Lowell Staats Mining Co. v. Pioneer Uravan, Inc.
596 F. Supp. 1428 (D. Colorado, 1984)
M.C. Anderson v. Golden
569 F. Supp. 122 (S.D. Georgia, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
487 F. Supp. 109, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eastern-tunneling-corp-v-southgate-sanitation-district-cod-1980.