L. J. McNulty, Inc. v. Village of Newport

187 N.W.2d 616, 290 Minn. 117, 1971 Minn. LEXIS 1104
CourtSupreme Court of Minnesota
DecidedApril 16, 1971
Docket42291
StatusPublished
Cited by9 cases

This text of 187 N.W.2d 616 (L. J. McNulty, Inc. v. Village of Newport) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L. J. McNulty, Inc. v. Village of Newport, 187 N.W.2d 616, 290 Minn. 117, 1971 Minn. LEXIS 1104 (Mich. 1971).

Opinion

Nelson, Justice.

This action was commenced in the District Court of Washington County by plaintiff, L. J. McNulty, Inc., against the village of Newport to recover damages of $100,710 by reason of false information furnished plaintiff by the village, on which informa *119 tion plaintiff based a construction bid. The village joined as third-party defendants its consulting engineer, Banister Engineering Company (hereinafter referred to as Banister), and Blake Engineering Company (hereinafter referred to as Blake), a firm engaged in the business of making soil borings.

The case was tried before the court, without a jury, in October 1968. By agreement of the parties, the question of liability was tried separately, the question of damages being reserved for future determination. At the close of plaintiff’s case, the court granted defendants’ motion for judgment of dismissal. Plaintiff subsequently moved that the order for judgment entered April 25,1969, and the judgment entered pursuant thereto be set aside and the cáse be reopened to take additional testimony or for a new trial. On October 14, 1969, the trial court filed its order denying plaintiff’s motion.

The pertinent facts appear to be as follows: In the fall of 1959 defendant village contracted with Banister for engineering services in connection with a contemplated program of sanitary sewers, sewage treatment plant, water mains, and supply and storage systems. Sometime prior to October 1962, Banister prepared a feasibility report outlining the proposed construction and its estimated cost.

A rock formation of Shakopee-Oneota limestone lies beneath the village of Newport, and in many places the rock comes close to the surface and is covered with only a thin layer of sand and gravel. It was evident that in order to properly estimate the costs and to design a sewer and water system for the village, determinations as to the below-surface rock conditions had to be made. Seventy soil borings and seismic soundings of the area had been obtained at an earlier time by the village to determine subsurface rock conditions, but Banister recommended that more borings be taken to determine the location of rock. On the basis of Banister’s recommendation, defendant village hired Blake to take soil borings.

*120 Blake was furnished an ordinary street map of the village showing where the sewer and water lines were to be laid and was instructed to make borings at street intersections and, in areas where it encountered obstructions, at midblock points in the shorter blocks and at 200-foot intervals in the longer blocks. The job was commenced in January 1963 and took approximately a month. Blake made the borings with a hydraulically operated drill consisting of a 6-inch auger equipped with a carbide bit. The boring points were taken within the street right-of-way, just off the edge of the blacktop, and about 12 feet from the centerline of the road.

Blake’s method of operation was to drill a hole until the drill met resistance and then to withdraw it from the hole and record the depth the bit had penetrated. If the bit had limestone dust on it, Blake identified the obstruction as limestone. If it did not, Blake characterized the obstruction as something other than limestone and identified it as “boulder.” In all, Blake made borings at 206 points and plotted these depths on the street map provided by Banister.

Banister used this boring data for planning and designing purposes in the preparation of the final plans. The data was plotted on plan profile sheets which illustrated the project in two forms —a view from the top in the form of a map or plan showing adjacent property, the location of buildings and existing utilities, and the location of the proposed sewer and water systems; and a view from the side of the street in the form of a profile showing the elevation above sea level of the centerline of the street and the elevation of the proposed water and sewer systems. After Blake’s drilling points were plotted, the points were connected with straight lines to make up a “rock profile” which was included in the side-view aspect of the plan profile sheets.

Banister used the rock profile to make adjustments and alterations in previous plans for the system. The cost estimate submitted by Banister with the original feasibility report was also modified as the plans were changed, and the final cost estimate *121 for the system of sanitary sewers and water mains arrived at was $1,070,000. All of this information was furnished to defendant village prior to the letting of any contracts to begin construction on the project.

In May 1963, the village of Newport advertised for bids. It furnished plans and specifications, including the rock profile sheets, to bidding contractors sometime after May 16, 1963. Bids were opened on June 7, 1963, and a contract for the sewer and water systems was awarded to plaintiff, who was the low bidder at $1,010,416.

Plaintiff commenced work July 8,1963, and almost immediately began complaining to Banister’s project engineer that rock was being found at a higher level at the construction site, the center of the street, than was shown on the plans of the project. The job went forward; however, plaintiff and Banister’s engineer agreed that field notes of the rock depth found in the trenches dug out by plaintiff’s crews would be kept. Thereafter, measurements were taken from the top of the ground down to the level of rock at 25-foot intervals along the trench site. These measurements were recorded in field notebooks and were plotted on “As-built” plans as the work progressed.

Some months after the job was commenced, Blake was asked to return and make some more borings in an effort to discover the reason for the discrepancies between the rock level plotted from Blake’s borings and shown on the project plans, and the rock level found in the trenches at the center of the street. Blake made seven borings near areas where original borings had been taken. The reborings for the most part showed rock elevations at points corresponding to Blake’s original data — some below and some above the elevations shown by Blake.

The controlling issue on this appeal is whether a rock profile presented to bidders on a sewer construction contract and plotted from soil borings which accurately measured depth of rock along a line parallel to but 12 feet to one side of a proposed trench constitutes actionable misrepresentation of the depth of rock in the *122 trench when later excavation of the trench revealed material inconsistencies between the depth of rock found there and the depth found at boring points making up the profile.

A false or fraudulent representation of a material fact, made with the intent that it be acted upon, may indeed be actionable if another person is thereby induced to act or justified in acting to his detriment. However, in the instant case, the trial court found that defendant village had not misrepresented any material fact or otherwise defrauded or misled plaintiff into entering into the contract for the construction of a sewer and water system.

That defendant village is built atop a formation of limestone is a matter of common knowledge.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

D.H. Blattner & Sons, Inc. v. Firemen's Insurance Co.
535 N.W.2d 671 (Court of Appeals of Minnesota, 1995)
Brown Bros. Inc. v. Metropolitan Government
877 S.W.2d 745 (Court of Appeals of Tennessee, 1993)
Midwest Dredging Co. v. McAninch Corp.
424 N.W.2d 216 (Supreme Court of Iowa, 1988)
Cook v. Oklahoma Board of Public Affairs
1987 OK 22 (Supreme Court of Oklahoma, 1987)
Jasper Construction, Inc. v. Foothill Junior College District
91 Cal. App. 3d 1 (California Court of Appeal, 1979)
Robert E. McKee, Inc. v. City of Atlanta
414 F. Supp. 957 (N.D. Georgia, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
187 N.W.2d 616, 290 Minn. 117, 1971 Minn. LEXIS 1104, Counsel Stack Legal Research, https://law.counselstack.com/opinion/l-j-mcnulty-inc-v-village-of-newport-minn-1971.