McCree & Company v. State

91 N.W.2d 713, 253 Minn. 295, 1958 Minn. LEXIS 674
CourtSupreme Court of Minnesota
DecidedAugust 1, 1958
Docket37,316
StatusPublished
Cited by23 cases

This text of 91 N.W.2d 713 (McCree & Company v. State) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McCree & Company v. State, 91 N.W.2d 713, 253 Minn. 295, 1958 Minn. LEXIS 674 (Mich. 1958).

Opinion

Nelson, Justice.

McCree & Company brings this action against the State of Minnesota to recover damages for an alleged breach of warranty arising out of a contract for the improvement of Trunk Highway Nos. 14 and 22 in southern Minnesota, in the vicinity of the city of Mankato, and also to recover an amount which has been withheld by the state. The Highway Department engineers started work in the fall of 1950 on plans and specifications for the improvement. Subsequent to April 2, 1951, the state advertised for competitive bids, and, within 15 days after receiving notice of the advertisement for bids, plaintiff submitted its bid bearing date April 27, 1951. The contract was let to plaintiff as low bidder on the same date. A formal contract, drafted in its entirety by the state, *298 was thereafter entered into between the parties pursuant to existing highway regulations and requirements.

The plans and specifications, which were made a part of the contract, required the plaintiff to compact the soil used as embankment material to a specified density tested by the standard laboratory method of tests for the compaction and density of soils. Relying upon the state’s plans and specifications providing for strict compliance under supervision and inspection by the state’s engineers, plaintiff contends that it was led to believe and did believe that the soil materials could be compacted as specifically required by the state therein. The plaintiff as contractor was given no right to deviate from the plans and specifications under the contract provisions. The following contract clauses are indicative of the extent to which the terms of the contract were obligatory upon plaintiff both as to performance and the accomplishment of results. Section 1401 states that “The intent of the Plans and Specifications is to prescribe a complete improvement. No deviations from the Plans shall be made unless authorized by the Engineer.” Section 1502 states “All work shall be done in accordance with the lines, grades and dimensions shown in the Plans except as otherwise ordered by the Engineer.” Section 1509 states “Any unauthorized work may be ordered removed and replaced at the Contractor’s expense.”

We think it clear from the foregoing that one of the main issues presented on this appeal is whether the state impliedly represented and agreed in its contract with plaintiff that soil conditions at the work site were such as to make it practicable to perform the prescribed work pursuant to plans and specifications; that the provisions of the contract contained practicable directions for doing and completing the work; and that these were adequate and sufficient for the purposes therein stated.

The testimony on behalf of the plaintiff is to the effect that it was compelled to rely and did rely upon the representations and agreement on the part of the state that the soil conditions were suitable and sufficient to make it practicable to comply with the plans and specifications and for the plaintiff to perform the work to completion in the very definite and specific manner prescribed. The plaintiff had been obligated by the terms of the contract to compact the embankment *299 material between what has been described as stations 31 and 46 to a degree of density specifically required in the plans and specifications. However, in an attempted course of construction throughout the area between stations 31 and 46 plaintiff found it impossible to get compaction to the specified density. It is contended by plaintiff that this was due to the wet condition of the underlying soil and its plastic nature in that area which made it impossible to accomplish compaction by the methods prescribed and definitely required in the plans and specifications prepared and furnished by the engineers for the state.

A reading of the record indicates that the conditions at the work site made it obvious that compaction could not be achieved under the state’s plans and specifications without the state’s authorization to deviate therefrom. Plaintiff brought these facts to the attention of the state’s engineers as soon as the conditions were discovered shortly after commencement of the job on June 4, 1951, and suggested the corrective action needed. It is to be noted that the plaintiff had entered into a contract to do specified work in a specified manner for which payment was to be made on a unit basis; that it commenced work on the project June 4, 1951; and that it was obligated under the terms of the contract to complete the construction work and accomplish the required results by October 15, 1951. Although there was state inspection from the beginning of the project and the state was notified almost immediately regarding the conditions between stations 31 and 46, no change order appears to have been executed on behalf of the state permitting plaintiff to take corrective action, as suggested, by installing perforated drainpipe in the subgrade and using gravel fill rather than a clay fill until order No. 9 was issued in September 1951. This order permitted plaintiff to lay only 800 feet of perforated pipe in the area where these compaction difficulties had been encountered. It was found that that was not sufficient. The compaction difficulties continued to exist in the balance of the area and yet no change order giving plaintiff permission to take similar corrective action throughout the remaining area was issued until May 12, 1952, as change order No. 11, permitting the installation of an additional 900 feet of perforated drainage pipe. The latter change order finally solved the matter so that the plaintiff could go on to a completion of the project.

*300 While the plaintiff under the terms of the contract was required to complete the job by October 15, 1951, it appears that the completion time had to be extended to the month of June 1952. Because of the delay due to the unforeseen wet and plastic soil condition plaintiff was forced to carry over through the winter. It had to provide and spread gravel for winter protection, incur expenses for extra labor and extra use of equipment which could otherwise have been avoided. The construction work was not finally accepted by the state until May 2, 1953.

Plaintiff takes the position that the state, through the contract provisions and the methods and specifications prescribed, in effect represented and warranted it to that the subsoil under and adjacent to the proposed highways between stations 31 and 46 was capable of being compacted as specified and directed; that the soil material was stable and workable under the methods prescribed; and that it was free from excessive subsurface water. Plaintiff further contends that the plans and specifications as they applied to compacting soil materials were wholly inadequate and insufficient in that they failed to disclose the true condition of the soil materials in an area where the state’s engineers had conducted in excess of 100 test-hole drillings over a distance approximating 10,000 lineal feet in October and November 1950; and in that they failed to recognize and disclose that sub-drainage in the area would be required; and in that they failed to make suitable provisions therefor.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

D.H. Blattner & Sons, Inc. v. Firemen's Insurance Co.
535 N.W.2d 671 (Court of Appeals of Minnesota, 1995)
Zontelli & Sons, Inc. v. City of Nashwauk
373 N.W.2d 744 (Supreme Court of Minnesota, 1985)
Julian Johnson Construction Corp. v. Parranto
352 N.W.2d 808 (Court of Appeals of Minnesota, 1984)
Jasper Construction, Inc. v. Foothill Junior College District
91 Cal. App. 3d 1 (California Court of Appeal, 1979)
Mayville-Portland School District No. 10 v. C. L. Linfoot Co.
261 N.W.2d 907 (North Dakota Supreme Court, 1978)
Eric A. Carlstrom Construction Co. v. Independent School District No. 77
256 N.W.2d 479 (Supreme Court of Minnesota, 1977)
Alley Construction Co., Inc. v. State
219 N.W.2d 922 (Supreme Court of Minnesota, 1974)
VINNELL CORPORATION v. State
512 P.2d 71 (New Mexico Supreme Court, 1973)
Megarry Brothers, Inc. v. State
188 N.W.2d 919 (Supreme Court of Minnesota, 1971)
L. J. McNulty, Inc. v. Village of Newport
187 N.W.2d 616 (Supreme Court of Minnesota, 1971)
Healy v. Brewster
251 Cal. App. 2d 541 (California Court of Appeal, 1967)
Robertson Lumber Co. v. Stephen Farmers Cooperative Elevator Co.
143 N.W.2d 622 (Supreme Court of Minnesota, 1966)
M. L. Shalloo, Inc. v. Ricciardi & Sons Construction, Inc.
205 N.E.2d 239 (Massachusetts Supreme Judicial Court, 1965)
Souza & McCue Construction Co. v. Superior Court
370 P.2d 338 (California Supreme Court, 1962)
Majerus v. Guelsow
113 N.W.2d 450 (Supreme Court of Minnesota, 1962)
In Re Appeal of Roberts Construction Company
111 N.W.2d 767 (Nebraska Supreme Court, 1961)
Clark v. City of Humansville, Missouri
348 S.W.2d 369 (Missouri Court of Appeals, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
91 N.W.2d 713, 253 Minn. 295, 1958 Minn. LEXIS 674, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mccree-company-v-state-minn-1958.